Chittur Project Dn - EE |
Date: 23/08/2022 |
Work has been completed | 100% Completed
Final bill under scuitiny at Division.
Chittur Project Dn - AE 4 |
Date: 31/05/2022 |
Work has been completed | 100% Completed
Road restoration work completed, PIPE LAYING work completed on 31.3.2021. balance Bill under preparation
Chittur Project Dn - AE 4 |
Date: 10/05/2022 |
Work has been completed | 100% Completed
Road restoration work completed, PIPE LAYING work completed on 31.3.2021. balance Bill under preparation
Chittur Project Dn - AE 4 |
Date: 02/05/2022 |
Work in progress | 98% Completed
Road restoration work in progress
Chittur Project Dn - AE 4 |
Date: 25/04/2022 |
Work in progress | 98% Completed
Road restoration work in progress
Chittur Project Dn - AE 4 |
Date: 18/04/2022 |
Work in progress | 98% Completed
Road restoration work in progress
Chittur Project Dn - AE 4 |
Date: 12/04/2022 |
Work in progress | 98% Completed
Road restoration work in progress
Chittur Project Dn - AE 4 |
Date: 06/04/2022 |
Work in progress | 98% Completed
Road restoration work in progress
Chittur Project Dn - AE 4 |
Date: 31/03/2022 |
Work in progress | 98% Completed
Road restoration work in progress
Chittur Project Dn - AE 4 |
Date: 23/03/2022 |
Work in progress | 98% Completed
Road restoration work in progress
Chittur Project Dn - AE 4 |
Date: 17/03/2022 |
Work in progress | 98% Completed
Road restoration work in progress
Chittur Project Dn - AE 4 |
Date: 16/03/2022 |
Work in progress | 98% Completed
Road restoration work in progress
Chittur Project Dn - AE 4 |
Date: 15/03/2022 |
Work in progress | 98% Completed
Road restoration work in progress
Chittur Project Dn - AE 4 |
Date: 09/03/2022 |
Work in progress | 98% Completed
Road restoration work in progress
Chittur Project Dn - AE 4 |
Date: 03/03/2022 |
Work in progress | 98% Completed
Road restoration work in progress
Chittur Project Dn - AE 4 |
Date: 22/02/2022 |
Work in progress | 98% Completed
Road restoration work in progress
Chittur Project Dn - AE 4 |
Date: 13/02/2022 |
Work in progress | 94% Completed
Tarring works in progress at PWD Road
Chittur Project Dn - AE 4 |
Date: 06/02/2022 |
Work in progress | 94% Completed
Tarring works in progress at PWD Road
Chittur Project Dn - AE 4 |
Date: 02/02/2022 |
Work in progress | 92% Completed
GSB and Wet Mix spreading works in PWD road in progress
Chittur Project Dn - AE 4 |
Date: 01/02/2022 |
Work in progress | 92% Completed
GSB and Wet Mix spreading works in PWD road in progress
Chittur Project Dn - AE 4 |
Date: 24/01/2022 |
Work in progress | 92% Completed
GSB and Wet Mix spreading works in PWD road in progress
Chittur Project Dn - AE 4 |
Date: 20/01/2022 |
Work in progress | 92% Completed
GSB and Wet Mix spreading works in PWD road in progress
Chittur Project Dn - AE 4 |
Date: 12/01/2022 |
Work in progress | 92% Completed
GSB and Wet Mix spreading works in PWD road in progress
Chittur Project Dn - AE 4 |
Date: 10/01/2022 |
Work in progress | 92% Completed
GSB and Wet Mix spreading works in PWD road in progress
Chittur Project Dn - AE 4 |
Date: 02/01/2022 |
Work in progress | 92% Completed
GSB and Wet Mix spreading works in PWD road in progress
Chittur Project Dn - AE 4 |
Date: 28/12/2021 |
Work in progress | 92% Completed
GSB and Wet Mix spreading works in PWD road in progress
Chittur Project Dn - AE 4 |
Date: 22/12/2021 |
Work in progress | 92% Completed
GSB and Wet Mix spreading works in PWD road in progress
Chittur Project Dn - AE 1 |
Date: 21/12/2021 |
Chittur Project Dn - AE 4 |
Date: 19/12/2021 |
Work in progress | 92% Completed
GSB and Wet Mix spreading works in PWD road under progress. Road survey works and taking of road levels prior to tarring completed.
Chittur Project Dn - AE 4 |
Date: 18/12/2021 |
Work in progress | 92% Completed
GSB and Wet Mix spreading works in PWD road under progress. Road survey works and taking of road levels prior to tarring completed.
