| Kozhikode Dist 1 Sn 2 - AE |
| Date: 20/06/2025 |
Work in progress | 86% Completed
pipe laying completed
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 28/04/2025 |
Work in progress | 81% Completed
work ongoing
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 18/03/2025 |
Work in progress | 80% Completed
work ongoing
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 13/02/2025 |
Work in progress | 71% Completed
Works along corporation roads completed and Work got delayed since PWD Road cutting permission not received.PBG and Chalan submitted.But not approved by PWD
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 16/01/2025 |
Work in progress | 71% Completed
Works along corporation roads completed and Work got delayed since PWD Road cutting permission not received.PBG and Chalan submitted.But not approved by PWD
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 07/12/2024 |
Work in progress | 71% Completed
Works along corporation roads completed and Work got delayed since PWD Road cutting permission not received.PBG and Chalan submitted.But not approved by PWD
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 19/11/2024 |
Work in progress | 70% Completed
Works along corporation roads completed and Work got delayed since PWD Road cutting permission not received.PBG and Chalan submitted.But not approved by PWD
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 06/11/2024 |
Work in progress | 70% Completed
Works along corporation roads completed and Work got delayed since PWD Road cutting permission not received.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 26/10/2024 |
Work in progress | 70% Completed
Works along corporation roads completed and Work got delayed since PWD Road cutting permission not received.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 22/10/2024 |
Work in progress | 70% Completed
Works along corporation roads completed and Work got delayed since PWD Road cutting permission not received.
| Kozhikode Dist 1 Sn 2 - AE |
| Date: 21/08/2024 |
Work in progress | 70% Completed
Work in progress. PWD road cutting permission pending.
| Kozhikode PH Dn EE |
| Date: 21/04/2024 |
Work in progress | 55% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 35% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 20% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 16% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 12% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 12/01/2024 |
Work in progress | 8% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 12/12/2023 |
Work in progress | 7% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 29/11/2023 |
Work in progress | 5% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 31/10/2023 |
Work in progress | 2% Completed
Pipe Supplied