Palakkad Proj Dn AE 4
Date: 03/07/2024

Work in progress | 26% Completed

4.816/18kms layed so far.PVC Laying details Today layed length 90 mm 8 kg = 120 M Total layed length =3703 M GI laying details 80 mm GI = 114 M Total layed length= 1113 M

Palakkad Proj Dn AE 4
Date: 02/07/2024

Work in progress | 25% Completed

4.816/18kms layed so far.PVC Laying details Today layed length 90 mm 8 kg = 120 M Total layed length =3703 M GI laying details 80 mm GI = 114 M Total layed length= 1113 M

Palakkad Proj Dn AE 4
Date: 01/07/2024

Work in progress | 24% Completed

4.816/18kms layed so far.PVC Laying details Today layed length 90 mm 8 kg = 120 M Total layed length =3703 M GI laying details 80 mm GI = 114 M Total layed length= 1113 M

Palakkad Proj Dn AE 4
Date: 29/06/2024

Work in progress | 23% Completed

4.816/18kms layed so far.PVC Laying details Today layed length 90 mm 8 kg = 120 M Total layed length =3703 M GI laying details 80 mm GI = 114 M Total layed length= 1113 M

Palakkad Proj Dn AE 4
Date: 28/06/2024

Work in progress | 21% Completed

4.816/18kms layed so far.PVC Laying details Today layed length 90 mm 8 kg = 120 M Total layed length =3703 M GI laying details 80 mm GI = 114 M Total layed length= 1113 M

Palakkad Proj Dn AE 4
Date: 27/06/2024

Work in progress | 20% Completed

PVC Laying details Today layed length 90 mm 8 kg = nil Total layed length =2828 M GI laying details 80 mm GI = 27 M Total layed length= 652 M

Palakkad Proj Dn AE 4
Date: 19/06/2024

Work in progress | 18% Completed

PVC Laying details Today layed length 90 mm 8 kg = nil Total layed length =2828 M GI laying details 80 mm GI = 24 M Total layed length= 422 M

Palakkad Proj Dn AE 4
Date: 17/06/2024

Work in progress | 16% Completed

PVC Laying details Today layed length 90 mm 8 kg = 78M Total layed length =2828 M GI laying details 80 mm GI = 30 M Total layed length= 308 M

Palakkad Proj Dn AE 4
Date: 06/05/2024

Work in progress | 14% Completed

PVC Laying details Today layed length 90 mm 8 kg = 150 M Total layed length =2216M GI laying details 80 mm GI = nil Total layed length= 278 M

Palakkad Proj Dn AE 4
Date: 29/04/2024

Work in progress | 12% Completed

PVC Laying details Today laid length 90 mm 8 kg = 68 M Total layed length = 1363M GI laying details Today - Nil 80 mm GI Total layed length= 138 M

Palakkad Proj Dn AE 4
Date: 22/04/2024

Work in progress | 10% Completed

PVC Laying details Today laid length 90 mm 8 kg = 68 M Total layed length = 1363M GI laying details Today - Nil 80 mm GI Total layed length= 138 M

Palakkad Proj Dn AE 4
Date: 15/04/2024

Work in progress | 8% Completed

PVC Laying details, Today laid length 90 mm 8 kg = 36 M Total layed length = 691 M GI Work has not started yet

Palakkad Proj Dn AE 4
Date: 08/04/2024

Work in progress | 5% Completed

PVC Laying details Today laid length 90 mm 8 kg = 84 M Total layed length = 210 M GI Work has not started yet

Palakkad Proj Dn AE 4
Date: 05/04/2024

Work in progress | 5% Completed

PVC Laying details Cumulative length = 0 Today laid length 90 mm 8 kg = 24 M GI Work has not started yet

Palakkad Proj Dn AE 4
Date: 01/04/2024

Work in progress | 4% Completed

Pipe supplied.90mm 8kg PVC 15000m completed.

Palakkad Proj Dn AE 4
Date: 03/03/2024

Work in progress | 3% Completed

Site hand overed to contractor.

Palakkad Proj Dn AE 4
Date: 22/02/2024

Work in progress | 2% Completed

Agreement executed on this date - 41/2023-24/SE/PHC/PKD

Palakkad Proj Dn AE 4
Date: 19/01/2024

Work in progress | 1% Completed

WORK ORDER ISSUED - KWA/ PHC/PKD/JJM/ Ambalapara/2023-24