| Project | AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT - KOVOOR ZONE-EXTENSION AND REPLACEMENT OF DISTRIBUTION PIPELINE AND PROVIDING FHTC IN PWD ROADS WARD 22 - KOVOOR AND WARD 18 MAYANAD-Pipeline Work |
|---|---|
| Project Code | CLTAMRUT032313801P60 |
| Type | Package |
| Main Project | AMRUT 1.0-Kozhikode Water Supply Project-Providing FHTCs and Pipe Line extension |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT - KOVOOR ZONE-EXTENSION AND REPLACEMENT OF DISTRIBUTION PIPELINE AND PROVIDING FHTC IN PWD ROADS WARD 22 - KOVOOR AND WARD 18 MAYANAD-Pipeline Work |
| Status | On-going |
| District | Kozhikkode |
| Executing Office | Kozhikode Dist 1 Sn 2 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 15680000 |
| TS Number | 9165/2023-2024 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | 30/09/2024 |
| TS Date | 19 Jul 2023 |
|---|---|
| Estimate Approval | 14 Jul 2023 |
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 20/06/2025 |
Work in progress | 86% Completed
pipe laying completed.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 28/04/2025 |
Work in progress | 81% Completed
work ongoing.