Project | Jal Jeevan Mission- Kasaragod District- Kuttikol Grama Panchayath- ARWSS to Munnad Bedadka and Kuttikol Villages Phase II - Laying distribution System and providing FHTC-Construction of 2 lakhs litres OH Tank at Meeyanganam-Balance work |
---|---|
Project Code | KGDJJM08202906P3 |
Type | Package |
Main Project | Jal Jeevan Mission- Kasaragod District- Kuttikol Grama Panchayath- ARWSS to Munnad Bedadka and Kuttikol Villages Phase II - Laying distribution System and providing FHTC |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission- Kasaragod District- Kuttikol Grama Panchayath- ARWSS to Munnad Bedadka and Kuttikol Villages Phase II - Laying distribution System and providing FHTC-Construction of 2 lakhs litres OH Tank at Meeyanganam-Balance work |
Status | On-going |
District | Kasaragod |
Executing Office | Bovikkanam WSP Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 37000000 |
TS Number | 8761/2023-26-1-1 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | 04 Apr 2024 |
Expected date of Completion | 31/12/2024 |
TS Date | 09 Aug 2023 |
---|---|
Estimate Approval | 09 Aug 2023 |
Tender Closing | 16 Aug 2023 |
Price bid opening | 21 Aug 2023 |
Workorder Date | 05 Sep 2023 |
---|---|
NA | 25 Sep 2023 |
Bovikkanam WSP Sn AE |
Date: 01/07/2024 |
Work in progress | 1% Completed
Site handed over on 05/10/2023..
Bovikkanam WSP Sn AE |
Date: 28/06/2024 |
Work in progress | 1% Completed
Site handed over on 05/10/2023..