Deposit work - PWD : RWSS to Udumbanchola & RWSS to Rajakkad-Rajakumari - Shifting of water supply pipelines in the stretch between Udumbanchola and Chithrapuram road due to road development work by KIIFB

Project Deposit work - PWD : RWSS to Udumbanchola & RWSS to Rajakkad-Rajakumari - Shifting of water supply pipelines in the stretch between Udumbanchola and Chithrapuram road due to road development work by KIIFB
Project Code IDKDEPO11218784
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work - PWD : RWSS to Udumbanchola & RWSS to Rajakkad-Rajakumari - Shifting of water supply pipelines in the stretch between Udumbanchola and Chithrapuram road due to road development work by KIIFB
Status On-going
District Idukki
Executing Office Nedumkandam Sn
AS Amount (Rs) 9917259
AS Number KRFB/PMU/MVPA/IDK/UDMCLA-CPHM/2021
TS Amount (Rs) 3240000
TS Number 16415/2021-2022
Total Bill Submitted (Rs) 740587
Total Bill Paid (Rs) 740587
Population Benefitted 700
Capacity in MLD 0.05
Actual Project Completion Date Date is not specified
Coverage Udumbanchola town areas
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Deposit work - PWD : RWSS to Udumbanchola & RWSS to Rajakkad-Rajakumari - Shifting of water supply pipelines in the stretch between Udumbanchola and Chithrapuram road due to road development work by KIIFB Peerumedu Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Jan 2024 Pipe laying towards NR City to Punna City completed Thodupuzha PH Dn EE
01 Sep 2022 Udumbaanchola reach completed, Joint inspection of NR city reach with EE KRFB proposed on the secocd week of September Thodupuzha PH Dn EE
29 Aug 2022 bill of pipe supply has submitted Peerumedu Sn AE
25 Aug 2022 bill of pipe supply has submitted Peerumedu Sn AE
20 Aug 2022 bill of pipe supply has submitted Peerumedu Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 06/02/2022
Scheduled date of Completion of the Project 17 Jul 2022
Expected date of Completion 31/08/2022

Processing Dates

AS Date 22 Nov 2021
TS Date 28 Dec 2021

Other details

Project Officers View