| Kozhikode PH Dn EE |
| Date: 25/12/2024 |
Work has been completed | 100% Completed
Pipe (110mm) laying work completed - 1500m. 401 FHTC has been Given
| Kozhikode PH Dn EE |
| Date: 18/12/2024 |
Work in progress | 98% Completed
Pipe (110mm) laying work completed - 1500m. FHTC 314 Given
| Kozhikode PH Dn EE |
| Date: 16/12/2024 |
Work in progress | 98% Completed
Pipe (110mm) laying work completed - 1500m. FHTC 313 Given
| Kozhikode PH Dn EE |
| Date: 13/12/2024 |
Work in progress | 98% Completed
Pipe (110mm) laying work completed - 1500m. FHTC 311 Given
| Kozhikode PH Dn EE |
| Date: 10/12/2024 |
Work in progress | 98% Completed
Pipe (110mm) laying work completed - 1500m. FHTC 309 Given
| Kozhikode PH Dn EE |
| Date: 07/12/2024 |
Work in progress | 98% Completed
Pipe (110mm) laying work completed - 1500m. FHTC 307 Given
| Kozhikode PH Dn EE |
| Date: 02/12/2024 |
Work in progress | 98% Completed
Pipe (110mm) laying work completed - 1500m. FHTC 307 Given
| Kozhikode PH Dn EE |
| Date: 29/11/2024 |
Work in progress | 98% Completed
Pipe (110mm) laying work completed - 1500m. FHTC 307 Given
| Kozhikode PH Dn EE |
| Date: 25/11/2024 |
Work in progress | 98% Completed
Pipe (110mm) laying work completed - 1500m. FHTC 307 Given
| Kozhikode PH Dn EE |
| Date: 23/11/2024 |
Work in progress | 98% Completed
Pipe (110mm) laying work completed - 1500m. FHTC 304 Given
| Kozhikode PH Dn EE |
| Date: 21/11/2024 |
Work in progress | 98% Completed
Pipe (110mm) laying work completed - 1500m. FHTC 300 Given
| Kozhikode PH Dn EE |
| Date: 18/11/2024 |
Work in progress | 98% Completed
Pipe (110mm) laying work completed - 1500m. FHTC 292 Given
| Kozhikode PH Dn EE |
| Date: 14/11/2024 |
Work in progress | 98% Completed
Pipe (110mm) laying work completed - 1500m. FHTC 288 Given
| Kozhikode PH Dn EE |
| Date: 11/11/2024 |
Work in progress | 98% Completed
Pipe (110mm) laying work completed - 1500m. FHTC 283 Given
| Kozhikode PH Dn EE |
| Date: 08/11/2024 |
Work in progress | 98% Completed
Pipe (110mm) laying work completed - 1500m. FHTC 281 Given
| Kozhikode PH Dn EE |
| Date: 04/11/2024 |
Work in progress | 98% Completed
Pipe (110mm) laying work completed - 1500m. FHTC 274 Given
| Kozhikode PH Dn EE |
| Date: 31/10/2024 |
Work in progress | 98% Completed
Pipe (110mm) laying work completed - 1500m. FHTC 274 Given
| Kozhikode PH Dn EE |
| Date: 29/10/2024 |
Work in progress | 98% Completed
Restoration work in progress- FHTCs-277 Nos - Pipe (110mm) laying work completed - 1500m
| Kozhikode PH Dn EE |
| Date: 24/10/2024 |
Work in progress | 98% Completed
Restoration work in progress- FHTCs-277 Nos - Pipe (110mm) laying work completed - 1500m
| Kozhikode PH Dn EE |
| Date: 21/10/2024 |
Work in progress | 98% Completed
Restoration work in progress- FHTCs-277 Nos - Pipe (110mm) laying work completed - 1500m
| Kozhikode PH Dn EE |
| Date: 17/10/2024 |
Work in progress | 98% Completed
Restoration work in progress- FHTCs-277 Nos - Pipe (110mm) laying work completed - 1500m
| Kozhikode PH Dn EE |
| Date: 14/10/2024 |
Work in progress | 98% Completed
Restoration work in progress- FHTCs-277 Nos - Pipe (110mm) laying work completed - 1500m
| Kozhikode PH Dn EE |
| Date: 10/10/2024 |
Work in progress | 98% Completed
