Deposit work - PWD : RWSS to Udumbanchola & RWSS to Rajakkad-Rajakumari - Shifting of water supply pipelines in the stretch between Udumbanchola and Chithrapuram road due to road development work by KIIFB

Project Deposit work - PWD : RWSS to Udumbanchola & RWSS to Rajakkad-Rajakumari - Shifting of water supply pipelines in the stretch between Udumbanchola and Chithrapuram road due to road development work by KIIFB
Project Code IDKDEPO11218784P1
Type Package
Main Project Deposit work - PWD : RWSS to Udumbanchola & RWSS to Rajakkad-Rajakumari - Shifting of water supply pipelines in the stretch between Udumbanchola and Chithrapuram road due to road development work by KIIFB
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work - PWD : RWSS to Udumbanchola & RWSS to Rajakkad-Rajakumari - Shifting of water supply pipelines in the stretch between Udumbanchola and Chithrapuram road due to road development work by KIIFB
Status On-going
District Idukki
Executing Office Peerumedu Sn
Agreement Number
Agreement Date
TS Amount (Rs) 3240000
TS Number 16415/2021-2022
Technical specification 90 mm PVC and 80 mm GI pipe laying work

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 06/02/2022
Scheduled date of Completion as per agreement 17 Jul 2022
Expected date of Completion 31/08/2022

Processing Dates

TS Date 28 Dec 2021
Estimate Approval 28 Dec 2021
NIT Approval 28 Dec 2021
Tender Closing 28 Dec 2021
Technichal Pre-Qualification 28 Dec 2021
Price bid opening 28 Dec 2021

Approval Dates

Workorder Date 28 Dec 2021
NA 28 Dec 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Nedumkandam Sn AE
Date: 04/01/2024

Work has been completed | 100% Completed

Work completed. Pipeline should be brought in live along with the ongoing JJM works in Rajakkad Panchayath..

Thodupuzha PH Dn EE
Date: 01/01/2024

Work in progress | 97% Completed

Pipe laying towards NR City to Punna City completed.