Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Kozhikode PH Dn EE
Date: 25/12/2024

Work has been completed | 100% Completed

Pipe (110mm) laying work completed - 1500m. 401 FHTC has been Given

Kozhikode PH Dn EE
Date: 18/12/2024

Work in progress | 98% Completed

Pipe (110mm) laying work completed - 1500m. FHTC 314 Given

Kozhikode PH Dn EE
Date: 16/12/2024

Work in progress | 98% Completed

Pipe (110mm) laying work completed - 1500m. FHTC 313 Given

Kozhikode PH Dn EE
Date: 13/12/2024

Work in progress | 98% Completed

Pipe (110mm) laying work completed - 1500m. FHTC 311 Given

Kozhikode PH Dn EE
Date: 10/12/2024

Work in progress | 98% Completed

Pipe (110mm) laying work completed - 1500m. FHTC 309 Given

Kozhikode PH Dn EE
Date: 07/12/2024

Work in progress | 98% Completed

Pipe (110mm) laying work completed - 1500m. FHTC 307 Given

Kozhikode PH Dn EE
Date: 02/12/2024

Work in progress | 98% Completed

Pipe (110mm) laying work completed - 1500m. FHTC 307 Given

Kozhikode PH Dn EE
Date: 29/11/2024

Work in progress | 98% Completed

Pipe (110mm) laying work completed - 1500m. FHTC 307 Given

Kozhikode PH Dn EE
Date: 25/11/2024

Work in progress | 98% Completed

Pipe (110mm) laying work completed - 1500m. FHTC 307 Given

Kozhikode PH Dn EE
Date: 23/11/2024

Work in progress | 98% Completed

Pipe (110mm) laying work completed - 1500m. FHTC 304 Given

Kozhikode PH Dn EE
Date: 21/11/2024

Work in progress | 98% Completed

Pipe (110mm) laying work completed - 1500m. FHTC 300 Given

Kozhikode PH Dn EE
Date: 18/11/2024

Work in progress | 98% Completed

Pipe (110mm) laying work completed - 1500m. FHTC 292 Given

Kozhikode PH Dn EE
Date: 14/11/2024

Work in progress | 98% Completed

Pipe (110mm) laying work completed - 1500m. FHTC 288 Given

Kozhikode PH Dn EE
Date: 11/11/2024

Work in progress | 98% Completed

Pipe (110mm) laying work completed - 1500m. FHTC 283 Given

Kozhikode PH Dn EE
Date: 08/11/2024

Work in progress | 98% Completed

Pipe (110mm) laying work completed - 1500m. FHTC 281 Given

Kozhikode PH Dn EE
Date: 04/11/2024

Work in progress | 98% Completed

Pipe (110mm) laying work completed - 1500m. FHTC 274 Given

Kozhikode PH Dn EE
Date: 31/10/2024

Work in progress | 98% Completed

Pipe (110mm) laying work completed - 1500m. FHTC 274 Given

Kozhikode PH Dn EE
Date: 29/10/2024

Work in progress | 98% Completed

Restoration work in progress- FHTCs-277 Nos - Pipe (110mm) laying work completed - 1500m

Kozhikode PH Dn EE
Date: 24/10/2024

Work in progress | 98% Completed

Restoration work in progress- FHTCs-277 Nos - Pipe (110mm) laying work completed - 1500m

Kozhikode PH Dn EE
Date: 21/10/2024

Work in progress | 98% Completed

Restoration work in progress- FHTCs-277 Nos - Pipe (110mm) laying work completed - 1500m

Kozhikode PH Dn EE
Date: 17/10/2024

Work in progress | 98% Completed

Restoration work in progress- FHTCs-277 Nos - Pipe (110mm) laying work completed - 1500m

Kozhikode PH Dn EE
Date: 14/10/2024

Work in progress | 98% Completed

Restoration work in progress- FHTCs-277 Nos - Pipe (110mm) laying work completed - 1500m

Kozhikode PH Dn EE
Date: 10/10/2024

Work in progress | 98% Completed

Restoration work in progress- FHTCs-277 Nos - Pipe (110mm) laying work completed - 1500m

Kozhikode PH Dn EE
Date: 07/10/2024

Work in progress | 98% Completed

Restoration work in progress- FHTCs-277 Nos - Pipe (110mm) laying work completed - 1500m

Kozhikode PH Dn EE
Date: 03/10/2024

Work in progress | 98% Completed

Restoration work in progress- FHTCs-277 Nos - Pipe (110mm) laying work completed - 1500m

Kozhikode PH Dn EE
Date: 30/09/2024

Work in progress | 98% Completed

Restoration work in progress- FHTCs-274 Nos - Pipe (110mm) laying work completed - 1500m

Kozhikode PH Dn EE
Date: 27/09/2024

Work in progress | 98% Completed

Restoration work in progress- FHTCs-271 Nos - Pipe (110mm) laying work completed - 1500m

