KIIFB - Comprehensive & RWSS to Kollengode and adjoining Panchayaths - Replacement of 300 mm AC CW Gravity Main from Meenkara Kalikavu OHSR to Kollengode OHSR with 300mm DI K9 pipe

Project KIIFB - Comprehensive & RWSS to Kollengode and adjoining Panchayaths - Replacement of 300 mm AC CW Gravity Main from Meenkara Kalikavu OHSR to Kollengode OHSR with 300mm DI K9 pipe
Project Code PKDKIIFB03195477
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description WRD 005-128-Reaplacement of old transmission mains in Palakkad Circle - Project 1- Comprehensive and RWSS to Kollengode and adj. Panchayaths-Replacement of 300mm AC clear water gravity main from Meenkara kalikavu OHSR to Kollengode OHSR with 300mm DI K9 pipe
Status Completed
District Palakkad
Executing Office Nenmara Sn
AS Amount (Rs) 89800000
AS Number WRD 005/128/PA/01
TS Amount (Rs) 88700000
TS Number TS/2020-21/2019/15374
Total Bill Submitted (Rs) 52425235
Total Bill Paid (Rs) 52425235
Population Benefitted 15000
Capacity in MLD 7.00
Actual Project Completion Date 18 Nov 2022
Coverage Replacement of 300mm AC clear water gravity main from Meenkara kalikavu OHSR to Kollengode OHSR with 300mm DI K9 pipe
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB CRWSS to Kollengode and adjoing pt Supplying,Laying, Testing, Commissioning, and Maintenance of clear water gravity main from Meenkara Kalikavu OHSR to Kollengode OHSR with 300mm DI K9 pipe, Providing steel bridges including road restoration Nenmara Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Apr 2024 The work completed on 18/11/2022. The final bill was prepared on 04/07/2023 and trying to upoad the bill in KIIFB PFMS, it was directed submit the Variation staement approved by TS authority. So the variation statement has been prepared and approved by CE NR on 05/04/2024. now the variation approved statement has been submitted submitted to KIIFB for approval so that the final bill can be uploaded and approved. Palakkad PH Dn EE
24 Jan 2023 work completed on 18/11/22 Palakkad PH Dn EE
11 Jul 2022 Physical progress of work 97% , Out of 11.40km 11.064km completed. Road restoration work is pending. Financial progess is 74%, 5.24Cr out of APAC 7.12 Cr Chittur PH Sub Dn AEE
19 Apr 2022 Letter for cutting trees by PWD has been given to EE PWD roads & Secretary Muthalamada GP on 30/03/2022. Palakkad PH Dn EE
19 Apr 2022 10.79km completed. Balance 700 m to be completed after tree cutting (4 Nos) from PWD Roads Palakkad Chittur PH Sub Dn AEE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 22/10/2020
Scheduled date of Completion of the Project 31 Jul 2022
Expected date of Completion 30/11/2022

Processing Dates

AS Date 23 Mar 2019
TS Date 19 Aug 2019

Other details

Project Officers View