AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT-- Replacing old and damaged 100mm and 150mm AC pipe with 110mm and 160mm PVC at various locations under Distribution Section 1/1.-Pipeline Work

Project AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT-- Replacing old and damaged 100mm and 150mm AC pipe with 110mm and 160mm PVC at various locations under Distribution Section 1/1.-Pipeline Work
Project Code CLTAMRUT032313801P32
Type Package
Main Project AMRUT 1.0-Kozhikode Water Supply Project-Providing FHTCs and Pipe Line extension
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT-- Replacing old and damaged 100mm and 150mm AC pipe with 110mm and 160mm PVC at various locations under Distribution Section 1/1.-Pipeline Work
Status On-going
District Kozhikkode
Executing Office Kozhikode Dist 1 Sn 1
Agreement Number
Agreement Date
TS Amount (Rs) 37890000
TS Number 17438/2022-2023
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 31/10/2024

Processing Dates

TS Date 25 Mar 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kozhikode WestHill Distribution Sn - 1/1 - AE
Date: 25/06/2025

Work in progress | 90% Completed

During rain (Ban period) work now stopped.

Kozhikode WestHill Distribution Sn - 1/1 - AE
Date: 19/06/2025

Work in progress | 88% Completed

During rain (Ban period) work now stopped .