Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Kalliassery W S Section - AE
Date: 08/01/2026

Work has been completed | 100% Completed

work completed final bill to be submitted

Kalliassery W S Section - AE
Date: 22/12/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted. RE required before final bill and under preparation.

Kalliassery W S Section - AE
Date: 18/11/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 05/11/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 27/10/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 07/10/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 17/09/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 30/08/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 16/08/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 02/08/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 11/07/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 27/06/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 13/05/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 08/05/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 29/04/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 27/03/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 06/03/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 19/02/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 04/02/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 27/01/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 20/01/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 15/01/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 01/01/2025

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3085 FHTCs out of 3085 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 18/12/2024

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3080 FHTCs out of 3080 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 26/11/2024

Work in progress | 99% Completed

10,000 m distribution pipe laying completed. 3080 FHTCs out of 3080 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 11/11/2024

Work in progress | 98% Completed

10,000 m distribution pipe laying completed. 2999 FHTCs out of 3080 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 08/11/2024

Work in progress | 98% Completed

10,000 m distribution pipe laying completed. 2999 FHTCs out of 3080 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 04/11/2024

Work in progress | 98% Completed

10,000 m distribution pipe laying completed. 2999 FHTCs out of 3080 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 30/10/2024

Work in progress | 98% Completed

10,000 m distribution pipe laying completed. 2999 FHTCs out of 3080 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 22/10/2024

Work in progress | 98% Completed

10,000 m distribution pipe laying completed. 2995 FHTCs out of 3080 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 19/10/2024

Work in progress | 98% Completed

10,000 m distribution pipe laying completed. 2956 FHTCs out of 3080 FHTCs completed.CC VI th and part Bill submitted

Kalliassery W S Section - AE
Date: 16/10/2024

Work in progress | 98% Completed

10,000 m distribution pipe laying completed. 2951 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 09/10/2024

Work in progress | 98% Completed

10,000 m distribution pipe laying completed. 2951 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 05/10/2024

Work in progress | 98% Completed

10,000 m distribution pipe laying completed. 2921 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 26/09/2024

Work in progress | 97% Completed

10,000 m distribution pipe laying completed. 2909 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 19/09/2024

Work in progress | 97% Completed

10,000 m distribution pipe laying completed. 2884 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 10/09/2024

Work in progress | 97% Completed

10,000 m distribution pipe laying completed. 2863 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 03/09/2024

Work in progress | 97% Completed

10,000 m distribution pipe laying completed. 2863 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 21/08/2024

Work in progress | 96% Completed

10,000 m distribution pipe laying completed. 2853 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 07/08/2024

Work in progress | 96% Completed

10,000 m distribution pipe laying completed. 2853 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 29/07/2024

Work in progress | 95% Completed

10,000 m distribution pipe laying completed. 2767 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 24/07/2024

Work in progress | 95% Completed

10,000 m distribution pipe laying completed. 2767 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 18/07/2024

Work in progress | 95% Completed

10,000 m distribution pipe laying completed. 2736 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 12/07/2024

Work in progress | 95% Completed

10,000 m distribution pipe laying completed. 2723 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 08/07/2024

Work in progress | 94% Completed

10,000 m distribution pipe laying completed. 2707 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 06/07/2024

Work in progress | 94% Completed

10,000 m distribution pipe laying completed. 2707 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 03/07/2024

Work in progress | 94% Completed

10,000 m distribution pipe laying completed. 2700 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 28/06/2024

Work in progress | 93% Completed

10,000 m distribution pipe laying completed. 2697 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 24/06/2024

Work in progress | 93% Completed

10,000 m distribution pipe laying completed. 2697 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 14/06/2024

Work in progress | 93% Completed

10,000 m distribution pipe laying completed. 2697 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 10/06/2024

Work in progress | 93% Completed

10,000 m distribution pipe laying completed. 2697 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 06/06/2024

Work in progress | 93% Completed

10,000 m distribution pipe laying completed. 2697 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 28/05/2024

Work in progress | 92% Completed

10,000 m distribution pipe laying completed. 2682 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 14/05/2024

