KIIFB-Budget-2017-2018- Project-TRAN 10-WRD 025-05:WSS TO Edayur Panchayath including service level improvement of existing WSS TO Irimbiliyam Panchayath and Valanchery Municipality in Malappuram District.(PACKAGE III:Electro Mechanic Works- Transformers IN RWPH and WTP sites &Pumpsets in RWPH)
Project |
KIIFB-Budget-2017-2018- Project-TRAN 10-WRD 025-05:WSS TO Edayur Panchayath including service level improvement of existing WSS TO Irimbiliyam Panchayath and Valanchery Municipality in Malappuram District.(PACKAGE III:Electro Mechanic Works- Transformers IN RWPH and WTP sites &Pumpsets in RWPH) |
Project Code |
MLPKIIFB1118553P3 |
Type |
Package |
Main Project |
Budget 2017-18-KIIFB-TRAN 10-WRD025-05:WSS to Edayur Panchayath of Malappuram District
|
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
(PACKAGE III:Electro Mechanic Works
- Transformers IN RWPH(750 KVA indoor type-1 no,100KVA indoor type-1no)
and WTP site(250KVA out door type-1)
&Pumpsets in RWPH 270 HP VT 3nos)
|
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
35300000 |
TS Number |
TS/2019-2020/2019/7644 DATED 24/02/2020 |
Technical specification |
Transformers IN RWPH(750 KVA indoor type-1 no,100KVA indoor type-1no)
and WTP site(250KVA out door type-1)
&Pumpsets in RWPH 270 HP VT 3nos)
|
Contractor |
M/S Midland Engg & Const. (Mob: 9496878105) |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
12/05/2021 |
Scheduled date of Completion as per agreement |
31 Dec 2023 |
Expected date of Completion |
31/12/2023 |
Processing Dates
TS Date |
24 Feb 2020 |
Estimate Approval |
24 Feb 2020 |
NIT Approval |
02 Nov 2020 |
Tender Closing |
02 Dec 2020 |
Technichal Pre-Qualification |
26 Feb 2021 |
Price bid opening |
22 Mar 2021 |
Approval Dates
Workorder Date |
05 May 2021 |
NA |
14 May 2021 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Malappuram Project Dn AE3 |
Date: 03/05/2024 |
Work in progress | 94% Completed
Construction of Transformer Room Completed. Pump set erection progress. Transformer Supply and erection Completed
.
Malappuram Project Dn AE3 |
Date: 02/05/2024 |
Work in progress | 94% Completed
Construction of Transformer Room Completed. Pump set erection progress. Transformer Supply and erection Completed
.