Jal Jeevan Mission - Providing Functional Household Tap Connections at Pattazhy Panchayath in Kollam District.

Project Jal Jeevan Mission - Providing Functional Household Tap Connections at Pattazhy Panchayath in Kollam District.
Project Code KLMJJM08203111P2
Type Package
Main Project Jal Jeevan Mission - Providing Functional Household Tap Connections at Pattazhy Panchayath in Kollam District.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission - Providing Functional Household Tap Connections at Pattazhy Panchayath in Kollam District.
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 27760000
TS Number TS/2020-21/2020/16264
Technical specification house connection as per approved drawing
Contractor M/s HITECH CONSTRUCTION GROUP (Mob: 9656737227)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
13 Apr 2022 Pending Pending Road Cut Related Risk PWD rejected road cutting permission since road under krfb, request submitted to krfb on 7/02/2022 To solve the road cutting related issues, District Administraion conducted a joint meeting at Collectorate Conference Hall on 12/08/2022. As per direction of this meeting, application resubmitted to KRFB through e mail 30.8.2022 Action Taken
13 Apr 2022 Pending Pending Road Cut Related Risk PWD rejected road cutting permission since road under krfb, request submitted to krfb on 7/02/2022 To solve the road cutting related issues, District Administraion conducted a joint meeting at Collectorate Conference Hall on 12/08/2022. As per direction of this meeting, application resubmitted to KRFB through e mail 30.8.2022 Action Taken
13 Apr 2022 Pending Pending Road Cut Related Risk PWD rejected road cutting permission since road under krfb, request submitted to krfb on 7/02/2022 To solve the road cutting related issues, District Administraion conducted a joint meeting at Collectorate Conference Hall on 12/08/2022. As per direction of this meeting, application resubmitted to KRFB through e mail 30.8.2022 Action Taken
13 Apr 2022 Pending Pending Road Cut Related Risk PWD rejected road cutting permission since road under KRFB, request submitted to KRFB on 7/02/2022 To solve the road cutting related issues, District Administraion conducted a joint meeting at Collectorate Conference Hall on 12/08/2022. As per direction of this meeting, application resubmitted to KRFB through e mail 30.8.2022 Action Taken
11 Nov 2021 Pending Pending Natural Calamities Related heavy rain in project area ,work delaying No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 09/07/2021
Scheduled date of Completion as per agreement 23 Jun 2022
Expected date of Completion 31/10/2022

Processing Dates

TS Date 27 Aug 2020
Estimate Approval 27 Aug 2020
NIT Approval 03 Sep 2020
Tender Closing 04 Jan 2021
Technichal Pre-Qualification 06 Jan 2021
Price bid opening 06 Jan 2021

Approval Dates

Workorder Date 27 Apr 2021
NA 24 Jun 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project Dn AE
Date: 22/06/2024

Work in progress | 97% Completed

Work fore closed.

Kollam Project Dn EE
Date: 23/07/2023

Work in progress | 97% Completed

83 FHTC long pending in pattazhy kunnicodu KRFB road. Application submitted through RoW portal rejected by KRFB since the road is under DLP. For obtaining sanction application re submitted to KRFB and this application also rejected. Hence contractor requested to pre close the work and request granted by SE, PH Circle Kollam.