Work in progress | 90% Completed

10,000 m distribution pipe laying completed. 2666 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 10/05/2024

Work in progress | 90% Completed

10,000 m distribution pipe laying completed. 2666 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 06/05/2024

Work in progress | 89% Completed

10,000 m distribution pipe laying completed. 2635 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 23/04/2024

Work in progress | 87% Completed

10,000 m distribution pipe laying completed. 2607 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 20/04/2024

Work in progress | 87% Completed

10,000 m distribution pipe laying completed. 2600 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 03/04/2024

Work in progress | 86% Completed

10,000 m distribution pipe laying completed. 2573 FHTCs out of 3080 FHTCs completed.CC Vth and part Bill submitted

Kalliassery W S Section - AE
Date: 20/03/2024

Work in progress | 85% Completed

10,000 m distribution pipe laying completed. 2475 FHTCs out of 3080 FHTCs completed.CC IVth and part Bill submitted

Kalliassery W S Section - AE
Date: 11/03/2024

Work in progress | 84% Completed

10,000 m distribution pipe laying completed. 2376 FHTCs out of 3080 FHTCs completed.CC IVth and part Bill submitted

Kalliassery W S Section - AE
Date: 28/02/2024

Work in progress | 82% Completed

10,000 m distribution pipe laying completed. 2369 FHTCs out of 3080 FHTCs completed.CC IVth and part Bill submitted

Kalliassery W S Section - AE
Date: 22/02/2024

Work in progress | 80% Completed

10,000 m distribution pipe laying completed. 2344 FHTCs out of 3080 FHTCs completed.CC IVth and part Bill submitted

Kalliassery W S Section - AE
Date: 17/02/2024

Work in progress | 78% Completed

10,000 m distribution pipe laying completed. 2282 FHTCs out of 3080 FHTCs completed.CC IVth and part Bill submitted

Kalliassery W S Section - AE
Date: 13/02/2024

Work in progress | 70% Completed

10,000 m distribution pipe laying completed. 2027 FHTCs out of 3080 FHTCs completed.CC IVth and part Bill submitted

Kalliassery W S Section - AE
Date: 07/02/2024

Work in progress | 70% Completed

10,000 m distribution pipe laying completed. 2090 FHTCs out of 3080 FHTCs completed.CC IVth and part Bill submitted

Kalliassery W S Section - AE
Date: 02/02/2024

Work in progress | 67% Completed

10,000 m distribution pipe laying completed. 1960 FHTCs out of 3080 FHTCs completed.CC IVth and part Bill submitted

Kalliassery W S Section - AE
Date: 23/01/2024

Work in progress | 67% Completed

10,000 m distribution pipe laying completed. 1960 FHTCs out of 3080 FHTCs completed.CC IVth and part Bill submitted

Kalliassery W S Section - AE
Date: 20/01/2024

Work in progress | 65% Completed

10,000 m distribution pipe laying completed. 1942 FHTCs out of 3080 FHTCs completed

Kalliassery W S Section - AE
Date: 17/01/2024

Work in progress | 65% Completed

10,000 m distribution pipe laying completed. 1920 FHTCs out of 3080 FHTCs completed

Kalliassery W S Section - AE
Date: 08/01/2024

Work in progress | 65% Completed

10,000 m distribution pipe laying completed. 1837 FHTCs out of 3080 FHTCs completed

Kalliassery W S Section - AE
Date: 06/01/2024

Work in progress | 58% Completed

10,000 m distribution pipe laying completed. 1787 FHTCs out of 3080 FHTCs completed

Kalliassery W S Section - AE
Date: 03/01/2024

Work in progress | 56% Completed

10,000 m distribution pipe laying completed. 1716 FHTCs out of 3080 FHTCs completed

Kalliassery W S Section - AE
Date: 31/12/2023

Work in progress | 56% Completed

10,000 m distribution pipe laying completed. 1716 FHTCs out of 3080 FHTCs completed

Kalliassery W S Section - AE
Date: 28/12/2023

Work in progress | 56% Completed

10,000 m distribution pipe laying completed. 1716 FHTCs out of 3080 FHTCs completed.

