| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Oct 2022 | This work was fully stopped due to the unexpected death of the contractor , and rearranged the balance work.Now the balance work is ongoing as per separate agreement. | Bovikkanam WSP Sn AE | |
| 21 Oct 2022 | on going | Bovikkanam WSP Sn AE | |
| 17 Oct 2022 | on going | Bovikkanam WSP Sn AE | |
| 13 Oct 2022 | on going | Bovikkanam WSP Sn AE | |
| 11 Oct 2022 | on going | Bovikkanam WSP Sn AE | |
| 07 Oct 2022 | on going | Bovikkanam WSP Sn AE | |
| 03 Oct 2022 | On going | Bovikkanam WSP Sn AE | |
| 26 Sep 2022 | On going | Bovikkanam WSP Sn AE | |
| 19 Sep 2022 | Ongoing | Bovikkanam WSP Sn AE | |
| 12 Sep 2022 | Ongoing | Bovikkanam WSP Sn AE |