AMRUT-ANTHOOR MUNICIPALITY- AMRUT 2.0-2022-23-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN ANTHOOR MUNICIPALITY
| Project |
AMRUT-ANTHOOR MUNICIPALITY- AMRUT 2.0-2022-23-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN ANTHOOR MUNICIPALITY |
| Project Code |
KNRAMRUT112213590 |
| Type |
Main project |
| Funding Agency |
AMRUT |
| Category |
AMRUT |
| Type of scheme |
Water Supply |
| Scheme |
AMRUT |
| Description |
AMRUT-ANTHOOR MUNICIPALITY- AMRUT 2.0-2022-23-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN ANTHOOR MUNICIPALITY |
| Status |
Completed |
| District |
Kannur |
| Executing Office |
Thaliparambu WS Dn |
| AS Amount (Rs) |
67550000
|
| AS Number |
G.O.(Rt)No.2906/2022/LSGD |
| TS Amount (Rs) |
67600000 |
| TS Number |
WRD/KWA-CE(NR)/EST_TS/5119/2022_5_1_1 |
| Total Bill Submitted (Rs) |
20540632 |
| Total Bill Paid (Rs) |
11119054 |
| Population Benefitted |
15900 |
| Capacity in MLD |
2.75 |
| Actual Project Completion Date |
08 Jan 2026 |
| Coverage |
Providing 3080 Nos. of FHTCS in the 28 wards of Anthoor Municipality. |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
AMRUT-ANTHOOR MUNICIPALITY- AMRUT 2.0-2022-23-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN ANTHOOR MUNICIPALITY |
Kalliassery WS Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 08 Jan 2026 |
RE Submitted. Work completed. Final bill to be submitted |
Kalliassery W S Section - AE |
|
| 22 Dec 2025 |
RE required before final bill. |
Kalliassery W S Section - AE |
|
| 12 Feb 2024 |
10,000 m distribution pipe laying completed. 2027 FHTCs out of 3080 FHTCs completed.CC IVth and part Bill submitted |
Thaliparamba WS Dn EE |
|
| 08 Jan 2024 |
10,000 m distribution pipe laying completed. 1837 FHTCs out of 3080 FHTCs completed |
Thaliparamba WS Dn EE |
|
| 08 Jan 2024 |
10,000 m distribution pipe laying completed. 1837 FHTCs out of 3080 FHTCs completed |
Thaliparamba WS Dn EE |
|
No project review have been added to this project
Reported Issues
| Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
| 10 Dec 2023 |
Pending |
Pending |
Social Project Risks |
Delay in obtaining Ownership certificate by beneficiaries. |
No comments available. |
Pending |
Duration & Sanction dates
| Date of start of Project |
10/04/2023 |
| Scheduled date of Completion of the Project |
03 Feb 2024 |
| Expected date of Completion |
03/02/2024 |
Processing Dates
| AS Date |
24 Nov 2022 |
| TS Date |
18 Jan 2023 |