| Kozhikode PH Dn EE |
| Date: 23/06/2025 |
Work in progress | 98% Completed
Work in progress-pipe supplied 3600 m, laid 3390 m. FHTCs-750 nos. Work near completion only interconnection work pending.
| Kozhikode PH Dn EE |
| Date: 21/01/2025 |
Work in progress | 98% Completed
Work in progress-pipe supplied 3600 m, laid 2600 m , PWD road cutting permission not received for laying 160mm PVC ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-750 nos.
| Kozhikode PH Dn EE |
| Date: 31/12/2024 |
Work in progress | 98% Completed
Work in progress-pipe supplied 3600 m, laid 2600 m , PWD road cutting permission not received for laying 160mm PVC ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-750 nos.
| Kozhikode PH Dn EE |
| Date: 18/12/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not received for laying 160mm PVC for a length of 1600m ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-750 nos.
| Kozhikode PH Dn EE |
| Date: 16/12/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not received for laying 160mm PVC for a length of 1600m ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-749 nos.
| Kozhikode PH Dn EE |
| Date: 12/12/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not received for laying 160mm PVC for a length of 1600m ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-748 nos.
| Kozhikode PH Dn EE |
| Date: 09/12/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not received for laying 160mm PVC for a length of 1600m ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-748 nos.
| Kozhikode PH Dn EE |
| Date: 07/12/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not received for laying 160mm PVC for a length of 1600m ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-748 nos.
| Kozhikode PH Dn EE |
| Date: 02/12/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not received for laying 160mm PVC for a length of 1600m ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-748 nos.
| Kozhikode PH Dn EE |
| Date: 29/11/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not received for laying 160mm PVC for a length of 1600m ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-748 nos.
| Kozhikode PH Dn EE |
| Date: 25/11/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not received for laying 160mm PVC for a length of 1600m ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-748 nos.
| Kozhikode PH Dn EE |
| Date: 23/11/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not received for laying 160mm PVC for a length of 1600m ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-734 nos.
| Kozhikode PH Dn EE |
| Date: 21/11/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not received for laying 160mm PVC for a length of 1600m ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-725 nos.
| Kozhikode PH Dn EE |
| Date: 20/11/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not received for laying 160mm PVC for a length of 1600m ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-719 nos.
| Kozhikode PH Dn EE |
| Date: 19/11/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not received for laying 160mm PVC for a length of 1600m ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-712 nos.
| Kozhikode PH Dn EE |
| Date: 18/11/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not received for laying 160mm PVC for a length of 1600m ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-707 nos.
| Kozhikode PH Dn EE |
| Date: 16/11/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not received for laying 160mm PVC for a length of 1600m ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-699 nos.
| Kozhikode PH Dn EE |
| Date: 15/11/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not received for laying 160mm PVC for a length of 1600m ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-695 nos.
| Kozhikode PH Dn EE |
| Date: 13/11/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not received for laying 160mm PVC for a length of 1600m ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-686 nos.
| Kozhikode PH Dn EE |
| Date: 11/11/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not received for laying 160mm PVC for a length of 1600m ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-680 nos.
| Kozhikode PH Dn EE |
| Date: 06/11/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not received for laying 160mm PVC for a length of 1600m ( Road under DLP - NH 766 Chelavoor to Pallithazham), FHTCs-680 nos.
| Kozhikode PH Dn EE |
| Date: 29/10/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-680 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 25/10/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-680 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 21/10/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-680 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 17/10/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-680 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 14/10/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-680 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 10/10/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-679 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 07/10/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-677 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 03/10/2024 |
Work in progress | 98% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-675 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 01/10/2024 |
Work in progress | 96% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-656 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 30/09/2024 |
Work in progress | 96% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-651 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 25/09/2024 |
Work in progress | 96% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-638 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 23/09/2024 |
Work in progress | 96% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-620 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 21/09/2024 |
Work in progress | 96% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-607 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 20/09/2024 |
Work in progress | 96% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-599 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 19/09/2024 |
Work in progress | 96% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-592 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 18/09/2024 |
| Kozhikode PH Dn EE |
| Date: 16/09/2024 |
Work in progress | 96% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-581 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 14/09/2024 |
Work in progress | 96% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-577 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 11/09/2024 |
Work in progress | 96% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-569 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 09/09/2024 |
Work in progress | 96% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-565nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 06/09/2024 |
Work in progress | 96% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-558 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 04/09/2024 |
Work in progress | 96% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-550 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 02/09/2024 |
Work in progress | 96% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-545nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 29/08/2024 |
Work in progress | 96% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-539nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 26/08/2024 |
Work in progress | 96% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-528 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 23/08/2024 |
Work in progress | 96% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-522 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 21/08/2024 |
Work in progress | 96% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved for laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-517 nos. Hard copy submitted to PWD for getting approval from Morth
| Kozhikode PH Dn EE |
| Date: 16/08/2024 |
Work in progress | 96% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved fpor laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-410 nos.