Chittur Project Dn - AE 1 |
Date: 16/12/2021 |
Chittur Project Dn - AE 4 |
Date: 12/12/2021 |
Work in progress | 92% Completed
road restoration works and inter linking works in progress
Chittur Project Dn - AE 4 |
Date: 05/12/2021 |
Work in progress | 92% Completed
road restoration works and inter linking works in progress
Chittur Project Dn - AE 4 |
Date: 28/11/2021 |
Work in progress | 92% Completed
road restoration works and inter linking works in progress
Chittur Project Dn - AE 4 |
Date: 21/11/2021 |
Work in progress | 91% Completed
road restoration work started
Chittur Project Dn - AE 4 |
Date: 14/11/2021 |
Work in progress | 91% Completed
all other works except road restoration completed. Road restoration to be done
Chittur Project Dn - AE 4 |
Date: 07/11/2021 |
Work in progress | 91% Completed
all other works except road restoration completed. Road restoration to be done
Chittur Project Dn - AE 4 |
Date: 31/10/2021 |
Work in progress | 91% Completed
all other works except road restoration completed. Road restoration to be done
Chittur Project Dn - AE 4 |
Date: 24/10/2021 |
Work in progress | 91% Completed
all other works except road restoration completed. Road restoration to be done
Chittur Project Dn - AE 4 |
Date: 17/10/2021 |
Work in progress | 91% Completed
all other works except road restoration completed. Road restoration to be done
Chittur Project Dn - AE 4 |
Date: 10/10/2021 |
Work in progress | 91% Completed
all other works except road restoration completed. Road restoration to be done
Chittur Project Dn - AE 4 |
Date: 03/10/2021 |
Work in progress | 91% Completed
all other works except road restoration completed. Road restoration to be done
Chittur Project Dn - AE 4 |
Date: 27/09/2021 |
Work in progress | 91% Completed
all other works except road restoration completed. Road restoration will be done
Chittur Project Dn - AE 4 |
Date: 24/09/2021 |
Work in progress | 91% Completed
all other works except road restoration completed. Road restoration will be done
Chittur Project Dn - AE 4 |
Date: 20/09/2021 |
Work in progress | 91% Completed
all other works except road restoration completed. Road restoration will be done
Chittur Project Dn - AE 4 |
Date: 12/09/2021 |
Work in progress | 91% Completed
all other works except road restoration completed. Road restoration will be done after lifting monsoon ban
Chittur Project Dn - AE 4 |
Date: 05/09/2021 |
Work in progress | 91% Completed
all other works except road restoration completed. Road restoration will be done after lifting monsoon ban
Chittur Project Dn - AE 4 |
Date: 29/08/2021 |
Work in progress | 91% Completed
all other works except road restoration completed. Road restoration will be done after lifting monsoon ban
Chittur Project Dn - AE 4 |
Date: 16/08/2021 |
Work in progress | 91% Completed
all other works except road restoration completed. Road restoration will be done after lifting monsoon ban
Chittur Project Dn - AE 4 |
Date: 09/08/2021 |
Work in progress | 91% Completed
all other works except road restoration completed. Road restoration will be done after lifting monsoon ban
Chittur Project Dn - AE 4 |
Date: 01/08/2021 |
Work in progress | 91% Completed
all other works except road restoration completed. Road restoration will be done after lifting monsoon ban
Chittur Project Dn - AE 4 |
Date: 27/07/2021 |
Work in progress | 91% Completed
all other works except road restoration completed. Road restoration will be done after lifting monsoon ban
Chittur Project Dn - AE 4 |
Date: 24/07/2021 |
Work in progress | 91% Completed
ll other works except road restoration completed. Road restoration will be done after lifting monsoon ban
Chittur Project Dn - AE 4 |
Date: 19/07/2021 |
Work in progress | 91% Completed
All other works except road restoration completed. Road restoration will be done after lifting monsoon ban
Chittur Project Dn - AE 4 |
Date: 11/07/2021 |
Work in progress | 91% Completed
All other works except road restoration completed. Road restoration will be done after lifting monsoon ban
Chittur Project Dn - AE 4 |
Date: 05/07/2021 |
Work in progress | 91% Completed
All other works except road restoration completed. Road restoration will be done after lifting monsoon ban
Chittur Project Dn - AE 4 |
Date: 28/06/2021 |
Work in progress | 91% Completed
Road restoration work to be completed
Chittur Project Dn - AE 4 |
Date: 25/06/2021 |
Work in progress | 91% Completed
Road restoration work to be completed .
Chittur Project Dn - AE 4 |
Date: 20/06/2021 |
Work in progress | 91% Completed
Road restoration work to be completed . AE prepared cc second and part bill for Rs,89.966 Lakhs.
Chittur Project Dn - AE 4 |
Date: 18/06/2021 |
Work in progress | 91% Completed
Road restoration work to be completed . AE prepared cc second and part bill for Rs,89.966 Lakhs.
Chittur Project Dn - AE 4 |
Date: 08/06/2021 |
Work in progress | 91% Completed
91% of the work completed. Road restoration work to be completed . AE prepared cc second and part bill for Rs,89.966 Lakhs.