Restoration work in progress- FHTCs-277 Nos - Pipe (110mm) laying work completed - 1500m
| Kozhikode PH Dn EE |
| Date: 07/10/2024 |
Work in progress | 98% Completed
Restoration work in progress- FHTCs-277 Nos - Pipe (110mm) laying work completed - 1500m
| Kozhikode PH Dn EE |
| Date: 03/10/2024 |
Work in progress | 98% Completed
Restoration work in progress- FHTCs-277 Nos - Pipe (110mm) laying work completed - 1500m
| Kozhikode PH Dn EE |
| Date: 30/09/2024 |
Work in progress | 98% Completed
Restoration work in progress- FHTCs-274 Nos - Pipe (110mm) laying work completed - 1500m
| Kozhikode PH Dn EE |
| Date: 27/09/2024 |
Work in progress | 98% Completed
Restoration work in progress- FHTCs-271 Nos - Pipe (110mm) laying work completed - 1500m
| Kozhikode PH Dn EE |
| Date: 25/09/2024 |
Work in progress | 98% Completed
Restoration work in progress- FHTCs-267 Nos - Pipe (110mm) laying work completed - 1500m
| Kozhikode PH Dn EE |
| Date: 23/09/2024 |
Work in progress | 98% Completed
Restoration work in progress- FHTCs-264 Nos - Pipe (110mm) laying work completed - 1500m
| Kozhikode PH Dn EE |
| Date: 20/09/2024 |
Work in progress | 98% Completed
Restoration work in progress- FHTCs-261 Nos - Pipe (110mm) laying work completed - 1500m
| Kozhikode PH Dn EE |
| Date: 17/09/2024 |
Work in progress | 98% Completed
Restoration work in progress- FHTCs-258 Nos - Pipe (110mm) laying work completed - 1500m
| Kozhikode PH Dn EE |
| Date: 13/09/2024 |
Work in progress | 98% Completed
Restoration work in progress- FHTCs-250 Nos - Pipe (110mm) laying work completed - 1500m
| Kozhikode PH Dn EE |
| Date: 10/09/2024 |
Work in progress | 98% Completed
Restoration work in progress- FHTCs-247 Nos - Pipe (110mm) laying work completed - 1500m - Requested to time extension
| Kozhikode PH Dn EE |
| Date: 06/09/2024 |
Work in progress | 98% Completed
Restoration work in progress- FHTCs-247 Nos - Pipe (110mm) laying work completed - 1500m - Requested to time extension
| Kozhikode PH Dn EE |
| Date: 03/09/2024 |
Work in progress | 98% Completed
Restoration work in progress- FHTCs-247 Nos - Pipe (110mm) laying work completed - 1500m - Requested to time extension
| Kozhikode PH Dn EE |
| Date: 30/08/2024 |
Work in progress | 98% Completed
Restoration work in progress- FHTCs-247 Nos - Pipe (110mm) laying work completed
| Kozhikode PH Dn EE |
| Date: 24/08/2024 |
Work in progress | 98% Completed
work on going
| Kozhikode PH Dn EE |
| Date: 23/08/2024 |
Work in progress | 98% Completed
work on going
| Kozhikode PH Dn EE |
| Date: 22/08/2024 |
Work in progress | 97% Completed
work on going
| Kozhikode PH Dn EE |
| Date: 21/08/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laying and restoration works completed. Fhtcs Work in progress
| Kozhikode PH Dn EE |
| Date: 19/08/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laying and restoration works completed. Fhtcs Work in progress
| Kozhikode PH Dn EE |
| Date: 16/08/2024 |
Work in progress | 97% Completed
Work in progress. Pipe laying and restoration works completed. Fhtcs Work in progress
| Kozhikode PH Dn EE |
| Date: 25/06/2024 |
Work in progress | 97% Completed
Pipe laid-110mm PVC -1500m, FHTCs-120 nos.
| Kozhikode PH Dn EE |
| Date: 24/06/2024 |
Work in progress | 97% Completed
Pipe laid-110mm PVC -1500m, FHTCs-120 nos.
