Project | Package 2 - WSS - to Santhanpara, Rajakumary (Part) and Senapathy (Part) Panchayaths in Idukki District Package IV A- Supplying and Laying Distribution and providing FHTC in Santhanpara GP |
---|---|
Project Code | IDKJJM092110877P2 |
Type | Package |
Main Project | JJM:Providing FHTCs to Santhanpara, Rajakumary(part) and Senapathy (part) panchayats in Idukki |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Supplying and Laying Distribution and providing FHTC in Santhanpara GP |
Status | On-going |
District | Idukki |
Executing Office | Kattappana Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 388290000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/6970/2022_26_5_4 |
Technical specification | 3799 FHTC Total length of pipeline- 171495 m |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 17/12/2022 |
---|---|
Scheduled date of Completion as per agreement | 20 Nov 2024 |
Expected date of Completion | 30/03/2024 |
TS Date | 09 Dec 2022 |
---|---|
Estimate Approval | 09 Dec 2022 |
NIT Approval | 31 Mar 2023 |
Tender Closing | 10 Apr 2023 |
Technichal Pre-Qualification | 22 Apr 2023 |
Price bid opening | 24 Apr 2023 |
Workorder Date | 10 Apr 2023 |
---|---|
NA | 20 May 2023 |
Kattappana AEE 1 |
Date: 29/06/2024 |
Work in progress | 38% Completed
Road restoration works are ongoing..
Kattappana AEE 1 |
Date: 28/06/2024 |
Work in progress | 37% Completed
Pipeline works halted because of rain..