Kalliassery W S Section - AE
Date: 26/12/2023

Work in progress | 47% Completed

1451 FHTCs out of 3080 FHTCs completed,CC IIIrd & part bill prepared and under scrutiny

Kalliassery W S Section - AE
Date: 18/12/2023

Work in progress | 44% Completed

1341 FHTCs out of 3080 FHTCs completed,CC IIIrd & part bill prepared and under scrutiny

Kalliassery W S Section - AE
Date: 13/12/2023

Work in progress | 44% Completed

1341 FHTCs out of 3080 FHTCs completed,CC IIIrd & part bill prepared and under scrutiny

Kalliassery W S Section - AE
Date: 10/12/2023

Work in progress | 44% Completed

1341 FHTCs out of 3080 FHTCs completed,CC IIIrd & part bill prepared and under scrutiny

Kalliassery W S Section - AE
Date: 30/11/2023

Work in progress | 37% Completed

Work started, 1157 FHTCs out of 3080 FHTCs completed,CC IInd & part bill submitted

Kalliassery W S Section - AE
Date: 25/11/2023

Work in progress | 32% Completed

Work started, 1037 FHTCs out of 3080 FHTCs completed,CC IInd & part bill submitted

Kalliassery W S Section - AE
Date: 18/11/2023

Work in progress | 29% Completed

Work started, 897 FHTCs out of 3080 FHTCs completed,CC IInd & part bill submitted

Kalliassery W S Section - AE
Date: 14/11/2023

Work in progress | 26% Completed

Work started, 788 FHTCs out of 3080 FHTCs completed,CC IInd & part bill submitted

Kalliassery W S Section - AE
Date: 07/11/2023

Work in progress | 25% Completed

Work started, 731 FHTCs out of 3080 FHTCs completed,CC IInd & part bill submitted

Kalliassery W S Section - AE
Date: 02/11/2023

Work in progress | 25% Completed

Work started, 642 FHTCs out of 3080 FHTCs completed,CC IInd & part bill submitted

Kalliassery W S Section - AE
Date: 30/10/2023

Work in progress | 25% Completed

Work started, 640 FHTCs out of 3080 FHTCs completed,CC IInd & part bill submitted

Kalliassery W S Section - AE
Date: 25/10/2023

Work in progress | 25% Completed

Work started, 550 FHTCs out of 3080 FHTCs completed,CC IInd & part bill submitted

Kalliassery W S Section - AE
Date: 19/10/2023

Work in progress | 25% Completed

Work started, 520 FHTCs out of 3080 FHTCs completed,CC IInd & part bill submitted

Kalliassery W S Section - AE
Date: 18/10/2023

Work in progress | 25% Completed

Work started, 490 FHTCs out of 3080 FHTCs completed,CC IInd & part bill submitted

Kalliassery W S Section - AE
Date: 13/10/2023

Work in progress | 25% Completed

Work started, 470 FHTCs out of 3080 FHTCs completed

Kalliassery W S Section - AE
Date: 10/10/2023

Work in progress | 25% Completed

Work started, 450 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 06/10/2023

Work in progress | 23% Completed

Work started, 400 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 30/09/2023

Work in progress | 20% Completed

Work started, 396 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 27/09/2023

Work in progress | 20% Completed

Work started, 396 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 23/09/2023

Work in progress | 20% Completed

Work started, 396 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 19/09/2023

Work in progress | 20% Completed

Work started, 396 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 15/09/2023

Work in progress | 20% Completed

Work started, PVC pipes for distribution line supplied, 396 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 12/09/2023

Work in progress | 20% Completed

Work started, PVC pipes for distribution line supplied, 396 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 08/09/2023

Work in progress | 20% Completed

Work started, PVC pipes for distribution line supplied, 396 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 07/09/2023

Work in progress | 20% Completed

Work started, PVC pipes for distribution line supplied, 396 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 05/09/2023

Work in progress | 20% Completed

Work started, PVC pipes for distribution line supplied, 150 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 01/09/2023

