| Project | AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT - Balamandiram Zone IV-Pipeline Extension and Providing FHTC in Chevarambalam,Civil station wards -Pipeline Work |
|---|---|
| Project Code | CLTAMRUT032313801P11 |
| Type | Package |
| Main Project | AMRUT 1.0-Kozhikode Water Supply Project-Providing FHTCs and Pipe Line extension |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT - Balamandiram Zone IV-Pipeline Extension and Providing FHTC in Chevarambalam,Civil station wards -Pipeline Work |
| Status | On-going |
| District | Kozhikkode |
| Executing Office | Kozhikode Dist Sn 4 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 18672300 |
| TS Number | 16131/2022-2023 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | 09 Jan 2024 |
| Expected date of Completion | 30/11/2024 |
| TS Date | 13 Mar 2023 |
|---|---|
| Estimate Approval | 13 Mar 2023 |
| NIT Approval | 13 Mar 2023 |
| Tender Closing | 25 Mar 2023 |
| NA | 31 Mar 2023 |
|---|
| Kozhikode PH Dn EE |
| Date: 25/12/2024 |
Work has been completed | 100% Completed
Pipe (110mm) laying work completed - 1500m. 401 FHTC has been Given.
| Kozhikode PH Dn EE |
| Date: 18/12/2024 |
Work in progress | 98% Completed
Pipe (110mm) laying work completed - 1500m. FHTC 314 Given.