Palakkad Proj AE 3 |
Date: 28/06/2024 |
Work in progress | 5% Completed
Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 498M. Total laid-552M
Palakkad Proj AE 3 |
Date: 27/06/2024 |
Work in progress | 5% Completed
Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 498M. Total laid-552M
Palakkad Proj AE 3 |
Date: 26/06/2024 |
Work in progress | 5% Completed
Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 402M. Total laid-456M
Palakkad Proj AE 3 |
Date: 25/06/2024 |
Work in progress | 5% Completed
Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 282M. Total laid-336M
Palakkad Proj AE 3 |
Date: 22/06/2024 |
Work in progress | 5% Completed
Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 102M. Total laid-156M
Palakkad Proj AE 3 |
Date: 20/06/2024 |
Work in progress | 4% Completed
Laying started.90mm PN 8 - 54M laid.
Palakkad Project Dn EE |
Date: 25/05/2024 |
Work in progress | 4% Completed
Laying started.90mm PN 8 - 54M laid.
Palakkad Proj AE 3 |
Date: 18/05/2024 |
Work in progress | 4% Completed
Laying started.90mm PN 8 - 54M laid
Palakkad Proj AE 3 |
Date: 13/05/2024 |
Work in progress | 4% Completed
Laying started.90mm PN 8 - 54M laid
Palakkad Proj AE 3 |
Date: 09/05/2024 |
Work in progress | 4% Completed
Laying started.90mm PN 8 - 54M laid
Palakkad Proj AE 3 |
Date: 06/05/2024 |
Work in progress | 3% Completed
Full pipe supplied by the contractor for 11km's.
Palakkad Proj AE 3 |
Date: 01/05/2024 |
Work in progress | 1% Completed
Agreement executed on 22nd January 2024