Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Palakkad Proj AE 3
Date: 28/06/2024

Work in progress | 5% Completed

Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 498M. Total laid-552M

Palakkad Proj AE 3
Date: 27/06/2024

Work in progress | 5% Completed

Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 498M. Total laid-552M

Palakkad Proj AE 3
Date: 26/06/2024

Work in progress | 5% Completed

Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 402M. Total laid-456M

Palakkad Proj AE 3
Date: 25/06/2024

Work in progress | 5% Completed

Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 282M. Total laid-336M

Palakkad Proj AE 3
Date: 22/06/2024

Work in progress | 5% Completed

Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 102M. Total laid-156M

Palakkad Proj AE 3
Date: 20/06/2024

Work in progress | 4% Completed

Laying started.90mm PN 8 - 54M laid.

Palakkad Project Dn EE
Date: 25/05/2024

Work in progress | 4% Completed

Laying started.90mm PN 8 - 54M laid.

Palakkad Proj AE 3
Date: 18/05/2024

Work in progress | 4% Completed

Laying started.90mm PN 8 - 54M laid

Palakkad Proj AE 3
Date: 13/05/2024

Work in progress | 4% Completed

Laying started.90mm PN 8 - 54M laid

Palakkad Proj AE 3
Date: 09/05/2024

Work in progress | 4% Completed

Laying started.90mm PN 8 - 54M laid

Palakkad Proj AE 3
Date: 06/05/2024

Work in progress | 3% Completed

Full pipe supplied by the contractor for 11km's.

Palakkad Proj AE 3
Date: 01/05/2024

Work in progress | 1% Completed

Agreement executed on 22nd January 2024