KIIFB-Budget-2017-2018- Project -TRAN 10-WAD 025-05-WSS to Edayur Panchayath including service level improvement of existing WSS to Irimbiliyam Panchayath and Valanchery Municipality in Malappuram District(Package-II:Distribution System.

Project KIIFB-Budget-2017-2018- Project -TRAN 10-WAD 025-05-WSS to Edayur Panchayath including service level improvement of existing WSS to Irimbiliyam Panchayath and Valanchery Municipality in Malappuram District(Package-II:Distribution System.
Project Code MLPKIIFB1118553P2
Type Package
Main Project Budget 2017-18-KIIFB-TRAN 10-WRD025-05:WSS to Edayur Panchayath of Malappuram District
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description (Package-II:Distribution lines (DI,PVC and GI)to Edayur GP(145 KM) and relaying frequently bursting distribution main 355mm PVC by 400 MM DIpipe (4000m) ............................................................................ Supply Line- 450 mm DI -K9- 4000M/ 350 mm DI K9 -3166M / 300 mm DI K-9 – 2151M Distribution network – 250 mm DI K9- 6439M 200mm DI K-9- 1063M 100 mm DI K9- 1050M 160mm PVC - 8400M 140mm PVC -24,800M 110 mm PVC – 5780M 90 mm PVC – 87051M Expected annual revenue – 26,000 KL x Rs 4/KL x 30 days = Rs 31,20,000 Ratio of material and labour - Total cost of project – Rs 72.20 Crores Source of funding- KIIFB Date of AS – 19-11-2018 (KIIFB) TS Issue Date – 10-07-2020 (Rs. 34,22,00,000 for this package) Date of tender – 13-07-2020 Work Order Date - 06-11-2020 (27,95,55,783) Agreement Date –Not Done Expected date of completion – 05-05-2022 Time overrun in days/weeks - NA Officer now responsible for execution – EE Project Division Malappuram
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 342200000
TS Number TS/2020-2021/2019/9988 DATED 10/07/2020
Technical specification Supply Line- 450 mm DI -K9- 4000M/ 350 mm DI K9 -3166M / 300 mm DI K-9 – 2151M Distribution network – 250 mm DI K9- 6439M 200mm DI K-9- 1063M 100 mm DI K9- 1050M 160mm PVC - 8400M 140mm PVC -24,800M 110 mm PVC – 5780M 90 mm PVC – 87051M
Contractor Mohammed Rasheed K.M (Mob: 9846200115)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 08/01/2021
Scheduled date of Completion as per agreement 31 May 2023
Expected date of Completion 31/12/2023

Processing Dates

TS Date 10 Jul 2020
Estimate Approval 10 Jul 2020
NIT Approval 13 Jul 2020
Tender Closing 15 Sep 2020
Technichal Pre-Qualification 08 Oct 2020
Price bid opening 08 Oct 2020

Approval Dates

Workorder Date 06 Nov 2020
NA 17 Dec 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE3
Date: 03/05/2024

Work in progress | 93% Completed

13.245 km DI, 108.796 km PVC and 989.8 m GI Pipes are Laid. .

Malappuram Project Dn AE3
Date: 02/05/2024

Work in progress | 93% Completed

13.245 km DI, 108.796 km PVC and 989.8 m GI Pipes are Laid. .