Jal Jeevan Mission Phase I- 2020-21- RWSS to Sooranadu South- Providing FHTC, PVC pipe lineJ extension, supply and errection of pump sets, installation of bulk water meter etc. in Sooranadu South grama panchayath.

Project Jal Jeevan Mission Phase I- 2020-21- RWSS to Sooranadu South- Providing FHTC, PVC pipe lineJ extension, supply and errection of pump sets, installation of bulk water meter etc. in Sooranadu South grama panchayath.
Project Code KLMJJM08206538P1
Type Package
Main Project Jal Jeevan Mission Phase I- 2020-21- RWSS to Sooranadu South- Providing FHTC, PVC pipe lineJ extension, supply and errection of pump sets, installation of bulk water meter etc. in Sooranadu South grama panchayath.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission Phase I- 2020-21- RWSS to Sooranadu South- Providing FHTC, PVC pipe lineJ extension, supply and errection of pump sets, installation of bulk water meter etc. in Sooranadu South grama panchayath.
Status On-going
District Kollam
Executing Office Sasthamcottah WS Sn1
Agreement Number
Agreement Date
TS Amount (Rs) 61990000
TS Number ORDER No. TS/2020-2021/2020/16515
Technical specification A total of 2643 FHTCs to be given under this work in Sooranadu South grama panchayth.
Contractor E Sirajudeen (Mob: 9446181093)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
17 Sep 2021 Pending Pending Road Cut Related Risk road cutting permission request for a length of 6424mts in various PWD roads has been rejected by the PWD authorities At the beginning of the work the work has temporary stopped for 45 days due to the objection from the panchayath authorities regarding road cutting reasons and that has been solved. No comments available. Pending
17 Sep 2021 Pending Pending Road Cut Related Risk Road cutting permission request for a length of 6424mts at various PWD roads has been rejected by the PWD authorities. At the beginning the work has temporarily stopped for 45days due to the objection from the panchayath authorities regarding road cutting reasons and has been solved No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/01/2021
Scheduled date of Completion as per agreement 21 Jan 2022
Expected date of Completion 13/05/2024

Processing Dates

TS Date 21 Aug 2020
Estimate Approval 21 Aug 2020
NIT Approval 21 Aug 2020
Tender Closing 19 Oct 2020
Price bid opening 01 Dec 2021

Approval Dates

Workorder Date 17 Dec 2020
NA 22 Jan 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Sasthamcotta WS Sn 1 - AE
Date: 29/06/2024

Work in progress | 80% Completed

The work has delayed due to the delay in getting PWD/KRFB road cutting permission and RE sanction. The RE sanction now obatained on 25.04.2024. After getting the RE sanction the ime extension request was submitted by the contracor on 09.05.2024 and recommendation has been already forwarded..

Sasthamcotta WS Sn 1 - AE
Date: 26/06/2024

Work in progress | 80% Completed

The work has delayed due to the delay in getting PWD/KRFB road cutting permission and RE sanction. The RE sanction now obatained on 25.04.2024. After getting the RE sanction the ime extension request was submitted by the contracor on 09.05.2024 and recommendation has been already forwarded..