Project | JJM-WSS to Kanjirapuzha Grama Panchayath-Additional works. |
---|---|
Project Code | PKDJJM102315879P1 |
Type | Package |
Main Project | JJM-WSS to Kanjirapuzha Grama Panchayath-Additional works. |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM-WSS to Kanjirapuzha Grama Panchayath-Additional works - Additional distribution network to uncovered areas and LSGD Road Restoration works. |
Status | On-going |
District | Palakkad |
Executing Office | Palakkad Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 30500000 |
TS Number | WRD/KWA-CE(NR)/EST-TS/25922/2023 |
Technical specification | Extending 14km's the existing distribution network to uncovered areas of Kanjirapuzha Grama Panchayath. |
Contractor | A.Suresh (Mob: 8075033241) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 14/02/2024 |
---|---|
Scheduled date of Completion as per agreement | 13 Nov 2024 |
Expected date of Completion | 13/11/2024 |
TS Date | 30 Nov 2023 |
---|---|
Estimate Approval | 30 Nov 2023 |
Tender Closing | 23 Jan 2024 |
Price bid opening | 23 Jan 2024 |
Workorder Date | 20 Feb 2024 |
---|---|
NA | 14 Mar 2024 |
Palakkad Proj AE 3 |
Date: 28/06/2024 |
Work in progress | 15% Completed
Total pipe laid - 4.9211 Km.House connection shifting work on-going..
Palakkad Proj AE 3 |
Date: 26/06/2024 |
Work in progress | 15% Completed
Total pipe laid - 4.9211 Km.House connection shifting work on-going..