KIIFB PROJECT-CARWSS to kozhinjampara and adjoining villages-Replacement of 200 mm AC clear water gravity main

Project KIIFB PROJECT-CARWSS to kozhinjampara and adjoining villages-Replacement of 200 mm AC clear water gravity main
Project Code PKDKIIFB0319689P1
Type Package
Main Project KIIFB PROJECT-CARWSS to kozhinjampara and adjoining villages-Replacement of 200 mm AC clear water gravity main from master OHSR at moongilmada to sathram sump with 200 mm DI k9 pipe for 16000 m-replacement of 200 mm AC Clear water gravity main from master OHSR at oonkilmada to kozhinjampara OHSR with 250 mm DI K9 PIPE FOR 6750 M
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Replacement of 200 mm AC Clear water gravity main from master OHSR at Moonkilmada to kozhinjampara OHSR with 250 mm DI K9 PIPE FOR 6750 M
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 38200000
TS Number 2019-2020/2019/18397 dated 18-02-2020
Technical specification Replacement of 200 mm AC Clear water gravity main from master OHSR at oonkilmada to kozhinjampara OHSR with 250 mm DI K9 PIPE for 6750 M
Contractor K.O Jose (Mob: 9447081236)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 23/03/2020
Scheduled date of Completion as per agreement 22 Sep 2020
Expected date of Completion 31/07/2022

Processing Dates

TS Date 18 Feb 2020
Estimate Approval 18 Feb 2020
NIT Approval 16 Mar 2020
Tender Closing 12 Mar 2020
Technichal Pre-Qualification 16 Mar 2020
Price bid opening 16 Mar 2020

Approval Dates

Workorder Date 23 Mar 2020
NA 01 Jun 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - EE
Date: 23/08/2022

Work has been completed | 100% Completed

Final bill under scuitiny at Division..

Chittur Project Dn - AE 4
Date: 31/05/2022

Work has been completed | 100% Completed

Road restoration work completed, PIPE LAYING work completed on 31.3.2021. balance Bill under preparation.