JJM:Providing FHTCs to Santhanpara, Rajakumary(part) and Senapathy (part) panchayats in Idukki

Project JJM:Providing FHTCs to Santhanpara, Rajakumary(part) and Senapathy (part) panchayats in Idukki
Project Code IDKJJM092110877
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description A comprehensive water supply scheme to Santhanapara and parts og Rajakumary and Senapathy panchayats under Jal Jeevan Mission Scheme including providing FHTCs to households
Status On-going
District Idukki
Executing Office Kattappana Project Dn
AS Amount (Rs) 920400000
AS Number GO(Rt)No.489/2021/WRD
TS Amount (Rs) 0
TS Number 0.000
Total Bill Submitted (Rs) 180329400
Total Bill Paid (Rs) 110641100
Population Benefitted 44530
Capacity in MLD 8.25
Actual Project Completion Date Date is not specified
Coverage Santhanpara, Rajakumary (Part) and Senapathy (Part) Panchayaths in Idukki
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Package 10 -WSS - to Santhanpara, Rajakumary (Part) and Senapathy (Part) Panchayaths in Idukki DistrictWSS - to Santhanpara, Rajakumary (Part) and Senapathy (Part) Panchayaths in Idukki District Package V-Supply, erection, testing and commissioning of Raw water pump set ,Clear water pump sets ,Supply and installation of flow meters ,Electrical and allied works Project Division Kattapana
2 Package 1- Survey and investigation works. Project Division Kattapana
3 Package 2 - WSS - to Santhanpara, Rajakumary (Part) and Senapathy (Part) Panchayaths in Idukki District Package IV A- Supplying and Laying Distribution and providing FHTC in Santhanpara GP Project Division Kattapana
4 Package 3 - WSS - to Santhanpara, Rajakumary (Part) and Senapathy (Part) Panchayaths in Idukki District Package IIA - Supplying and Laying Distribution and Providing FHTCs in Senapathy GP Project Division Kattapana
5 Package 4-WSS - to Santhanpara, Rajakumary (Part) and Senapathy (Part) Panchayaths in Idukki District Package IIIASupplying and Laying Distribution and providing FHTC in Rajakumary GP Project Division Kattapana
6 PACKAGE 5-WSS - to Santhanpara, Rajakumary (Part) and Senapathy (Part) Panchayaths in Idukki District Package II- Clear Water Pumping Main, Sump cum pump house, GLSR in Senapathy GP Project Division Kattapana
7 Package 6-WSS - to Santhanpara, Rajakumary (Part) and Senapathy (Part) Panchayaths in Idukki District Package III- Clear Water Pumping Main, GLSR in Rajakumary GP Project Division Kattapana
8 Package 7-WSS - to Santhanpara, Rajakumary (Part) and Senapathy (Part) Panchayaths in Idukki District Package 1B-Source protection work- Project Division Kattapana
9 Package 8-WSS - to Santhanpara,Rajakumary (Part) and Senapathy (Part) Panchayaths in Idukki District Package IV- Clear Water Pumping Main, Sump cum pump house, GLSR in Santhanpara GP Project Division Kattapana
10 Package 9-WSS - to Santhanpara, Rajakumary (Part) and Senapathy (Part) Panchayaths in Idukki District Package I- Construction of 8.25 MLD WTP Project Division Kattapana
11 WSS - to Santhanpara, Rajakumary (Part) and Senapathy (Part) Panchayaths in Idukki District Package 1A-Renovation of existing well cum pump house, Supplying and Laying of RWPM Project Division Kattapana

Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Jun 2024 PACKAGE 1 - SURVEY WORK COMPLETED, PACKAGE 1A,2,3,4,5,6,7 -works are ongoing, Package 8- Agreement executed on 25-01-2024, Package 9- Agreement executed on 13-02-2024, Package 10- Work order given to ELECTRIC PROJECT CONSULTANTS. Kattappana AEE 1
22 Jun 2024 PACKAGE 1 - SURVEY WORK COMPLETED, PACKAGE 1A,2,3,4,5,6,7 -works are ongoing, Package 8- Agreement executed on 25-01-2024, Package 9- Agreement executed on 13-02-2024, Package 10- Work order given to ELECTRIC PROJECT CONSULTANTS. Kattappana AEE 1
19 Jun 2024 PACKAGE 1 - SURVEY WORK COMPLETED, PACKAGE 1A,2,3,4,5,6,7 -works are ongoing, Package 8- Agreement executed on 25-01-2024, Package 9- Agreement executed on 13-02-2024, Package 10- Work order given to ELECTRIC PROJECT CONSULTANTS. Kattappana AEE 1
16 Jun 2024 PACKAGE 1 - SURVEY WORK COMPLETED, PACKAGE 1A,2,3,4,5,6,7 -works are ongoing, Package 8- Agreement executed on 25-01-2024, Package 9- Agreement executed on 13-02-2024, Package 10- Work order given to ELECTRIC PROJECT CONSULTANTS. Kattappana AEE 1
13 Jun 2024 PACKAGE 1 - SURVEY WORK COMPLETED, PACKAGE 1A,2,3,4,5,6,7 -works are ongoing, Package 8- Agreement executed on 25-01-2024, Package 9- Agreement executed on 13-02-2024, Package 10- Work order given to ELECTRIC PROJECT CONSULTANTS. Kattappana AEE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 11/02/2022
Scheduled date of Completion of the Project 29 Mar 2024
Expected date of Completion 31/03/2024

Processing Dates

AS Date 18 Sep 2021
TS Date 11 Feb 2022

Other details