| Project | AMRUT-ANTHOOR MUNICIPALITY- AMRUT 2.0-2022-23-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN ANTHOOR MUNICIPALITY |
|---|---|
| Project Code | KNRAMRUT112213590P1 |
| Type | Package |
| Main Project | AMRUT-ANTHOOR MUNICIPALITY- AMRUT 2.0-2022-23-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN ANTHOOR MUNICIPALITY |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT-ANTHOOR MUNICIPALITY- AMRUT 2.0-2022-23-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN ANTHOOR MUNICIPALITY |
| Status | On-going |
| District | Kannur |
| Executing Office | Kalliassery WS Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 67600000 |
| TS Number | WRD/KWA-CE(NR)/EST_TS/5119/2022_5_1_1 |
| Technical specification | Providing 3080 Nos. of FHTCS in the 28 wards of Anthoor Municipality. |
| Contractor | Baburaj.P.k (Mob: 9447152707) |
| Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
|---|---|---|---|---|---|---|
| 10 Dec 2023 | Pending | Pending | KRWSA-Organisational Project Risk | 1 | No comments available. | Pending |
| 10 Dec 2023 | Pending | Pending | KRWSA-Organisational Project Risk | 1 | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 10/04/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 03 Feb 2024 |
| Expected date of Completion | 30/04/2025 |
| TS Date | 18 Jan 2023 |
|---|---|
| Estimate Approval | 18 Jan 2023 |
| NIT Approval | 06 Feb 2023 |
| Tender Closing | 20 Feb 2023 |
| Technichal Pre-Qualification | 17 Mar 2023 |
| Price bid opening | 21 Feb 2023 |
| Workorder Date | 10 Apr 2023 |
|---|---|
| NA | 03 May 2023 |
| Kalliassery W S Section - AE |
| Date: 08/01/2026 |
Work has been completed | 100% Completed
work completed final bill to be submitted.
| Kalliassery W S Section - AE |
| Date: 22/12/2025 |
Work in progress | 99% Completed
10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted. RE required before final bill and under preparation..