Project | JJM- WSS to Ambalappara Panchayaths – Augmentation and gap filling by using GI Pipe of existing distribution network and LSGD Road Restoration works |
---|---|
Project Code | PKDJJM102316050P1 |
Type | Package |
Main Project | JJM- WSS to Ambalappara Panchayaths – Augmentation and gap filling by using GI Pipe of existing distribution network and LSGD Road Restoration works |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM- WSS to Ambalappara Panchayaths – Augmentation and gap filling by using GI Pipe of existing distribution network and LSGD Road Restoration works |
Status | On-going |
District | Palakkad |
Executing Office | Palakkad Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 58800000 |
TS Number | WRD/KWA-CE(NR)/EST-TS/25720/2023 |
Technical specification | Augmentation and gap filling by using GI Pipe of existing distribution network and LSGD Road Restoration works |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 20/01/2024 |
---|---|
Scheduled date of Completion as per agreement | 19 Sep 2024 |
Expected date of Completion | 19/09/2024 |
TS Date | 13 Dec 2023 |
---|---|
Estimate Approval | 13 Dec 2023 |
Tender Closing | 27 Dec 2023 |
Price bid opening | 30 Dec 2023 |
Workorder Date | 19 Jan 2024 |
---|---|
NA | 22 Feb 2024 |
Palakkad Proj Dn AE 4 |
Date: 27/06/2024 |
Work in progress | 20% Completed
PVC Laying details Today layed length 90 mm 8 kg = nil Total layed length =2828 M GI laying details 80 mm GI = 27 M Total layed length= 652 M.
Palakkad Proj Dn AE 4 |
Date: 19/06/2024 |
Work in progress | 18% Completed
PVC Laying details Today layed length 90 mm 8 kg = nil Total layed length =2828 M GI laying details 80 mm GI = 24 M Total layed length= 422 M.