Project | Jal Jeevan Mission - Providing Functional Household Tap Connections at Pattazhy Panchayath in Kollam District. |
---|---|
Project Code | KLMJJM08203111P2 |
Type | Package |
Main Project | Jal Jeevan Mission - Providing Functional Household Tap Connections at Pattazhy Panchayath in Kollam District. |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission - Providing Functional Household Tap Connections at Pattazhy Panchayath in Kollam District. |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 27760000 |
TS Number | TS/2020-21/2020/16264 |
Technical specification | house connection as per approved drawing |
Contractor | M/s HITECH CONSTRUCTION GROUP (Mob: 9656737227) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
13 Apr 2022 | Pending | Pending | Road Cut Related Risk | PWD rejected road cutting permission since road under krfb, request submitted to krfb on 7/02/2022 | To solve the road cutting related issues, District Administraion conducted a joint meeting at Collectorate Conference Hall on 12/08/2022. As per direction of this meeting, application resubmitted to KRFB through e mail 30.8.2022 | Action Taken |
13 Apr 2022 | Pending | Pending | Road Cut Related Risk | PWD rejected road cutting permission since road under krfb, request submitted to krfb on 7/02/2022 | To solve the road cutting related issues, District Administraion conducted a joint meeting at Collectorate Conference Hall on 12/08/2022. As per direction of this meeting, application resubmitted to KRFB through e mail 30.8.2022 | Action Taken |
13 Apr 2022 | Pending | Pending | Road Cut Related Risk | PWD rejected road cutting permission since road under krfb, request submitted to krfb on 7/02/2022 | To solve the road cutting related issues, District Administraion conducted a joint meeting at Collectorate Conference Hall on 12/08/2022. As per direction of this meeting, application resubmitted to KRFB through e mail 30.8.2022 | Action Taken |
13 Apr 2022 | Pending | Pending | Road Cut Related Risk | PWD rejected road cutting permission since road under KRFB, request submitted to KRFB on 7/02/2022 | To solve the road cutting related issues, District Administraion conducted a joint meeting at Collectorate Conference Hall on 12/08/2022. As per direction of this meeting, application resubmitted to KRFB through e mail 30.8.2022 | Action Taken |
11 Nov 2021 | Pending | Pending | Natural Calamities Related | heavy rain in project area ,work delaying | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 09/07/2021 |
---|---|
Scheduled date of Completion as per agreement | 23 Jun 2022 |
Expected date of Completion | 31/10/2022 |
TS Date | 27 Aug 2020 |
---|---|
Estimate Approval | 27 Aug 2020 |
NIT Approval | 03 Sep 2020 |
Tender Closing | 04 Jan 2021 |
Technichal Pre-Qualification | 06 Jan 2021 |
Price bid opening | 06 Jan 2021 |
Workorder Date | 27 Apr 2021 |
---|---|
NA | 24 Jun 2021 |
Kollam Project Dn AE |
Date: 22/06/2024 |
Work in progress | 97% Completed
Work fore closed.
Kollam Project Dn EE |
Date: 23/07/2023 |
Work in progress | 97% Completed
83 FHTC long pending in pattazhy kunnicodu KRFB road. Application submitted through RoW portal rejected by KRFB since the road is under DLP. For obtaining sanction application re submitted to KRFB and this application also rejected. Hence contractor requested to pre close the work and request granted by SE, PH Circle Kollam.