AMRUT-ANTHOOR MUNICIPALITY- AMRUT 2.0-2022-23-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN ANTHOOR MUNICIPALITY

Project AMRUT-ANTHOOR MUNICIPALITY- AMRUT 2.0-2022-23-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN ANTHOOR MUNICIPALITY
Project Code KNRAMRUT112213590
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-ANTHOOR MUNICIPALITY- AMRUT 2.0-2022-23-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN ANTHOOR MUNICIPALITY
Status On-going
District Kannur
Executing Office Thaliparambu WS Dn
AS Amount (Rs) 67550000
AS Number G.O.(Rt)No.2906/2022/LSGD
TS Amount (Rs) 67600000
TS Number WRD/KWA-CE(NR)/EST_TS/5119/2022_5_1_1
Total Bill Submitted (Rs) 20540632
Total Bill Paid (Rs) 11119054
Population Benefitted 15900
Capacity in MLD 2.75
Actual Project Completion Date Date is not specified
Coverage Providing 3080 Nos. of FHTCS in the 28 wards of Anthoor Municipality.
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 AMRUT-ANTHOOR MUNICIPALITY- AMRUT 2.0-2022-23-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN ANTHOOR MUNICIPALITY Kalliassery WS Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Feb 2024 10,000 m distribution pipe laying completed. 2027 FHTCs out of 3080 FHTCs completed.CC IVth and part Bill submitted Thaliparamba WS Dn EE
08 Jan 2024 10,000 m distribution pipe laying completed. 1837 FHTCs out of 3080 FHTCs completed Thaliparamba WS Dn EE
08 Jan 2024 10,000 m distribution pipe laying completed. 1837 FHTCs out of 3080 FHTCs completed Thaliparamba WS Dn EE
10 Dec 2023 1341 FHTCs out of 3080 FHTCs completed. 6 km of distribution pipeline laying completed and Interconnection wroks going on. CC IIIrd & part bill prepared and under scrutiny. Kalliassery W S Section - AE
09 Dec 2023 1157 FHTCs completed. Pipe laying 95% completed. 3rd and part bill submitted and is under scrutiny Thaliparamba WS Dn EE

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
10 Dec 2023 Pending Pending Social Project Risks Delay in obtaining Ownership certificate by beneficiaries. No comments available. Pending

Duration & Sanction dates

Date of start of Project 10/04/2023
Scheduled date of Completion of the Project 03 Feb 2024
Expected date of Completion 03/02/2024

Processing Dates

AS Date 24 Nov 2022
TS Date 18 Jan 2023