Kozhikode PH Dn EE
Date: 25/09/2024

Work in progress | 98% Completed

Restoration work in progress- FHTCs-267 Nos - Pipe (110mm) laying work completed - 1500m

Kozhikode PH Dn EE
Date: 23/09/2024

Work in progress | 98% Completed

Restoration work in progress- FHTCs-264 Nos - Pipe (110mm) laying work completed - 1500m

Kozhikode PH Dn EE
Date: 20/09/2024

Work in progress | 98% Completed

Restoration work in progress- FHTCs-261 Nos - Pipe (110mm) laying work completed - 1500m

Kozhikode PH Dn EE
Date: 17/09/2024

Work in progress | 98% Completed

Restoration work in progress- FHTCs-258 Nos - Pipe (110mm) laying work completed - 1500m

Kozhikode PH Dn EE
Date: 13/09/2024

Work in progress | 98% Completed

Restoration work in progress- FHTCs-250 Nos - Pipe (110mm) laying work completed - 1500m

Kozhikode PH Dn EE
Date: 10/09/2024

Work in progress | 98% Completed

Restoration work in progress- FHTCs-247 Nos - Pipe (110mm) laying work completed - 1500m - Requested to time extension

Kozhikode PH Dn EE
Date: 06/09/2024

Work in progress | 98% Completed

Restoration work in progress- FHTCs-247 Nos - Pipe (110mm) laying work completed - 1500m - Requested to time extension

Kozhikode PH Dn EE
Date: 03/09/2024

Work in progress | 98% Completed

Restoration work in progress- FHTCs-247 Nos - Pipe (110mm) laying work completed - 1500m - Requested to time extension

Kozhikode PH Dn EE
Date: 30/08/2024

Work in progress | 98% Completed

Restoration work in progress- FHTCs-247 Nos - Pipe (110mm) laying work completed

Kozhikode PH Dn EE
Date: 24/08/2024

Work in progress | 98% Completed

work on going

Kozhikode PH Dn EE
Date: 23/08/2024

Work in progress | 98% Completed

work on going

Kozhikode PH Dn EE
Date: 22/08/2024

Work in progress | 97% Completed

work on going

Kozhikode PH Dn EE
Date: 21/08/2024

Work in progress | 97% Completed

Work in progress. Pipe laying and restoration works completed. Fhtcs Work in progress

Kozhikode PH Dn EE
Date: 19/08/2024

Work in progress | 97% Completed

Work in progress. Pipe laying and restoration works completed. Fhtcs Work in progress

Kozhikode PH Dn EE
Date: 16/08/2024

Work in progress | 97% Completed

Work in progress. Pipe laying and restoration works completed. Fhtcs Work in progress

Kozhikode PH Dn EE
Date: 25/06/2024

Work in progress | 97% Completed

Pipe laid-110mm PVC -1500m, FHTCs-120 nos.

Kozhikode PH Dn EE
Date: 24/06/2024

Work in progress | 97% Completed

Pipe laid-110mm PVC -1500m, FHTCs-120 nos.

Kozhikode PH Dn EE
Date: 14/06/2024

Work in progress | 97% Completed

pipe laid-110 mm PVC-1500m

Kozhikode PH Dn EE
Date: 20/04/2024

Work in progress | 97% Completed

Work in progress

Kozhikode PH Dn EE
Date: 04/04/2024

Work in progress | 95% Completed

Work in progress

Kozhikode PH Dn EE
Date: 12/03/2024

Work in progress | 92% Completed

Work in progress

Kozhikode PH Dn EE
Date: 05/03/2024

Work in progress | 89% Completed

work in progress

Kozhikode PH Dn EE
Date: 04/03/2024

Work in progress | 89% Completed

work in progress

Kozhikode PH Dn EE
Date: 03/03/2024

Work in progress | 89% Completed

work in progress

Kozhikode PH Dn EE
Date: 02/03/2024

Work in progress | 88% Completed

work in progress

Kozhikode PH Dn EE
Date: 01/03/2024

Work in progress | 88% Completed

Work in progress

Kozhikode PH Dn EE
Date: 26/02/2024

Work in progress | 86% Completed

work in process

Kozhikode PH Dn EE
Date: 24/02/2024

Work in progress | 86% Completed

work in progress

Kozhikode PH Dn EE
Date: 23/02/2024

Work in progress | 86% Completed

work in progress

Kozhikode PH Dn EE
Date: 22/02/2024

Work in progress | 86% Completed

work in progress

Kozhikode PH Dn EE
Date: 21/02/2024

Work in progress | 86% Completed

work in progress

Kozhikode PH Dn EE
Date: 14/02/2024

Work in progress | 85% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 31/01/2024