| Kozhikode PH Dn EE |
| Date: 14/06/2024 |
Work in progress | 97% Completed
pipe laid-110 mm PVC-1500m
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 97% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 95% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 92% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 05/03/2024 |
Work in progress | 89% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 04/03/2024 |
Work in progress | 89% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 03/03/2024 |
Work in progress | 89% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 02/03/2024 |
Work in progress | 88% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 01/03/2024 |
Work in progress | 88% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 26/02/2024 |
Work in progress | 86% Completed
work in process
| Kozhikode PH Dn EE |
| Date: 24/02/2024 |
Work in progress | 86% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 23/02/2024 |
Work in progress | 86% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 22/02/2024 |
Work in progress | 86% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 21/02/2024 |
Work in progress | 86% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 85% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 31/01/2024 |
Work in progress | 79% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 30/01/2024 |
Work in progress | 78% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 29/01/2024 |
Work in progress | 78% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 78% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 22/01/2024 |
Work in progress | 76% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 21/01/2024 |
Work in progress | 76% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 20/01/2024 |
Work in progress | 76% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 19/01/2024 |
Work in progress | 76% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 18/01/2024 |
Work in progress | 76% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 17/01/2024 |
Work in progress | 76% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 16/01/2024 |
Work in progress | 75% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 15/01/2024 |
Work in progress | 75% Completed
WORK IN PROGRESS
| Kozhikode PH Dn EE |
| Date: 14/01/2024 |
Work in progress | 75% Completed
WORK IN PROGRESS
| Kozhikode PH Dn EE |
| Date: 13/01/2024 |
Work in progress | 75% Completed
WORK IN PROGRESS
| Kozhikode PH Dn EE |
| Date: 12/01/2024 |
Work in progress | 75% Completed
WORK IN PROGRESS
| Kozhikode PH Dn EE |
| Date: 11/01/2024 |
Work in progress | 75% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 10/01/2024 |
Work in progress | 66% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 07/01/2024 |
Work in progress | 66% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 06/01/2024 |
Work in progress | 66% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 05/01/2024 |
Work in progress | 66% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 04/01/2024 |
Work in progress | 66% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 03/01/2024 |
Work in progress | 66% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 02/01/2024 |
Work in progress | 66% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 01/01/2024 |
Work in progress | 66% Completed
work in progress
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work in progress | 65% Completed
pipe laid 110 mm 1376.5 m
| Kozhikode PH Dn EE |
| Date: 28/11/2023 |
Work in progress | 60% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 09/11/2023 |
Work in progress | 52% Completed
work started
| Kozhikode PH Dn EE |
| Date: 27/10/2023 |
Work in progress | 50% Completed
work started
| Kozhikode PH Dn EE |
| Date: 17/10/2023 |
Work in progress | 45% Completed
work started
| Kozhikode PH Dn EE |
| Date: 15/09/2023 |
Work in progress | 35% Completed
Pipe laying started
| Kozhikode PH Dn EE |
| Date: 05/09/2023 |
Work in progress | 30% Completed
Pipe laying started
| Kozhikode PH Dn EE |
| Date: 17/08/2023 |
Work in progress | 15% Completed
Pipe laying started
| Kozhikode PH Dn EE |
| Date: 07/08/2023 |
Work in progress | 10% Completed
Pipe laying started
| Kozhikode PH Dn EE |
| Date: 27/07/2023 |
Work in progress | 5% Completed
Pipe laying started
| Kozhikode PH Dn EE |
| Date: 24/07/2023 |
Work has started | 0% Completed
Site Handed Over
| Kozhikode PH Dn EE |
| Date: 12/07/2023 |
Work has started | 0% Completed
Work Order Issued. Not Yet Started
| Kozhikode PH Dn EE |
| Date: 05/07/2023 |
Work has started | 0% Completed
Work Order Issued. Not Yet Started
| Kozhikode PH Dn EE |
| Date: 30/06/2023 |
Work has started | 0% Completed
Work Order Issued. Not Yet Started
| Kozhikode PH Dn EE |
| Date: 20/06/2023 |
Work has started | 0% Completed
Work Order Issued. Not Yet Started
| Kozhikode PH Dn EE |
| Date: 13/06/2023 |
Work has started | 0% Completed
Work Order Issued. Not Yet Started
| Kozhikode PH Dn EE |
| Date: 08/06/2023 |
Work has started | 0% Completed
Work Order Issued. Not Yet Started
| Kozhikode PH Dn EE |
| Date: 05/06/2023 |
Work in progress | 1% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 01/06/2023 |
Work in progress | 1% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 26/05/2023 |
Work in progress | 1% Completed
Agreement Executed