| Thaliparamba WS Section |
| Date: 28/09/2026 |
Work in progress | 75% Completed
ank structure completed. Handrails work and vertical pipe works completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 780 connections given.
| Thaliparamba WS Section |
| Date: 02/07/2026 |
Work in progress | 65% Completed
Tank top slab work completed. vertical pipe work and handrail work started. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 345 connections given.
| Thaliparamba WS Section |
| Date: 25/06/2026 |
Work in progress | 65% Completed
Tank top slab work completed. vertical pipe work and handrail work started. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 345 connections given.
| Thaliparamba WS Section |
| Date: 09/06/2026 |
Work in progress | 64% Completed
Tank top slab work completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 345 connections given.
| Thaliparamba WS Section |
| Date: 12/05/2026 |
Work in progress | 64% Completed
tank wall up to top slab completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 225 connections given
| Thaliparamba WS Section |
| Date: 24/04/2026 |
Work in progress | 60% Completed
Tank wall up to 1.8m completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 160 connections given.
| Thaliparamba WS Section |
| Date: 07/04/2026 |
Work in progress | 50% Completed
Deck slab concrete work completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 160 FHTC given.
| Thaliparamba WS Section |
| Date: 27/03/2026 |
Work in progress | 50% Completed
Deck slab concrete work completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 160 FHTC given.
| Thaliparamba WS Section |
| Date: 13/03/2026 |
Work in progress | 40% Completed
Deck slab concrete work completed. PVC pipe laid for 2.3km. DI pipe laying started. 120 FHTC completed.
| Thaliparamba WS Section |
| Date: 04/03/2026 |
Work in progress | 26% Completed
Deck slab reinforcement work completed. PVC pipe laid for 2.3km. DI pipe laying started.
| Thaliparamba WS Section |
| Date: 21/02/2026 |
Work in progress | 25% Completed
Tank work upto deck beam completed. PVC pipe laid for 2km. DI laying from tank and PVC distribution work started
| Thaliparamba WS Section |
| Date: 16/02/2026 |
Work in progress | 25% Completed
Tank work upto deck beam completed. PVC pipe laid for 2km. DI laying from tank and PVC distribution work started
| Thaliparamba WS Section |
| Date: 06/02/2026 |
Work in progress | 25% Completed
Tank work upto deck beam completed. PVC pipe laid for 2km. DI laying from tank and PVC distribution work started
| Thaliparamba WS Section |
| Date: 28/01/2026 |
Work in progress | 10% Completed
Tank work uptodeck beam completed. PVC pipe laid for 2km. DI laying from tank and PVC distribution work started
| Thaliparamba WS Section |
| Date: 23/01/2026 |
Work in progress | 10% Completed
Tank work upto second brace beam completed. PVC pipe laid for 2km. DI laying from tank and PVC distribution work started
| Thaliparamba WS Section |
| Date: 17/01/2026 |
Work in progress | 10% Completed
Tank work upto second brace beam completed. PVC pipe laid for 2km
| Thaliparamba WS Section |
| Date: 12/01/2026 |
Work in progress | 5% Completed
Second brace beam work completed
| Thaliparamba WS Dn EE |
| Date: 09/01/2026 |
Work in progress | 4% Completed
4% completed
| Thaliparamba WS Section |
| Date: 07/01/2026 |
Work in progress | 4% Completed
Second brace beam work completed
| Thaliparamba WS Section |
| Date: 31/12/2025 |
Work in progress | 4% Completed
Second brace beam work completed
| Thaliparamba WS Section |
| Date: 22/12/2025 |
Work in progress | 4% Completed
First brace beam work completed
| Thaliparamba WS Section |
| Date: 15/12/2025 |
Work in progress | 4% Completed
First brace beam work started
| Thaliparamba WS Section |
| Date: 01/12/2025 |
Work in progress | 2% Completed
Reinforcement for column work started
| Thaliparamba WS Section |
| Date: 22/11/2025 |
Work in progress | 2% Completed
Plinth beam work started
| Thaliparamba WS Section |
| Date: 13/11/2025 |
Work in progress | 2% Completed
Reinforcement for foundation completed
| Thaliparamba WS Section |
| Date: 04/11/2025 |
Work in progress | 1% Completed
PCC for foundation completed
| Thaliparamba WS Section |
| Date: 28/10/2025 |
Work in progress | 1% Completed
foundation excavation work completed
| Thaliparamba WS Section |
| Date: 22/10/2025 |
Work in progress | 0% Completed
foundation excavation work completed
| Thaliparamba WS Section |
| Date: 15/10/2025 |
Work in progress | 0% Completed
Excavation for foundation work started.
| Thaliparamba WS Section |
| Date: 23/09/2025 |
Work in progress | 0% Completed
Work started.
| Thaliparamba WS Section |
| Date: 04/08/2025 |
Work in progress | 0% Completed
Site handed over on
| Thaliparamba WS Dn EE |
| Date: 28/06/2025 |
Work has started | 0% Completed
Tender Scrutiny