| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 25/06/2025 |
Work in progress | 90% Completed
During rain (Ban period) work now stopped
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 19/06/2025 |
Work in progress | 88% Completed
During rain (Ban period) work now stopped
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 19/03/2025 |
Work in progress | 87% Completed
On going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 30/01/2025 |
Work in progress | 86% Completed
ongoing
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 20/01/2025 |
Work in progress | 85% Completed
ON GOING
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 07/12/2024 |
Work in progress | 85% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 03/12/2024 |
Work in progress | 84% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 22/11/2024 |
Work in progress | 84% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 06/11/2024 |
Work in progress | 84% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 26/10/2024 |
Work in progress | 84% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 23/10/2024 |
Work in progress | 84% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 05/10/2024 |
Work in progress | 84% Completed
work in progress
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 24/09/2024 |
Work in progress | 81% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 11/09/2024 |
Work in progress | 80% Completed
work ongoing
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 76% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 74% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 70% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 68% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 65% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 11/01/2024 |
Work in progress | 63% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work in progress | 62% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 28/11/2023 |
Work in progress | 60% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 09/11/2023 |
Work in progress | 53% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 28/10/2023 |
Work in progress | 50% Completed
Pipe laying work started
| Kozhikode PH Dn EE |
| Date: 17/10/2023 |
Work in progress | 45% Completed
Pipe laying work started
| Kozhikode PH Dn EE |
| Date: 14/09/2023 |
Work in progress | 35% Completed
Pipe laying work started
| Kozhikode PH Dn EE |
| Date: 05/09/2023 |
Work in progress | 30% Completed
Pipe laying work started
| Kozhikode PH Dn EE |
| Date: 17/08/2023 |
Work in progress | 15% Completed
Pipe laying work started
| Kozhikode PH Dn EE |
| Date: 08/08/2023 |
Work in progress | 10% Completed
Pipe laying work started
| Kozhikode PH Dn EE |
| Date: 27/07/2023 |
Work in progress | 5% Completed
Pipe laying work started
| Kozhikode PH Dn EE |
| Date: 24/07/2023 |
Work has started | 0% Completed
Site handovered. Work not yet started.
| Kozhikode PH Dn EE |
| Date: 12/07/2023 |
Work has started | 0% Completed
Site handovered. Work not yet started.
| Kozhikode PH Dn EE |
| Date: 05/07/2023 |
Work has started | 0% Completed
Site handovered. Work not yet started.
| Kozhikode PH Dn EE |
| Date: 30/06/2023 |
Work has started | 0% Completed
Site handovered. Work not yet started.
| Kozhikode PH Dn EE |
| Date: 20/06/2023 |
Work has started | 0% Completed
Site handovered. Work not yet started.
| Kozhikode PH Dn EE |
| Date: 13/06/2023 |
Work has started | 0% Completed
Site handovered
| Kozhikode PH Dn EE |
| Date: 08/06/2023 |
Work has started | 0% Completed
Site handovered. Work not started
| Kozhikode PH Dn EE |
| Date: 07/06/2023 |
Work has started | 0% Completed
Work Tendered