Thaliparamba WS Section
Date: 28/09/2026

Work in progress | 75% Completed

ank structure completed. Handrails work and vertical pipe works completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 780 connections given.

Thaliparamba WS Section
Date: 02/07/2026

Work in progress | 65% Completed

Tank top slab work completed. vertical pipe work and handrail work started. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 345 connections given.

Thaliparamba WS Section
Date: 25/06/2026

Work in progress | 65% Completed

Tank top slab work completed. vertical pipe work and handrail work started. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 345 connections given.

Thaliparamba WS Section
Date: 09/06/2026

Work in progress | 64% Completed

Tank top slab work completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 345 connections given.

Thaliparamba WS Section
Date: 12/05/2026

Work in progress | 64% Completed

tank wall up to top slab completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 225 connections given

Thaliparamba WS Section
Date: 24/04/2026

Work in progress | 60% Completed

Tank wall up to 1.8m completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 160 connections given.

Thaliparamba WS Section
Date: 07/04/2026

Work in progress | 50% Completed

Deck slab concrete work completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 160 FHTC given.

Thaliparamba WS Section
Date: 27/03/2026

Work in progress | 50% Completed

Deck slab concrete work completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 160 FHTC given.

Thaliparamba WS Section
Date: 13/03/2026

Work in progress | 40% Completed

Deck slab concrete work completed. PVC pipe laid for 2.3km. DI pipe laying started. 120 FHTC completed.

Thaliparamba WS Section
Date: 04/03/2026

Work in progress | 26% Completed

Deck slab reinforcement work completed. PVC pipe laid for 2.3km. DI pipe laying started.

Thaliparamba WS Section
Date: 21/02/2026

Work in progress | 25% Completed

Tank work upto deck beam completed. PVC pipe laid for 2km. DI laying from tank and PVC distribution work started

Thaliparamba WS Section
Date: 16/02/2026

Work in progress | 25% Completed

Tank work upto deck beam completed. PVC pipe laid for 2km. DI laying from tank and PVC distribution work started

Thaliparamba WS Section
Date: 06/02/2026

Work in progress | 25% Completed

Tank work upto deck beam completed. PVC pipe laid for 2km. DI laying from tank and PVC distribution work started

Thaliparamba WS Section
Date: 28/01/2026

Work in progress | 10% Completed

Tank work uptodeck beam completed. PVC pipe laid for 2km. DI laying from tank and PVC distribution work started

Thaliparamba WS Section
Date: 23/01/2026

Work in progress | 10% Completed

Tank work upto second brace beam completed. PVC pipe laid for 2km. DI laying from tank and PVC distribution work started

Thaliparamba WS Section
Date: 17/01/2026

Work in progress | 10% Completed

Tank work upto second brace beam completed. PVC pipe laid for 2km

Thaliparamba WS Section
Date: 12/01/2026

Work in progress | 5% Completed

Second brace beam work completed

Thaliparamba WS Dn EE
Date: 09/01/2026

Work in progress | 4% Completed

4% completed

Thaliparamba WS Section
Date: 07/01/2026

Work in progress | 4% Completed

Second brace beam work completed

Thaliparamba WS Section
Date: 31/12/2025

Work in progress | 4% Completed

Second brace beam work completed

Thaliparamba WS Section
Date: 22/12/2025

Work in progress | 4% Completed

First brace beam work completed

Thaliparamba WS Section
Date: 15/12/2025

Work in progress | 4% Completed

First brace beam work started

Thaliparamba WS Section
Date: 01/12/2025

Work in progress | 2% Completed

Reinforcement for column work started

Thaliparamba WS Section
Date: 22/11/2025

Work in progress | 2% Completed

Plinth beam work started

Thaliparamba WS Section
Date: 13/11/2025

Work in progress | 2% Completed

Reinforcement for foundation completed

Thaliparamba WS Section
Date: 04/11/2025

Work in progress | 1% Completed

PCC for foundation completed

Thaliparamba WS Section
Date: 28/10/2025

Work in progress | 1% Completed

foundation excavation work completed

Thaliparamba WS Section
Date: 22/10/2025

Work in progress | 0% Completed

foundation excavation work completed

Thaliparamba WS Section
Date: 15/10/2025

Work in progress | 0% Completed

Excavation for foundation work started.

Thaliparamba WS Section
Date: 23/09/2025

Work in progress | 0% Completed

Work started.

Thaliparamba WS Section
Date: 04/08/2025

Work in progress | 0% Completed

Site handed over on

Thaliparamba WS Dn EE
Date: 28/06/2025

Work has started | 0% Completed

Tender Scrutiny