Chittur Project Dn - AE 4 |
Date: 01/06/2021 |
Work in progress | 91% Completed
91% of the work completed. Road restoration work to be completed . AE prepared cc second and part bill for Rs,89.966 Lakhs.
Chittur Project Dn - AE 4 |
Date: 27/05/2021 |
Work in progress | 91% Completed
CC second and part bill prepared Rs50.00 Lakhs. 91% Completed ,Road restoration work pending,pipe line work completed
Chittur Project Dn - AE 4 |
Date: 19/05/2021 |
Work in progress | 91% Completed
CC second and part bill prepared Rs50.00 Lakhs. 91% Completed ,Road restoration work pending
Chittur Project Dn - AE 4 |
Date: 11/05/2021 |
Work in progress | 91% Completed
CC second and part bill under preparation.91% Completed ,Road restoration work pending
Chittur Project Dn - AE 4 |
Date: 29/04/2021 |
Work in progress | 91% Completed
CC second and part bill under preparation.91% Completed ,Road restoration work pending
Chittur Project Dn - AE 4 |
Date: 28/04/2021 |
Work in progress | 91% Completed
CC second and part bill under preparation.91% Completed ,Road restoration work pending , SECOND TIME EXTENTION UP TO 31.5.2021
Chittur Project Dn - AE 4 |
Date: 20/04/2021 |
Work in progress | 91% Completed
91 % of the work complete ,Road restoration work pending , SECOND TIME EXTENTION UP TO 31.5.2021
Chittur Project Dn - AE 4 |
Date: 13/04/2021 |
Work in progress | 91% Completed
91 % of the work complete Delay due to the Election ban (perumattachattam) , road restoration work -Bitumen has to be taken from BPCL and last linking works also balance , SECOND TIME EXTENTION UP TO 31.5.2021
Chittur Project Dn - AE 4 |
Date: 07/04/2021 |
Work in progress | 91% Completed
91 % of the work complete Delay due to the Election ban (perumattachattam) , road restoration work -Bitumen has to be taken from BPCL and last linking works also balance , SECOND TIME EXTENTION UP TO 31.5.2021
Chittur Project Dn - AE 4 |
Date: 31/03/2021 |
Work in progress | 91% Completed
250mm CWGM interlinking work almost completed , road restoration work, testing works to be done .second time extension up to -31.05.2021
Chittur Project Dn - AE 4 |
Date: 27/03/2021 |
Work in progress | 91% Completed
Pipe line work completed and inter connection and linking, road restoration work, testing works to be done .second time extension up to -31.05.2021
Chittur Project Dn - AE 4 |
Date: 17/03/2021 |
Work in progress | 90% Completed
250mm DI K9 pipe -total -6.600 km laid
Chittur Project Dn - AE 4 |
Date: 09/03/2021 |
Work in progress | 84% Completed
250mm DI K9 pipe -total -6.100 km laid
Chittur Project Dn - AE 4 |
Date: 08/03/2021 |
Work in progress | 73% Completed
Work in progress | 73% Completed | 07/03/2021 Total -6.00km pipe laid,250mm DI K9 pipe laying work and main road crossing works and vaive fixing work are in progress
Chittur Project Dn - AE 4 |
Date: 07/03/2021 |
Work in progress | 73% Completed
Total -5.60km pipe laid,250mm DI K9 pipe laying work and main road crossing works and vaive fixing work are in progress
Chittur Project Dn - AE 4 |
Date: 28/02/2021 |
Work in progress | 72% Completed
250mm DI K9 pipe laying work and main road crossing works and vaive fixing work are in progress
Chittur Project Dn - AE 4 |
Date: 24/02/2021 |
Work in progress | 72% Completed
250mm DI K9 pipe laying work -5.60km laid and main road crossing works and vaive fixing work are in progress
Chittur Project Dn - AE 4 |
Date: 18/02/2021 |
Work in progress | 71% Completed
250mm DI K9 pipe-5.60km laid and valve chamber work ,pressure test works are in progress
Chittur Project Dn - AE 4 |
Date: 16/02/2021 |
Work in progress | 71% Completed
250MM DI K9 PIPE laid for a length of 5.50 km and valve chamber work in progress
Chittur Project Dn - AE 4 |
Date: 01/02/2021 |
Work in progress | 70% Completed
250MM DI K9 PIPE laid for a length of 5 km
Chittur Project Dn - AE 4 |
Date: 02/01/2021 |
Work in progress | 34% Completed
Pipe laid for a length of 3200m.
Chittur Project Dn - AE 4 |
Date: 16/12/2020 |
Chittur Project Dn - AE 4 |
Date: 24/11/2020 |
Work in progress | 24% Completed
Pipe laying work in progress 250mm DI K9 pipe laid 1650m from Vannamada junction (out of 6750 m)