| Nedumkandam Sn AE |
| Date: 04/01/2024 |
Work has been completed | 100% Completed
Work completed. Pipeline should be brought in live along with the ongoing JJM works in Rajakkad Panchayath.
| Thodupuzha PH Dn EE |
| Date: 01/01/2024 |
Work in progress | 97% Completed
Pipe laying towards NR City to Punna City completed
| Nedumkandam Sn AE |
| Date: 05/12/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City to Punna City completed
| Nedumkandam Sn AE |
| Date: 29/11/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City to Punna City completed
| Nedumkandam Sn AE |
| Date: 27/11/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City to Punna City completed
| Nedumkandam Sn AE |
| Date: 25/11/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City to Punna City completed
| Nedumkandam Sn AE |
| Date: 23/11/2023 |
Work in progress | 97% Completed
Project Division Kattappana has already been proposed a project there, Hence this work cant start till this date View all update
| Nedumkandam Sn AE |
| Date: 20/11/2023 |
Work in progress | 97% Completed
Project Division Kattappana has already been proposed a project there, Hence this work cant start till this date View all update
| Nedumkandam Sn AE |
| Date: 17/11/2023 |
Work in progress | 97% Completed
Project Division Kattappana has already been proposed a project there, Hence this work cant start till this date View all update
| Nedumkandam Sn AE |
| Date: 14/11/2023 |
Work in progress | 97% Completed
Project Division Kattappana has already been proposed a project there, Hence this work cant start till this date View all update
| Nedumkandam Sn AE |
| Date: 13/11/2023 |
Work in progress | 97% Completed
Project Division Kattappana has already been proposed a project there, Hence this work cant start till this date View all update
| Nedumkandam Sn AE |
| Date: 10/11/2023 |
Work in progress | 97% Completed
Project Division Kattappana has already been proposed a project there, Hence this work cant start till this date View all updates
| Nedumkandam Sn AE |
| Date: 08/11/2023 |
Work in progress | 97% Completed
Project Division Kattappana has already been proposed a project there, Hence this work cant start till this date View all updates
| Nedumkandam Sn AE |
| Date: 07/11/2023 |
Work in progress | 97% Completed
Project Division Kattappana has already been proposed a project there, Hence this work cant start till this date View all updates
| Nedumkandam Sn AE |
| Date: 03/11/2023 |
Work in progress | 97% Completed
Project Division Kattappana has already been proposed a project there, Hence this work cant start till this date View all updates
| Nedumkandam Sn AE |
| Date: 30/10/2023 |
Work in progress | 97% Completed
Project Division Kattappana has already been proposed a project there, Hence this work cant start till this date View all updates
| Nedumkandam Sn AE |
| Date: 28/10/2023 |
Work in progress | 97% Completed
Project Division Kattappana has already been proposed a project there, Hence this work cant start till this date View all updates
| Nedumkandam Sn AE |
| Date: 10/10/2023 |
Work in progress | 97% Completed
Work in progress | 97% Completed | 29/09/2023
| Nedumkandam Sn AE |
| Date: 30/09/2023 |
Work in progress | 97% Completed
Work in progress | 97% Completed | 29/09/2023
| Nedumkandam Sn AE |
| Date: 29/09/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 27/09/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 25/09/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 23/09/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 14/09/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 07/09/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 04/09/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 01/09/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 26/08/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 23/08/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 14/08/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 11/08/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 09/08/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 07/08/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 05/08/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 02/08/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 29/07/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 27/07/2023 |
Work in progress | 97% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 24/07/2023 |
Work in progress | 96% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 20/07/2023 |
Work in progress | 96% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 11/07/2023 |
Work in progress | 96% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 10/07/2023 |
Work in progress | 96% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 05/07/2023 |
Work in progress | 96% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 30/06/2023 |
Work in progress | 95% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 21/06/2023 |
Work in progress | 95% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 15/06/2023 |
Work in progress | 94% Completed
Pipe laying towards NR City completed
| Nedumkandam Sn AE |
| Date: 12/06/2023 |
Work in progress | 92% Completed
Pipe laying towards NR city town
| Nedumkandam Sn AE |
| Date: 08/06/2023 |
Work in progress | 90% Completed
Work in progress near NR city school
| Nedumkandam Sn AE |
| Date: 01/06/2023 |
Work in progress | 82% Completed
NR City - Punna City route 1400 m of 90 mm PVC pipe laid from the last point. Other portions have land issues. That not solved and alignment not got from KRFB till now due to land issues.
