Project |
JJM : CWSS to Pulimath, Nagaroor and Karavaram Panchayaths, Phase II - Supplying, conveying, laying, testing and commissioning of distribution network and providing 15438 Nos FHTCs |
Project Code |
TVMJJM02229779P1 |
Type |
Package |
Main Project |
JJM : CWSS to Pulimath, Nagaroor and Karavaram Panchayaths, Phase II
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
This project envisages providing distribution network from OHSRs and sump proposed for the scheme in Phase-I and providing FHTCs (15348 Nos.) to households of all the three panchayaths
- Pulimath, Nagaroor and Karavaram under Jala Jeevan Mission. |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Trivandrum Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
877910000 |
TS Number |
TS/2022-2023/2021/19469 |
Technical specification |
This project envisages providing distribution network from OHSRs and sump proposed for the scheme in Phase-I and providing FHTCs (15348 Nos.) to households of all the three panchayaths
- Pulimath, Nagaroor and Karavaram under Jala Jeevan Mission. |
Contractor |
M/s. Standard Infratech India Pvt Ltd (Mob: 9447057957) |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
11/04/2022 |
Scheduled date of Completion as per agreement |
04 May 2024 |
Expected date of Completion |
04/05/2024 |
Processing Dates
TS Date |
11 Apr 2022 |
Estimate Approval |
12 Apr 2022 |
NIT Approval |
13 Apr 2022 |
Tender Closing |
09 May 2022 |
Technichal Pre-Qualification |
10 May 2022 |
Price bid opening |
02 Nov 2022 |
Approval Dates
Workorder Date |
05 Nov 2022 |
NA |
29 Dec 2022 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Thiruvananthapuram Project AE3 |
Date: 27/06/2024 |
Work in progress | 37% Completed
Leak rectification works ongoing. No other works scheduled by the contractor due to rain.
Attached images
Thiruvananthapuram Project AE3 |
Date: 24/06/2024 |
Work in progress | 37% Completed
Interconnection works as well as pressure test works progressing.
Attached images