| Project | AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT - Balamandiram Zone -II-Old AC Pipeline Replacement along Pallithazham Chelavoor Road and Providing FHTCs by extension in Chelavoor ,Moozhikkal wards -Pipeline Work |
|---|---|
| Project Code | CLTAMRUT032313801P9 |
| Type | Package |
| Main Project | AMRUT 1.0-Kozhikode Water Supply Project-Providing FHTCs and Pipe Line extension |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT - Balamandiram Zone -II-Old AC Pipeline Replacement along Pallithazham Chelavoor Road and Providing FHTCs by extension in Chelavoor ,Moozhikkal wards -Pipeline Work |
| Status | On-going |
| District | Kozhikkode |
| Executing Office | Kozhikode Dist SubDn2 Sn 4 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 24010000 |
| TS Number | 16129/2022-2023 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | 30/11/2024 |
| TS Date | 13 Mar 2023 |
|---|---|
| Estimate Approval | 13 Mar 2023 |
| NIT Approval | 13 Mar 2023 |
| Workorder Date | 30 Mar 2023 |
|---|---|
| NA | 31 Mar 2023 |
| Kozhikode PH Dn EE |
| Date: 23/06/2025 |
Work in progress | 98% Completed
Work in progress-pipe supplied 3600 m, laid 3390 m. FHTCs-750 nos. Work near completion only interconnection work pending. .
| Kozhikode PH Dn EE |
| Date: 21/01/2025 |
Work in progress | 98% Completed
Work in progress-pipe supplied 3600 m, laid 2600 m , PWD road cutting permission not received for laying 160mm PVC ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-750 nos..