| Nedumkandam Sn AE |
| Date: 20/05/2023 |
Work in progress | 82% Completed
NR City - Punna City route 1400 m of 90 mm PVC pipe laid from the last point. Other portions have land issues. That not solved and alignment not got from KRFB till now due to land issues.
| Nedumkandam Sn AE |
| Date: 17/05/2023 |
Work in progress | 82% Completed
NR City - Punna City route 1400 m of 90 mm PVC pipe laid from the last point. Other portions have land issues. That not solved and alignment not got from KRFB till now due to land issues.
| Nedumkandam Sn AE |
| Date: 12/05/2023 |
Work in progress | 82% Completed
NR City - Punna City route 1400 m of 90 mm PVC pipe laid from the last point. Other portions have land issues. That not solved and alignment not got from KRFB till now due to land issues.
| Nedumkandam Sn AE |
| Date: 06/05/2023 |
Work in progress | 82% Completed
NR City - Punna City route 1400 m of 90 mm PVC pipe laid from the last point. Other portions have land issues. That not solved and alignment not got from KRFB till now due to land issues.
| Nedumkandam Sn AE |
| Date: 29/04/2023 |
Work in progress | 82% Completed
NR City - Punna City route 1400 m of 90 mm PVC pipe laid from the last point. Other portions have land issues. That not solved and alignment not got from KRFB till now due to land issues.
| Nedumkandam Sn AE |
| Date: 22/04/2023 |
Work in progress | 82% Completed
NR City - Punna City route 1400 m of 90 mm PVC pipe laid from the last point. Other portions have land issues. That not solved and alignment not got from KRFB till now due to land issues.
| Nedumkandam Sn AE |
| Date: 11/04/2023 |
Work in progress | 82% Completed
NR City - Punna City route 1400 m of 90 mm PVC pipe laid from the last point. Other portions have land issues. That not solved and alignment not got from KRFB till now due to land issues.
| Nedumkandam Sn AE |
| Date: 30/03/2023 |
Work in progress | 82% Completed
NR City - Punna City route 1400 m of 90 mm PVC pipe laid from the last point. Other portions have land issues. That not solved and alignment not got from KRFB till now due to land issues.
| Nedumkandam Sn AE |
| Date: 23/03/2023 |
Work in progress | 82% Completed
NR City - Punna City route 1400 m of 90 mm PVC pipe laid from the last point. Other portions have land issues. That not solved and alignment not got from KRFB till now due to land issues.
| Nedumkandam Sn AE |
| Date: 17/03/2023 |
Work in progress | 82% Completed
NR City - Punna City route 1400 m of 90 mm PVC pipe laid from the last point. Other portions have land issues. That not solved and alignment not got from KRFB till now due to land issues.
| Nedumkandam Sn AE |
| Date: 09/03/2023 |
Work in progress | 82% Completed
NR City - Punna City route 1400 m of 90 mm PVC pipe laid from the last point. Other portions have land issues. That not solved and alignment not got from KRFB till now due to land issues.
| Nedumkandam Sn AE |
| Date: 03/03/2023 |
Work in progress | 82% Completed
NR City - Punna City route 1400 m of 90 mm PVC pipe laid from the last point. Other portions have land issues. That not solved and alignment not got from KRFB till now due to land issues.
| Nedumkandam Sn AE |
| Date: 20/02/2023 |
Work in progress | 82% Completed
NR City - Punna City route 1400 m of 90 mm PVC pipe laid from the last point. Other portions have land issues. That not solved and alignment not got from KRFB till now due to land issues.
