KIIFB-Budget-2017-2018- Project-TRAN 10-WRD 025-05:WSS TO Edayur Panchayath including service level improvement of existing WSS TO Irimbiliyam Panchayath and Valanchery Municipality in Malappuram District.(PACKAGE III:Electro Mechanic Works- Transformers IN RWPH and WTP sites &Pumpsets in RWPH)

Project KIIFB-Budget-2017-2018- Project-TRAN 10-WRD 025-05:WSS TO Edayur Panchayath including service level improvement of existing WSS TO Irimbiliyam Panchayath and Valanchery Municipality in Malappuram District.(PACKAGE III:Electro Mechanic Works- Transformers IN RWPH and WTP sites &Pumpsets in RWPH)
Project Code MLPKIIFB1118553P3
Type Package
Main Project Budget 2017-18-KIIFB-TRAN 10-WRD025-05:WSS to Edayur Panchayath of Malappuram District
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description (PACKAGE III:Electro Mechanic Works - Transformers IN RWPH(750 KVA indoor type-1 no,100KVA indoor type-1no) and WTP site(250KVA out door type-1) &Pumpsets in RWPH 270 HP VT 3nos)
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 35300000
TS Number TS/2019-2020/2019/7644 DATED 24/02/2020
Technical specification Transformers IN RWPH(750 KVA indoor type-1 no,100KVA indoor type-1no) and WTP site(250KVA out door type-1) &Pumpsets in RWPH 270 HP VT 3nos)
Contractor M/S Midland Engg & Const. (Mob: 9496878105)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 12/05/2021
Scheduled date of Completion as per agreement 31 Dec 2023
Expected date of Completion 31/12/2023

Processing Dates

TS Date 24 Feb 2020
Estimate Approval 24 Feb 2020
NIT Approval 02 Nov 2020
Tender Closing 02 Dec 2020
Technichal Pre-Qualification 26 Feb 2021
Price bid opening 22 Mar 2021

Approval Dates

Workorder Date 05 May 2021
NA 14 May 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE3
Date: 03/05/2024

Work in progress | 94% Completed

Construction of Transformer Room Completed. Pump set erection progress. Transformer Supply and erection Completed .

Malappuram Project Dn AE3
Date: 02/05/2024

Work in progress | 94% Completed

Construction of Transformer Room Completed. Pump set erection progress. Transformer Supply and erection Completed .