JJM : CWSS to Pulimath, Nagaroor and Karavaram Panchayaths, Phase II - Supplying, conveying, laying, testing and commissioning of distribution network and providing 15438 Nos FHTCs

Project JJM : CWSS to Pulimath, Nagaroor and Karavaram Panchayaths, Phase II - Supplying, conveying, laying, testing and commissioning of distribution network and providing 15438 Nos FHTCs
Project Code TVMJJM02229779P1
Type Package
Main Project JJM : CWSS to Pulimath, Nagaroor and Karavaram Panchayaths, Phase II
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description This project envisages providing distribution network from OHSRs and sump proposed for the scheme in Phase-I and providing FHTCs (15348 Nos.) to households of all the three panchayaths - Pulimath, Nagaroor and Karavaram under Jala Jeevan Mission.
Status On-going
District Thiruvananthapuram
Executing Office Trivandrum Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 877910000
TS Number TS/2022-2023/2021/19469
Technical specification This project envisages providing distribution network from OHSRs and sump proposed for the scheme in Phase-I and providing FHTCs (15348 Nos.) to households of all the three panchayaths - Pulimath, Nagaroor and Karavaram under Jala Jeevan Mission.
Contractor M/s. Standard Infratech India Pvt Ltd (Mob: 9447057957)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 11/04/2022
Scheduled date of Completion as per agreement 04 May 2024
Expected date of Completion 04/05/2024

Processing Dates

TS Date 11 Apr 2022
Estimate Approval 12 Apr 2022
NIT Approval 13 Apr 2022
Tender Closing 09 May 2022
Technichal Pre-Qualification 10 May 2022
Price bid opening 02 Nov 2022

Approval Dates

Workorder Date 05 Nov 2022
NA 29 Dec 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thiruvananthapuram Project AE3
Date: 27/06/2024

Work in progress | 37% Completed

Leak rectification works ongoing. No other works scheduled by the contractor due to rain.

Attached images

img img

Thiruvananthapuram Project AE3
Date: 24/06/2024

Work in progress | 37% Completed

Interconnection works as well as pressure test works progressing.

Attached images

img img img img