KIIFB CRWSS to Kollengode and adjoing pt Supplying,Laying, Testing, Commissioning, and Maintenance of clear water gravity main from Meenkara Kalikavu OHSR to Kollengode OHSR with 300mm DI K9 pipe, Providing steel bridges including road restoration
Project |
KIIFB CRWSS to Kollengode and adjoing pt Supplying,Laying, Testing, Commissioning, and Maintenance of clear water gravity main from Meenkara Kalikavu OHSR to Kollengode OHSR with 300mm DI K9 pipe, Providing steel bridges including road restoration |
Project Code |
PKDGOK03195477P1 |
Type |
Package |
Main Project |
KIIFB - Comprehensive & RWSS to Kollengode and adjoining Panchayaths - Replacement of 300 mm AC CW Gravity Main from Meenkara Kalikavu OHSR to Kollengode OHSR with 300mm DI K9 pipe
|
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Supplying,Laying, Testing, Commissioning, and Maintenance of clear water gravity main from Meenkara Kalikavu OHSR to Kollengode OHSR with 300mm DI K9 pipe, Providing steel bridges including road restoration |
Status |
On-going |
District |
Palakkad |
Executing Office |
Nenmara Sn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
88700000 |
TS Number |
TS/2020-21/2019/15374 |
Technical specification |
This project is to replace the exisisting 12500m 300mm AC pipe with 300mm DIK9 pipe clear gravity main from Meekara OHSR to Kollengod OHSr |
Contractor |
M/S INDIA TECH CONSTRUCTION (Mob: 9447081236) |
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
30 Mar 2022 |
Pending |
Pending |
Approval/Permissions Related (from other departments excluding road cut permission and land related) |
Tree cutting joint inspection conducted |
No comments available. |
Pending |
16 Oct 2021 |
25 Jan 2022 |
Pending |
Road Cut Related Risk |
PWD Roads , Palakkad instructed to stop the work since the trees at sides are close to the alignment |
No comments added. |
Solved |
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
22/10/2020 |
Scheduled date of Completion as per agreement |
21 Jul 2021 |
Expected date of Completion |
30/11/2022 |
Processing Dates
TS Date |
19 Aug 2019 |
Estimate Approval |
19 Aug 2019 |
NIT Approval |
28 Aug 2020 |
Tender Closing |
22 Sep 2020 |
Technichal Pre-Qualification |
25 Sep 2020 |
Price bid opening |
16 Oct 2020 |
Approval Dates
NA |
22 Oct 2020 |
Workorder Date |
22 Oct 2020 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Nenmara Sn AE |
Date: 07/12/2022 |
Work has been completed | 100% Completed
work completed.
Nenmara Sn AE |
Date: 17/11/2022 |
Work has been completed | 100% Completed
work completed.