Work in progress | 79% Completed

work in progress

Kozhikode PH Dn EE
Date: 30/01/2024

Work in progress | 78% Completed

Work in progress

Kozhikode PH Dn EE
Date: 29/01/2024

Work in progress | 78% Completed

Work in progress

Kozhikode PH Dn EE
Date: 27/01/2024

Work in progress | 78% Completed

Work in progress

Kozhikode PH Dn EE
Date: 22/01/2024

Work in progress | 76% Completed

work in progress

Kozhikode PH Dn EE
Date: 21/01/2024

Work in progress | 76% Completed

work in progress

Kozhikode PH Dn EE
Date: 20/01/2024

Work in progress | 76% Completed

work in progress

Kozhikode PH Dn EE
Date: 19/01/2024

Work in progress | 76% Completed

work in progress

Kozhikode PH Dn EE
Date: 18/01/2024

Work in progress | 76% Completed

work in progress

Kozhikode PH Dn EE
Date: 17/01/2024

Work in progress | 76% Completed

work in progress

Kozhikode PH Dn EE
Date: 16/01/2024

Work in progress | 75% Completed

work in progress

Kozhikode PH Dn EE
Date: 15/01/2024

Work in progress | 75% Completed

WORK IN PROGRESS

Kozhikode PH Dn EE
Date: 14/01/2024

Work in progress | 75% Completed

WORK IN PROGRESS

Kozhikode PH Dn EE
Date: 13/01/2024

Work in progress | 75% Completed

WORK IN PROGRESS

Kozhikode PH Dn EE
Date: 12/01/2024

Work in progress | 75% Completed

WORK IN PROGRESS

Kozhikode PH Dn EE
Date: 11/01/2024

Work in progress | 75% Completed

work in progress

Kozhikode PH Dn EE
Date: 10/01/2024

Work in progress | 66% Completed

work in progress

Kozhikode PH Dn EE
Date: 07/01/2024

Work in progress | 66% Completed

work in progress

Kozhikode PH Dn EE
Date: 06/01/2024

Work in progress | 66% Completed

work in progress

Kozhikode PH Dn EE
Date: 05/01/2024

Work in progress | 66% Completed

work in progress

Kozhikode PH Dn EE
Date: 04/01/2024

Work in progress | 66% Completed

work in progress

Kozhikode PH Dn EE
Date: 03/01/2024

Work in progress | 66% Completed

work in progress

Kozhikode PH Dn EE
Date: 02/01/2024

Work in progress | 66% Completed

work in progress

Kozhikode PH Dn EE
Date: 01/01/2024

Work in progress | 66% Completed

work in progress

Kozhikode PH Dn EE
Date: 11/12/2023

Work in progress | 65% Completed

pipe laid 110 mm 1376.5 m

Kozhikode PH Dn EE
Date: 28/11/2023

Work in progress | 60% Completed

Work in progress

Kozhikode PH Dn EE
Date: 09/11/2023

Work in progress | 52% Completed

work started

Kozhikode PH Dn EE
Date: 27/10/2023

Work in progress | 50% Completed

work started

Kozhikode PH Dn EE
Date: 17/10/2023

Work in progress | 45% Completed

work started

Kozhikode PH Dn EE
Date: 15/09/2023

Work in progress | 35% Completed

Pipe laying started

Kozhikode PH Dn EE
Date: 05/09/2023

Work in progress | 30% Completed

Pipe laying started

Kozhikode PH Dn EE
Date: 17/08/2023

Work in progress | 15% Completed

Pipe laying started

Kozhikode PH Dn EE
Date: 07/08/2023

Work in progress | 10% Completed

Pipe laying started

Kozhikode PH Dn EE
Date: 27/07/2023

Work in progress | 5% Completed

Pipe laying started

Kozhikode PH Dn EE
Date: 24/07/2023

Work has started | 0% Completed

Site Handed Over

Kozhikode PH Dn EE
Date: 12/07/2023

Work has started | 0% Completed

Work Order Issued. Not Yet Started

Kozhikode PH Dn EE
Date: 05/07/2023

Work has started | 0% Completed

Work Order Issued. Not Yet Started

Kozhikode PH Dn EE
Date: 30/06/2023

Work has started | 0% Completed

Work Order Issued. Not Yet Started

Kozhikode PH Dn EE
Date: 20/06/2023

Work has started | 0% Completed

Work Order Issued. Not Yet Started

Kozhikode PH Dn EE
Date: 13/06/2023

Work has started | 0% Completed

Work Order Issued. Not Yet Started

Kozhikode PH Dn EE
Date: 08/06/2023

Work has started | 0% Completed

Work Order Issued. Not Yet Started

Kozhikode PH Dn EE
Date: 05/06/2023

Work in progress | 1% Completed

Agreement Executed

Kozhikode PH Dn EE
Date: 01/06/2023

Work in progress | 1% Completed

Agreement Executed

Kozhikode PH Dn EE
Date: 26/05/2023

Work in progress | 1% Completed

Agreement Executed