Jal Jeevan Mission- Kasaragod District- Kuttikol Grama Panchayath- ARWSS to Munnad Bedadka and Kuttikol Villages Phase II - Laying distribution System and providing FHTC
Project |
Jal Jeevan Mission- Kasaragod District- Kuttikol Grama Panchayath- ARWSS to Munnad Bedadka and Kuttikol Villages Phase II - Laying distribution System and providing FHTC |
Project Code |
KGDJJM08202906 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Providing FHTC |
Status |
On-going |
District |
Kasaragod |
Executing Office |
Kasargod PH Dn |
AS Amount (Rs) |
53600000
|
AS Number |
GO(Rt) No 541/2020/WRD |
TS Amount (Rs) |
51690000 |
TS Number |
TS/2020-2021/2020/19159 |
Total Bill Submitted (Rs) |
8326313 |
Total Bill Paid (Rs) |
8326313 |
Population Benefitted |
10695 |
Capacity in MLD |
3.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Kuttikol Panchayath area |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission- Kasaragod District- Kuttikol Grama Panchayath- ARWSS to Munnad Bedadka and Kuttikol Villages Phase II - Laying distribution System and providing FHTC-Balance Work |
Bovikkanam WSP Sn |
|
2 |
Jal Jeevan Mission- Kasaragod District- Kuttikol Grama Panchayath- ARWSS to Munnad Bedadka and Kuttikol Villages Phase II - Laying distribution System and providing FHTC-Construction of 2 lakhs litres OH Tank at Meeyanganam-Balance work |
Bovikkanam WSP Sn |
|
3 |
Jal Jeevan Mission- Kasaragod District- Kuttikol Grama Panchayath- ARWSS to Munnad Bedadka and Kuttikol Villages Phase II - Laying distribution System and providing FHTC-Package |
Bovikkanam WSP Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
21 Oct 2022 |
This work was fully stopped due to the unexpected death of the contractor , and rearranged the balance work.Now the balance work is ongoing as per separate agreement. |
Bovikkanam WSP Sn AE |
|
21 Oct 2022 |
on going |
Bovikkanam WSP Sn AE |
|
17 Oct 2022 |
on going |
Bovikkanam WSP Sn AE |
|
13 Oct 2022 |
on going |
Bovikkanam WSP Sn AE |
|
11 Oct 2022 |
on going |
Bovikkanam WSP Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
10/10/2020 |
Scheduled date of Completion of the Project |
08 Feb 2021 |
Expected date of Completion |
04/04/2024 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
27 Aug 2020 |