| Kozhikode PH Dn EE |
| Date: 25/06/2024 |
Work in progress | 95% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved fpor laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-410 nos.
| Kozhikode PH Dn EE |
| Date: 24/06/2024 |
Work in progress | 95% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved fpor laying 160mm PVC for a length of 1600m ( Road under DLP), FHTCs-410 nos.
| Kozhikode PH Dn EE |
| Date: 14/06/2024 |
Work in progress | 95% Completed
Work in progress-pipe laid-110mm pVc-2000m, PWD road cutting permission not recieved fpor laying 160mm PVC for a length of 1600m ( Road under DLP)
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 94% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 93% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 90% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 01/03/2024 |
Work in progress | 88% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 23/02/2024 |
Work in progress | 86% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 22/02/2024 |
Work in progress | 86% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 21/02/2024 |
Work in progress | 86% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 85% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 31/01/2024 |
Work in progress | 81% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 80% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 22/01/2024 |
Work in progress | 77% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 21/01/2024 |
Work in progress | 77% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 20/01/2024 |
Work in progress | 77% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 19/01/2024 |
Work in progress | 77% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 18/01/2024 |
Work in progress | 76% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 17/01/2024 |
Work in progress | 76% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 16/01/2024 |
Work in progress | 76% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 15/01/2024 |
Work in progress | 76% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 14/01/2024 |
Work in progress | 76% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 13/01/2024 |
Work in progress | 76% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 12/01/2024 |
Work in progress | 76% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 11/01/2024 |
Work in progress | 75% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 10/01/2024 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 09/01/2024 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 08/01/2024 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 07/01/2024 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 06/01/2024 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 05/01/2024 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 04/01/2024 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 03/01/2024 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 02/01/2024 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 01/01/2024 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 31/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 30/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 29/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 28/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 27/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 26/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 25/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 24/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 23/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 22/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 21/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 20/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 19/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 18/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 17/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 16/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 15/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 14/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 13/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 12/12/2023 |
Work in progress | 63% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work in progress | 63% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 28/11/2023 |
Work in progress | 60% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 09/11/2023 |
Work in progress | 52% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 28/10/2023 |
Work in progress | 50% Completed
Work Started
| Kozhikode PH Dn EE |
| Date: 17/10/2023 |
Work in progress | 45% Completed
Work Started
| Kozhikode PH Dn EE |
| Date: 15/09/2023 |
Work in progress | 32% Completed
Work Started
| Kozhikode PH Dn EE |
| Date: 05/09/2023 |
Work in progress | 30% Completed
Work Started
| Kozhikode PH Dn EE |
| Date: 17/08/2023 |
Work in progress | 15% Completed
Work Started
| Kozhikode PH Dn EE |
| Date: 08/08/2023 |
Work in progress | 10% Completed
Work Started
| Kozhikode PH Dn EE |
| Date: 24/07/2023 |
Work has started | 0% Completed
Site Handed Over. Work not yet started.
| Kozhikode PH Dn EE |
| Date: 12/07/2023 |
Work has started | 0% Completed
Work Order Issued. Work not yet started.
| Kozhikode PH Dn EE |
| Date: 30/06/2023 |
Work has started | 0% Completed
Work Order Issued. Work not yet started.
| Kozhikode PH Dn EE |
| Date: 20/06/2023 |
Work has started | 0% Completed
Work Order Issued. Work not yet started.
| Kozhikode PH Dn EE |
| Date: 13/06/2023 |
Work has started | 0% Completed
Work Order Issued
| Kozhikode PH Dn EE |
| Date: 08/06/2023 |
Work has started | 0% Completed
Work Order Issued. Not Yet Started
| Kozhikode PH Dn EE |
| Date: 05/06/2023 |
Work has started | 0% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 01/06/2023 |
Work has started | 0% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 25/05/2023 |
Work has started | 0% Completed
Agreement Executed