Work in progress | 7% Completed

Work started, PVC pipes for distribution line supplied, 115 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 26/08/2023

Work in progress | 7% Completed

Work started, PVC pipes for distribution line supplied, 115 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 22/08/2023

Work in progress | 7% Completed

Work started, PVC pipes for distribution line supplied, 95 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 17/08/2023

Work in progress | 6% Completed

Work started, PVC pipes for distribution line supplied, 90 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 14/08/2023

Work in progress | 5% Completed

Work started, PVC pipes for distribution line supplied, 80 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 09/08/2023

Work in progress | 5% Completed

Work started, PVC pipes for distribution line supplied, 80 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 07/08/2023

Work in progress | 5% Completed

Work started, PVC pipes for distribution line supplied, 80 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 03/08/2023

Work in progress | 5% Completed

Work started, PVC pipes for distribution line supplied, 80 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 29/07/2023

Work in progress | 5% Completed

Work started, PVC pipes for distribution line supplied, 80 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 25/07/2023

Work in progress | 5% Completed

Work started, PVC pipes for distribution line supplied, 80 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 22/07/2023

Work in progress | 5% Completed

Work started, PVC pipes for distribution line supplied, 80 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 18/07/2023

Work in progress | 5% Completed

Work started, PVC pipes for distribution line supplied, 80 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 13/07/2023

Work in progress | 5% Completed

Work started, PVC pipes for distribution line supplied, 80 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 11/07/2023

Work in progress | 5% Completed

Work started, PVC pipes for distribution line supplied, 80 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 07/07/2023

Work in progress | 5% Completed

Work started, PVC pipes for distribution line supplied, 70 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 04/07/2023

Work in progress | 5% Completed

Work started, PVC pipes for distribution line supplied, 70 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 01/07/2023

Work in progress | 4% Completed

Work started, PVC pipes for distribution line supplied, 60 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 27/06/2023

Work in progress | 4% Completed

Work started, PVC pipes for distribution line supplied, 60 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 22/06/2023

Work in progress | 3% Completed

Work started, PVC pipes for distribution line supplied, 50 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 19/06/2023

Work in progress | 3% Completed

Work started, PVC pipes for distribution line supplied, 50 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 16/06/2023

Work in progress | 3% Completed

Work started, PVC pipes for distribution line supplied, 50 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 13/06/2023

Work in progress | 3% Completed

Work started, PVC pipes for distribution line supplied, 50 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 09/06/2023

Work in progress | 3% Completed

Work started, PVC pipes for distribution line supplied, 50 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 05/06/2023

Work in progress | 3% Completed

Work started, PVC pipes for distribution line supplied, 50 FHTC out of 3080 FHTC completed

Kalliassery W S Section - AE
Date: 01/06/2023

Work in progress | 2% Completed

Work order issued, Agreement executed, site handed over, pipe supplied

Kalliassery W S Section - AE
Date: 29/05/2023

Work in progress | 2% Completed

Work order issued, Agreement executed, site handed over, pipe supplied

Kalliassery W S Section - AE
Date: 26/05/2023

Work in progress | 2% Completed

Work order issued, Agreement executed, site handed over, pipe supplied

Kalliassery W S Section - AE
Date: 23/05/2023

Work in progress | 2% Completed

Work order issued, Agreement executed, site handed over, pipe supplied

Kalliassery W S Section - AE
Date: 20/05/2023

Work in progress | 2% Completed

Work order issued, Agreement executed, site handed over, pipe supplied

Kalliassery W S Section - AE
Date: 16/05/2023

Work in progress | 1% Completed

Work order issued, Agreement executed, site handed over

Kalliassery W S Section - AE
Date: 11/05/2023

Work in progress | 1% Completed

Work order issued, Agreement executed, site handed over

Thaliparamba WS Dn EE
Date: 04/05/2023

Work in progress | 1% Completed

Work order issued, Agreement executed, site handed over

Thaliparamba WS Dn EE
Date: 30/03/2023

Work has started | 0% Completed

Submitted to CE for tender approval