Nattika Project Dn AE 2 |
Date: 21/05/2024 |
Work has been completed | 100% Completed
Work completed.
Nattika Project Dn AE 2 |
Date: 20/05/2024 |
Work in progress | 95% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work completed and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 19/05/2024 |
Work in progress | 95% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work completed and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 18/05/2024 |
Work in progress | 95% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work completed and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 17/05/2024 |
Work in progress | 92% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work completed and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 16/05/2024 |
Work in progress | 92% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work completed and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 15/05/2024 |
Work in progress | 92% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work completed and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 14/05/2024 |
Work in progress | 92% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work completed and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 13/05/2024 |
Work in progress | 92% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work completed and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 12/05/2024 |
Work in progress | 92% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work completed and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 11/05/2024 |
Work in progress | 92% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work completed and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 10/05/2024 |
Work in progress | 92% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work completed and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 09/05/2024 |
Work in progress | 90% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 08/05/2024 |
Work in progress | 90% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 07/05/2024 |
Work in progress | 90% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 06/05/2024 |
Work in progress | 90% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 05/05/2024 |
Work in progress | 90% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 04/05/2024 |
Work in progress | 90% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 03/05/2024 |
Work in progress | 88% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 02/05/2024 |
Work in progress | 84% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work and Scour chamber finishing work & drainage works ongoing.
Nattika Project Dn AE 2 |
Date: 01/05/2024 |
Work in progress | 80% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 30/04/2024 |
Work in progress | 75% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 29/04/2024 |
Work in progress | 70% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 28/04/2024 |
Work in progress | 65% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 27/04/2024 |
Work in progress | 60% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 26/04/2024 |
Work in progress | 55% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 25/04/2024 |
Work in progress | 55% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 24/04/2024 |
Work in progress | 55% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 23/04/2024 |
Work in progress | 55% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work and Scour chamber work ongoing.
Nattika Project Dn AE 2 |
Date: 22/04/2024 |
Work in progress | 54% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work ongoing.
Nattika Project Dn AE 2 |
Date: 21/04/2024 |
Work in progress | 54% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work ongoing.
Nattika Project Dn AE 2 |
Date: 20/04/2024 |
Work in progress | 53% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work ongoing.
Nattika Project Dn AE 2 |
Date: 19/04/2024 |
Work in progress | 52% Completed
Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work ongoing.
Nattika Project Dn AE 2 |
Date: 18/04/2024 |
Work in progress | 51% Completed
Valve chamber cover slab concreting and Stub bend works.
Nattika Project Dn AE 2 |
Date: 17/04/2024 |
Work in progress | 51% Completed
Valve chamber cover slab concreting and Stub bend works.
Nattika Project Dn AE 2 |
Date: 16/04/2024 |
Work in progress | 50% Completed
HDPE pipe railway crossing work, 18.8 m completed.
Nattika Project Dn AE 2 |
Date: 15/04/2024 |
Work in progress | 35% Completed
Scour valve chamber work at south side ongoing.
Nattika Project Dn AE 2 |
Date: 14/04/2024 |
Work in progress | 35% Completed
Scour valve chamber work at south side ongoing.
Nattika Project Dn AE 2 |
Date: 13/04/2024 |
Work in progress | 35% Completed
Scour valve chamber work at south side ongoing.
Nattika Project Dn AE 2 |
Date: 12/04/2024 |
Work in progress | 32% Completed
Scour valve chamber work at south side ongoing.
Nattika Project Dn AE 2 |
Date: 11/04/2024 |
Work in progress | 31% Completed
Scour valve chamber work at south side ongoing.
Nattika Project Dn AE 2 |
Date: 10/04/2024 |
Work in progress | 30% Completed
300m DI pipe laying work ongoing, cumulative: 146.65m laid
Nattika Project Dn AE 2 |
Date: 09/04/2024 |
Work in progress | 30% Completed
300m DI pipe laying work ongoing, cumulative: 146.65m laid
Nattika Project Dn AE 2 |
Date: 08/04/2024 |
Work in progress | 29% Completed
Shuttering of valve chamber at South side and pipe laying work ongoing, 300 DI cumulative: 130.15m.
Nattika Project Dn AE 2 |
Date: 07/04/2024 |
Work in progress | 28% Completed
Deshuttering of valve chamber at north side and base slab concreting works of South side valve chamber ongoing.
Nattika Project Dn AE 2 |
Date: 06/04/2024 |
Work in progress | 28% Completed
Deshuttering of valve chamber at north side and base slab concreting works of South side valve chamber ongoing.
Nattika Project Dn AE 2 |
Date: 05/04/2024 |
Work in progress | 28% Completed
Concreting works of valve chamber at north side.
Nattika Project Dn AE 2 |
Date: 04/04/2024 |
Work in progress | 27% Completed
Shuttering & steel works of valve chamber(north & south sides) in progress.
Nattika Project Dn AE 2 |
Date: 03/04/2024 |
Work in progress | 27% Completed
Shuttering works of valve chamber(north & south sides) in progress.
Nattika Project Dn AE 2 |
Date: 02/04/2024 |
Work in progress | 27% Completed
Shuttering works of valve chamber(north & south sides) in progress.
Nattika Project Dn AE 2 |
Date: 01/04/2024 |
Work in progress | 25% Completed
Reinforcement and shuttering works of valve chamber(north side) in progress.
Nattika Project Dn AE 2 |
Date: 31/03/2024 |
Work in progress | 23% Completed
Construction of valve chamber and Pipe line work in progress, 300 DI laying 117.6m completed.
Nattika Project Dn AE 2 |
Date: 30/03/2024 |
Work in progress | 21% Completed
Pipe line work in progress, 300 DI laying 117.6m completed.
Nattika Project Dn AE 2 |
Date: 29/03/2024 |
Work in progress | 15% Completed
Pipe line works ongoing.
Nattika Project Dn AE 2 |
Date: 28/03/2024 |
Work in progress | 10% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 27/03/2024 |
Work in progress | 10% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 26/03/2024 |
Work in progress | 10% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 25/03/2024 |
Work in progress | 10% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 24/03/2024 |
Work in progress | 8% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 23/03/2024 |
Work in progress | 7% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 22/03/2024 |
Work in progress | 7% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 21/03/2024 |
Work in progress | 6% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 20/03/2024 |
Work in progress | 6% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 19/03/2024 |
Work in progress | 6% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 18/03/2024 |
Work in progress | 5% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 17/03/2024 |
Work in progress | 5% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 16/03/2024 |
Work in progress | 4% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 15/03/2024 |
Work in progress | 3% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 14/03/2024 |
Work in progress | 3% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 13/03/2024 |
Work in progress | 3% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 12/03/2024 |
Work in progress | 3% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 11/03/2024 |
Work in progress | 3% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 10/03/2024 |
Work in progress | 3% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 09/03/2024 |
Work in progress | 2% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 08/03/2024 |
Work in progress | 2% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 07/03/2024 |
Work in progress | 2% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 06/03/2024 |
Work in progress | 1% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 05/03/2024 |
Work in progress | 1% Completed
Boring works near railway crossing ongoing.
Nattika Project Dn AE 2 |
Date: 04/03/2024 |
Work in progress | 1% Completed
Boring works started near railway crossing.