Package 7-WSS - to Santhanpara, Rajakumary (Part) and Senapathy (Part) Panchayaths in Idukki District Package 1B-Source protection work-

Project Package 7-WSS - to Santhanpara, Rajakumary (Part) and Senapathy (Part) Panchayaths in Idukki District Package 1B-Source protection work-
Project Code IDKJJM092110877P7
Type Package
Main Project JJM:Providing FHTCs to Santhanpara, Rajakumary(part) and Senapathy (part) panchayats in Idukki
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Construction of weir at Panniyar river Rajakumary
Status On-going
District Idukki
Executing Office Kattappana Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 17370000
TS Number WRD/KWA-CE(CR)/EST_TS/6970/2022_5_5_4
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 06/02/2023
Scheduled date of Completion as per agreement 15 Jun 2024
Expected date of Completion 29/03/2024

Processing Dates

TS Date 04 Feb 2023
Estimate Approval 04 Feb 2023
Tender Closing 10 Aug 2023

Approval Dates

Workorder Date 10 Aug 2023
NA 16 Sep 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kattappana AEE 1
Date: 29/06/2024

Work in progress | 1% Completed

Waiting for concurrence from the irrigation department and design work is ongoing at WASCON..

Kattappana AEE 1
Date: 28/06/2024

Work in progress | 1% Completed

Waiting for concurrence from the irrigation department and design work is ongoing at WASCON..