Palakkad Proj AE 3 |
Date: 28/06/2024 |
Work in progress | 15% Completed
Total pipe laid - 4.9211 Km.House connection shifting work on-going.
Palakkad Proj AE 3 |
Date: 26/06/2024 |
Work in progress | 15% Completed
Total pipe laid - 4.9211 Km.House connection shifting work on-going.
Palakkad Proj AE 3 |
Date: 25/06/2024 |
Work in progress | 15% Completed
Total pipe laid - 4.9211 Km.House connection shifting work on-going.
Palakkad Proj AE 3 |
Date: 22/06/2024 |
Work in progress | 15% Completed
Total pipe laid - 4.9211 Km.House connection shifting work on-going.
Palakkad Proj AE 3 |
Date: 21/06/2024 |
Work in progress | 15% Completed
4.9211 Km.House connection shifting work on-going
Palakkad Proj AE 3 |
Date: 17/06/2024 |
Work in progress | 15% Completed
Total pipe laid - 4.9591 Km.House connection shifting work on-going.
Palakkad Proj AE 3 |
Date: 12/06/2024 |
Work in progress | 15% Completed
Total pipe laid - 4.9591 Km.House connection shifting work on-going.
Palakkad Proj AE 3 |
Date: 09/06/2024 |
Work in progress | 15% Completed
Total pipe laid - 4.9591 Km.House connection shifting work on-going.
Palakkad Proj AE 3 |
Date: 05/06/2024 |
Work in progress | 15% Completed
Total pipe laid - 4.756 Km.House connection shifting work on-going.
Palakkad Project Dn EE |
Date: 27/05/2024 |
Work in progress | 14% Completed
Total pipe laid - 3.2761 Km.House connection shifting work on-going.
Palakkad Project Dn EE |
Date: 25/05/2024 |
Work in progress | 12% Completed
Total pipe laid - 3.2761 Km.House connection shifting work on-going.
Palakkad Project Dn EE |
Date: 22/05/2024 |
Work in progress | 12% Completed
Total pipe laid - 2.4701 Km.House connection shifting work on-going.
Palakkad Project Dn EE |
Date: 20/05/2024 |
Work in progress | 10% Completed
Total pipe laid - 2.021 Km.House connection shifting work on-going.
Palakkad Project Dn EE |
Date: 18/05/2024 |
Work in progress | 7% Completed
Total laid - 1.4261Km.Today main line laid- ▫️90mm PN 8 - 366m in kallamkuzhi - Rajeev colony Road. Total laid till now - 110mm PN 8 - 586.3m 90mm PN 8 - 839.8m
Palakkad Project Dn EE |
Date: 15/05/2024 |
Work in progress | 5% Completed
Total laid - 956.1m.Today main line laid- ▫️90mm PN 8 - 180.8m in kallamkulam - kunnumpuram Road. Total laid till now - 110mm PN 8 - 586.3m 90mm PN 8 - 369.8m
Palakkad Proj AE 3 |
Date: 06/05/2024 |
Work in progress | 3% Completed
Agreement executed by the the contractor on 14th March 2024 & Full pipe supplied 14km's for the work.
Palakkad Proj AE 3 |
Date: 01/05/2024 |
Work in progress | 3% Completed
Agreement executed by the the contractor on 14th March 2024 & Full pipe supplied 14km's for the work.
Palakkad Proj AE 3 |
Date: 16/04/2024 |
Work in progress | 1% Completed
Supply of pipe for the work.