JJM-WSS to Kanjirapuzha Grama Panchayath-Additional works.
Project |
JJM-WSS to Kanjirapuzha Grama Panchayath-Additional works. |
Project Code |
PKDJJM102315879 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM-WSS to Kanjirapuzha Grama Panchayath-Additional works - Additional distribution network to uncovered areas and LSGD Road Restoration works. |
Status |
On-going |
District |
Palakkad |
Executing Office |
Palakkad Project Dn |
AS Amount (Rs) |
32200000
|
AS Number |
G.O.(Rt)No.897/2023/WRD |
TS Amount (Rs) |
30500000 |
TS Number |
WRD/KWA-CE(NR)/EST-TS/25922/2023 |
Total Bill Submitted (Rs) |
4942293 |
Total Bill Paid (Rs) |
|
Population Benefitted |
45633 |
Capacity in MLD |
12.00 |
Actual Project Completion Date |
13 Nov 2024 |
Coverage |
Uncovered areas of Kanjirapuzha Grama Panchayath |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM-WSS to Kanjirapuzha Grama Panchayath-Additional works. |
Project Division Palakkad |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
28 Jun 2024 |
Total pipe laid - 4.9211 Km.House connection shifting work on-going. |
Palakkad Proj AE 3 |
|
26 Jun 2024 |
Total pipe laid - 4.9211 Km.House connection shifting work on-going. |
Palakkad Proj AE 3 |
|
25 Jun 2024 |
Total pipe laid - 4.9211 Km.House connection shifting work on-going. |
Palakkad Proj AE 3 |
|
22 Jun 2024 |
Total pipe laid - 4.9211 Km.House connection shifting work on-going. |
Palakkad Proj AE 3 |
|
21 Jun 2024 |
Total pipe laid - 4.9211 Km.House connection shifting work on-going. |
Palakkad Proj AE 3 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
14/02/2024 |
Scheduled date of Completion of the Project |
13 Nov 2024 |
Expected date of Completion |
13/11/2024 |
Processing Dates
AS Date |
26 Oct 2023 |
TS Date |
30 Nov 2023 |