JJM - Kasaragod District - Mogral; Puthur Panchayath- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 3(Zone 9)-Laying Distribution system and providing FHTCs- from OHSR at Periyadukka.

Project JJM - Kasaragod District - Mogral; Puthur Panchayath- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 3(Zone 9)-Laying Distribution system and providing FHTCs- from OHSR at Periyadukka.
Project Code KGDJJM092110759P1
Type Package
Main Project JJM Kasaragod district - Mogral Puthur Panchayath - WSS to Chengala, Muliyar, Mogral Puthur and Madhur Panchayaths - Reach 3 (Zone 9) - Laying Distribution and Providing FHTCs - from OHSR at Periyadukka
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Mogral; Puthur Panchayath- WSS to Chengala, Muliyar , Madhur and Mogral Puthur Panchayaths - Reach 3(Zone 9)-Laying Distribution system and providing FHTCs- from OHSR at Periyadukka.
Status On-going
District Kasaragod
Executing Office Project Division Kannur ( KGD)
Agreement Number
Agreement Date
TS Amount (Rs) 80000000
TS Number TS/2021-2022/2021/40448
Technical specification Total FHTCs to be provided 1900 No

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 11/04/2022
Scheduled date of Completion as per agreement 01 Sep 2022
Expected date of Completion 01/09/2022

Processing Dates

TS Date 10 Dec 2021
Estimate Approval 10 Dec 2021
NIT Approval 15 Dec 2021
Tender Closing 17 Jan 2022
Technichal Pre-Qualification 25 Jan 2022
Price bid opening 01 Feb 2022

Approval Dates

Workorder Date 02 Mar 2022
NA 17 Mar 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kanhangad Proj Dn AE - 2
Date: 28/06/2024

Work in progress | 60% Completed

pipeline work in progress. total pipe tobe laid 28 km, total pipe laid 21km. 870 Nos of HTC given, 723 HTC billed.Dt. of completion 30.04.2024 EOT requested up to 30.10.2024..

Kanhangad Proj Dn AE - 2
Date: 26/06/2024

Work in progress | 60% Completed

pipeline work in progress. total pipe tobe laid 28 km, total pipe laid 21km. 870 Nos of HTC given, 723 HTC billed.Dt. of completion 30.04.2024 EOT requested up to 30.10.2024..