Jal Jeevan Mission Phase I- 2020-21- RWSS to Sooranadu South- Providing FHTC, PVC pipe lineJ extension, supply and errection of pump sets, installation of bulk water meter etc. in Sooranadu South grama panchayath.
Project |
Jal Jeevan Mission Phase I- 2020-21- RWSS to Sooranadu South- Providing FHTC, PVC pipe lineJ extension, supply and errection of pump sets, installation of bulk water meter etc. in Sooranadu South grama panchayath. |
Project Code |
KLMJJM08206538P1 |
Type |
Package |
Main Project |
Jal Jeevan Mission Phase I- 2020-21- RWSS to Sooranadu South- Providing FHTC, PVC pipe lineJ extension, supply and errection of pump sets, installation of bulk water meter etc. in Sooranadu South grama panchayath.
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission Phase I- 2020-21- RWSS to Sooranadu South- Providing FHTC, PVC pipe lineJ extension, supply and errection of pump sets, installation of bulk water meter etc. in Sooranadu South grama panchayath. |
Status |
On-going |
District |
Kollam |
Executing Office |
Sasthamcottah WS Sn1 |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
61990000 |
TS Number |
ORDER No. TS/2020-2021/2020/16515 |
Technical specification |
A total of 2643 FHTCs to be given under this work in Sooranadu South grama panchayth. |
Contractor |
E Sirajudeen (Mob: 9446181093) |
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
17 Sep 2021 |
Pending |
Pending |
Road Cut Related Risk |
road cutting permission request for a length of 6424mts in various PWD roads has been rejected by the PWD authorities
At the beginning of the work the work has temporary stopped for 45 days due to the objection from the panchayath authorities regarding road cutting reasons and that has been solved. |
No comments available. |
Pending |
17 Sep 2021 |
Pending |
Pending |
Road Cut Related Risk |
Road cutting permission request for a length of 6424mts at various PWD roads has been rejected by the PWD authorities.
At the beginning the work has temporarily stopped for 45days due to the objection from the panchayath authorities regarding road cutting reasons and has been solved
|
No comments available. |
Pending |
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
22/01/2021 |
Scheduled date of Completion as per agreement |
21 Jan 2022 |
Expected date of Completion |
13/05/2024 |
Processing Dates
TS Date |
21 Aug 2020 |
Estimate Approval |
21 Aug 2020 |
NIT Approval |
21 Aug 2020 |
Tender Closing |
19 Oct 2020 |
Price bid opening |
01 Dec 2021 |
Approval Dates
Workorder Date |
17 Dec 2020 |
NA |
22 Jan 2021 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Sasthamcotta WS Sn 1 - AE |
Date: 29/06/2024 |
Work in progress | 80% Completed
The work has delayed due to the delay in getting PWD/KRFB road cutting permission and RE sanction. The RE sanction now obatained on 25.04.2024. After getting the RE sanction the ime extension request was submitted by the contracor on 09.05.2024 and recommendation has been already forwarded..
Sasthamcotta WS Sn 1 - AE |
Date: 26/06/2024 |
Work in progress | 80% Completed
The work has delayed due to the delay in getting PWD/KRFB road cutting permission and RE sanction. The RE sanction now obatained on 25.04.2024. After getting the RE sanction the ime extension request was submitted by the contracor on 09.05.2024 and recommendation has been already forwarded..