Palakkad Proj Dn AE 4 |
Date: 03/07/2024 |
Work in progress | 26% Completed
4.816/18kms layed so far.PVC Laying details Today layed length 90 mm 8 kg = 120 M Total layed length =3703 M GI laying details 80 mm GI = 114 M Total layed length= 1113 M
Palakkad Proj Dn AE 4 |
Date: 02/07/2024 |
Work in progress | 25% Completed
4.816/18kms layed so far.PVC Laying details Today layed length 90 mm 8 kg = 120 M Total layed length =3703 M GI laying details 80 mm GI = 114 M Total layed length= 1113 M
Palakkad Proj Dn AE 4 |
Date: 01/07/2024 |
Work in progress | 24% Completed
4.816/18kms layed so far.PVC Laying details Today layed length 90 mm 8 kg = 120 M Total layed length =3703 M GI laying details 80 mm GI = 114 M Total layed length= 1113 M
Palakkad Proj Dn AE 4 |
Date: 29/06/2024 |
Work in progress | 23% Completed
4.816/18kms layed so far.PVC Laying details Today layed length 90 mm 8 kg = 120 M Total layed length =3703 M GI laying details 80 mm GI = 114 M Total layed length= 1113 M
Palakkad Proj Dn AE 4 |
Date: 28/06/2024 |
Work in progress | 21% Completed
4.816/18kms layed so far.PVC Laying details Today layed length 90 mm 8 kg = 120 M Total layed length =3703 M GI laying details 80 mm GI = 114 M Total layed length= 1113 M
Palakkad Proj Dn AE 4 |
Date: 27/06/2024 |
Work in progress | 20% Completed
PVC Laying details Today layed length 90 mm 8 kg = nil Total layed length =2828 M GI laying details 80 mm GI = 27 M Total layed length= 652 M
Palakkad Proj Dn AE 4 |
Date: 19/06/2024 |
Work in progress | 18% Completed
PVC Laying details Today layed length 90 mm 8 kg = nil Total layed length =2828 M GI laying details 80 mm GI = 24 M Total layed length= 422 M
Palakkad Proj Dn AE 4 |
Date: 17/06/2024 |
Work in progress | 16% Completed
PVC Laying details Today layed length 90 mm 8 kg = 78M Total layed length =2828 M GI laying details 80 mm GI = 30 M Total layed length= 308 M
Palakkad Proj Dn AE 4 |
Date: 06/05/2024 |
Work in progress | 14% Completed
PVC Laying details Today layed length 90 mm 8 kg = 150 M Total layed length =2216M GI laying details 80 mm GI = nil Total layed length= 278 M
Palakkad Proj Dn AE 4 |
Date: 29/04/2024 |
Work in progress | 12% Completed
PVC Laying details Today laid length 90 mm 8 kg = 68 M Total layed length = 1363M GI laying details Today - Nil 80 mm GI Total layed length= 138 M
Palakkad Proj Dn AE 4 |
Date: 22/04/2024 |
Work in progress | 10% Completed
PVC Laying details Today laid length 90 mm 8 kg = 68 M Total layed length = 1363M GI laying details Today - Nil 80 mm GI Total layed length= 138 M
Palakkad Proj Dn AE 4 |
Date: 15/04/2024 |
Work in progress | 8% Completed
PVC Laying details, Today laid length 90 mm 8 kg = 36 M Total layed length = 691 M GI Work has not started yet
Palakkad Proj Dn AE 4 |
Date: 08/04/2024 |
Work in progress | 5% Completed
PVC Laying details Today laid length 90 mm 8 kg = 84 M Total layed length = 210 M GI Work has not started yet
Palakkad Proj Dn AE 4 |
Date: 05/04/2024 |
Work in progress | 5% Completed
PVC Laying details Cumulative length = 0 Today laid length 90 mm 8 kg = 24 M GI Work has not started yet
Palakkad Proj Dn AE 4 |
Date: 01/04/2024 |
Work in progress | 4% Completed
Pipe supplied.90mm 8kg PVC 15000m completed.
Palakkad Proj Dn AE 4 |
Date: 03/03/2024 |
Work in progress | 3% Completed
Site hand overed to contractor.
Palakkad Proj Dn AE 4 |
Date: 22/02/2024 |
Work in progress | 2% Completed
Agreement executed on this date - 41/2023-24/SE/PHC/PKD
Palakkad Proj Dn AE 4 |
Date: 19/01/2024 |
Work in progress | 1% Completed
WORK ORDER ISSUED - KWA/ PHC/PKD/JJM/ Ambalapara/2023-24