- Home
- KIIFB-Budget-2017-2018- Project -TRAN 10...
KIIFB-Budget-2017-2018- Project -TRAN 10-WAD 025-05-WSS to Edayur Panchayath including service level improvement of existing WSS to Irimbiliyam Panchayath and Valanchery Municipality in Malappuram District(Package-II:Distribution System.
Project |
KIIFB-Budget-2017-2018- Project -TRAN 10-WAD 025-05-WSS to Edayur Panchayath including service level improvement of existing WSS to Irimbiliyam Panchayath and Valanchery Municipality in Malappuram District(Package-II:Distribution System. |
Project Code |
MLPKIIFB1118553P2 |
Type |
Package |
Main Project |
Budget 2017-18-KIIFB-TRAN 10-WRD025-05:WSS to Edayur Panchayath of Malappuram District
|
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
(Package-II:Distribution lines (DI,PVC and GI)to Edayur GP(145 KM) and relaying frequently bursting distribution main 355mm PVC by 400 MM DIpipe (4000m)
............................................................................
Supply Line- 450 mm DI -K9- 4000M/ 350 mm DI K9 -3166M / 300 mm DI K-9 – 2151M
Distribution network – 250 mm DI K9- 6439M 200mm DI K-9- 1063M 100 mm DI K9- 1050M 160mm PVC - 8400M 140mm PVC -24,800M 110 mm PVC – 5780M 90 mm PVC – 87051M
Expected annual revenue – 26,000 KL x Rs 4/KL x 30 days = Rs 31,20,000
Ratio of material and labour -
Total cost of project – Rs 72.20 Crores
Source of funding- KIIFB
Date of AS – 19-11-2018 (KIIFB)
TS Issue Date – 10-07-2020 (Rs. 34,22,00,000 for this package)
Date of tender – 13-07-2020
Work Order Date - 06-11-2020 (27,95,55,783)
Agreement Date –Not Done
Expected date of completion – 05-05-2022
Time overrun in days/weeks - NA
Officer now responsible for execution – EE Project Division Malappuram
|
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
342200000 |
TS Number |
TS/2020-2021/2019/9988 DATED 10/07/2020 |
Technical specification |
Supply Line- 450 mm DI -K9- 4000M/ 350 mm DI K9 -3166M / 300 mm DI K-9 – 2151M
Distribution network – 250 mm DI K9- 6439M 200mm DI K-9- 1063M 100 mm DI K9- 1050M 160mm PVC - 8400M 140mm PVC -24,800M 110 mm PVC – 5780M 90 mm PVC – 87051M |
Contractor |
Mohammed Rasheed K.M (Mob: 9846200115) |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
08/01/2021 |
Scheduled date of Completion as per agreement |
31 May 2023 |
Expected date of Completion |
31/12/2023 |
Processing Dates
TS Date |
10 Jul 2020 |
Estimate Approval |
10 Jul 2020 |
NIT Approval |
13 Jul 2020 |
Tender Closing |
15 Sep 2020 |
Technichal Pre-Qualification |
08 Oct 2020 |
Price bid opening |
08 Oct 2020 |
Approval Dates
Workorder Date |
06 Nov 2020 |
NA |
17 Dec 2020 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Malappuram Project Dn AE3 |
Date: 03/05/2024 |
Work in progress | 93% Completed
13.245 km DI, 108.796 km PVC and 989.8 m GI Pipes are Laid.
.
Malappuram Project Dn AE3 |
Date: 02/05/2024 |
Work in progress | 93% Completed
13.245 km DI, 108.796 km PVC and 989.8 m GI Pipes are Laid.
.