JJM- WSS to Ambalappara Panchayaths – Augmentation and gap filling by using GI Pipe of existing distribution network and LSGD Road Restoration works

Project JJM- WSS to Ambalappara Panchayaths – Augmentation and gap filling by using GI Pipe of existing distribution network and LSGD Road Restoration works
Project Code PKDJJM102316050
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Augmentation and gap filling by using GI Pipe of existing distribution network and LSGD Road Restoration works
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
AS Amount (Rs) 525800000
AS Number G.O.(Rt)No.897/2023/WRD
TS Amount (Rs) 58800000
TS Number WRD/KWA-CE(NR)/EST-TS/25720/2023
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 25000
Capacity in MLD 6.50
Actual Project Completion Date 19 Sep 2024
Coverage Ambalappara Panchayath

Packages

No. Project Name Location View
1 JJM- WSS to Ambalappara Panchayaths – Augmentation and gap filling by using GI Pipe of existing distribution network and LSGD Road Restoration works Project Division Palakkad

Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Jun 2024 4.816/18kms layed so far.PVC Laying details Today layed length 90 mm 8 kg = 120 M Total layed length =3703 M GI laying details 80 mm GI = 114 M Total layed length= 1113 M Palakkad Proj Dn AE 4
25 Jun 2024 4.816/18kms layed so far.PVC Laying details Today layed length 90 mm 8 kg = 120 M Total layed length =3703 M GI laying details 80 mm GI = 114 M Total layed length= 1113 M Palakkad Proj Dn AE 4
24 Jun 2024 4.816/18kms layed so far.PVC Laying details Today layed length 90 mm 8 kg = 120 M Total layed length =3703 M GI laying details 80 mm GI = 114 M Total layed length= 1113 M Palakkad Proj Dn AE 4
22 Jun 2024 PVC Laying details Today layed length 90 mm 8 kg = 120 M Total layed length =3703 M GI laying details 80 mm GI = 114 M Total layed length= 1113 M Palakkad Proj Dn AE 4
20 Jun 2024 PVC Laying detailsToday layed length90 mm 8 kg = 3 MTotal layed length =3478 MGI laying details80 mm GI = 66 MTotal layed length= 921 M Palakkad Proj Dn AE 4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 03/03/2024
Scheduled date of Completion of the Project 02 Nov 2024
Expected date of Completion 02/11/2024

Processing Dates

AS Date 26 Oct 2023
TS Date 13 Dec 2023

Other details

Project Officers View