JJM-WSS to Kanjirapuzha Grama Panchayath-Additional works.

Project JJM-WSS to Kanjirapuzha Grama Panchayath-Additional works.
Project Code PKDJJM102315879P1
Type Package
Main Project JJM-WSS to Kanjirapuzha Grama Panchayath-Additional works.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-WSS to Kanjirapuzha Grama Panchayath-Additional works - Additional distribution network to uncovered areas and LSGD Road Restoration works.
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 30500000
TS Number WRD/KWA-CE(NR)/EST-TS/25922/2023
Technical specification Extending 14km's the existing distribution network to uncovered areas of Kanjirapuzha Grama Panchayath.
Contractor A.Suresh (Mob: 8075033241)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 14/02/2024
Scheduled date of Completion as per agreement 13 Nov 2024
Expected date of Completion 13/11/2024

Processing Dates

TS Date 30 Nov 2023
Estimate Approval 30 Nov 2023
Tender Closing 23 Jan 2024
Price bid opening 23 Jan 2024

Approval Dates

Workorder Date 20 Feb 2024
NA 14 Mar 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Palakkad Proj AE 3
Date: 28/06/2024

Work in progress | 15% Completed

Total pipe laid - 4.9211 Km.House connection shifting work on-going..

Palakkad Proj AE 3
Date: 26/06/2024

Work in progress | 15% Completed

Total pipe laid - 4.9211 Km.House connection shifting work on-going..