| Nedumkandam Sn AE |
| Date: 15/02/2023 |
Work in progress | 82% Completed
NR City - Punna City route 1400 m of 90 mm PVC pipe laid from the last point. Other portions have land issues. That not solved and alignment not got from KRFB till now due to land issues.
| Nedumkandam Sn AE |
| Date: 10/02/2023 |
Work in progress | 65% Completed
NR City - Punna City route 1050 m of 90 mm PVC pipe laid from the last point. Other portions have land issues. That not solved and alignment not got from KRFB till now due to land issues.
| Nedumkandam Sn AE |
| Date: 26/01/2023 |
Work in progress | 40% Completed
NR City - Punna City route 450 m of 90 mm PVC pipe laid from the last point. Other portions have land issues. That not solved and alignment not got from KRFB till now.
| Nedumkandam Sn AE |
| Date: 07/01/2023 |
Work in progress | 40% Completed
NR City - Punna City route 450 m of 90 mm PVC pipe laid from the last point. Other portions have land issues. That not solved and alignment not got from KRFB till now.
| Nedumkandam Sn AE |
| Date: 29/12/2022 |
Work in progress | 40% Completed
NR City - Punna City route 450 m of 90 mm PVC pipe laid from the last point. Other portions have land issues. That not solved and alignment not got from KRFB till now.
| Nedumkandam Sn AE |
| Date: 11/12/2022 |
Work in progress | 35% Completed
Final alignment not given by KRFB Muvattupuzha in the strech NR City - Punna city
| Nedumkandam Sn AE |
| Date: 23/11/2022 |
Work in progress | 35% Completed
NR City - Punna City route 360 m of 90 mm PVC pipe laid
| Nedumkandam Sn AE |
| Date: 19/11/2022 |
Work in progress | 35% Completed
NR City - Punna City route 360 m of 90 mm PVC pipe laid
| Nedumkandam Sn AE |
| Date: 13/09/2022 |
Work in progress | 30% Completed
Udumbanchola reach completed
| Thodupuzha PH Dn EE |
| Date: 01/09/2022 |
Work in progress | 30% Completed
Udumbanchola reach completed, joint inspection with EE KRFB proposed on 2 nd week of Septenber
| Peerumedu Sn AE |
| Date: 25/08/2022 |
Work has started | 0% Completed
bill of pipe supply has submitted
| Peerumedu Sn AE |
| Date: 20/08/2022 |
Work has started | 0% Completed
bill of pipe supply has submitted
| Peerumedu Sn AE |
| Date: 16/08/2022 |
Work has started | 0% Completed
IDKDEPO11218784
| Thodupuzha PH Dn EE |
| Date: 05/08/2022 |
Work has started | 0% Completed
bill of pipe supply has submitted
| Thodupuzha PH Dn EE |
| Date: 01/08/2022 |
Work has started | 0% Completed
bill of pipe supply has submitted
| Thodupuzha PH Dn EE |
| Date: 19/07/2022 |
Work has started | 0% Completed
bill of pipe supply has submitted
| Thodupuzha PH Dn EE |
| Date: 12/07/2022 |
Work has started | 0% Completed
bill of pipe supply has submitted
| Thodupuzha PH Dn EE |
| Date: 08/07/2022 |
Work in progress | 0% Completed
1st part of bill of pipe supply has submitted
| Thodupuzha PH Dn EE |
| Date: 17/06/2022 |
Work has started | 0% Completed
Agreement executed on 31.01.2022
| Thodupuzha PH Dn EE |
| Date: 05/05/2022 |
Work in progress | 2% Completed
Order issued for Pipes
| Thodupuzha PH Dn EE |
| Date: 25/03/2022 |
Work in progress | 1% Completed
Order issued for Pipes
| Thodupuzha PH Dn EE |
| Date: 12/03/2022 |
Work has started | 0% Completed
Work to be e tendered