AMRUT-ANTHOOR MUNICIPALITY- AMRUT 2.0-2022-23-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN ANTHOOR MUNICIPALITY
Project |
AMRUT-ANTHOOR MUNICIPALITY- AMRUT 2.0-2022-23-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN ANTHOOR MUNICIPALITY |
Project Code |
KNRAMRUT112213590 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
AMRUT-ANTHOOR MUNICIPALITY- AMRUT 2.0-2022-23-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN ANTHOOR MUNICIPALITY |
Status |
On-going |
District |
Kannur |
Executing Office |
Thaliparambu WS Dn |
AS Amount (Rs) |
67550000
|
AS Number |
G.O.(Rt)No.2906/2022/LSGD |
TS Amount (Rs) |
67600000 |
TS Number |
WRD/KWA-CE(NR)/EST_TS/5119/2022_5_1_1 |
Total Bill Submitted (Rs) |
20540632 |
Total Bill Paid (Rs) |
11119054 |
Population Benefitted |
15900 |
Capacity in MLD |
2.75 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Providing 3080 Nos. of FHTCS in the 28 wards of Anthoor Municipality. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT-ANTHOOR MUNICIPALITY- AMRUT 2.0-2022-23-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN ANTHOOR MUNICIPALITY |
Kalliassery WS Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
12 Feb 2024 |
10,000 m distribution pipe laying completed. 2027 FHTCs out of 3080 FHTCs completed.CC IVth and part Bill submitted |
Thaliparamba WS Dn EE |
|
08 Jan 2024 |
10,000 m distribution pipe laying completed. 1837 FHTCs out of 3080 FHTCs completed |
Thaliparamba WS Dn EE |
|
08 Jan 2024 |
10,000 m distribution pipe laying completed. 1837 FHTCs out of 3080 FHTCs completed |
Thaliparamba WS Dn EE |
|
10 Dec 2023 |
1341 FHTCs out of 3080 FHTCs completed. 6 km of distribution pipeline laying completed and Interconnection wroks going on. CC IIIrd & part bill prepared and under scrutiny. |
Kalliassery W S Section - AE |
|
09 Dec 2023 |
1157 FHTCs completed. Pipe laying 95% completed. 3rd and part bill submitted and is under scrutiny |
Thaliparamba WS Dn EE |
|
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
10 Dec 2023 |
Pending |
Pending |
Social Project Risks |
Delay in obtaining Ownership certificate by beneficiaries. |
No comments available. |
Pending |
Duration & Sanction dates
Date of start of Project |
10/04/2023 |
Scheduled date of Completion of the Project |
03 Feb 2024 |
Expected date of Completion |
03/02/2024 |
Processing Dates
AS Date |
24 Nov 2022 |
TS Date |
18 Jan 2023 |