Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Apr 2024 The work completed on 18/11/2022. The final bill was prepared on 04/07/2023 and trying to upoad the bill in KIIFB PFMS, it was directed submit the Variation staement approved by TS authority. So the variation statement has been prepared and approved by CE NR on 05/04/2024. now the variation approved statement has been submitted submitted to KIIFB for approval so that the final bill can be uploaded and approved. Palakkad PH Dn EE
24 Jan 2023 work completed on 18/11/22 Palakkad PH Dn EE
11 Jul 2022 Physical progress of work 97% , Out of 11.40km 11.064km completed. Road restoration work is pending. Financial progess is 74%, 5.24Cr out of APAC 7.12 Cr Chittur PH Sub Dn AEE
19 Apr 2022 Letter for cutting trees by PWD has been given to EE PWD roads & Secretary Muthalamada GP on 30/03/2022. Palakkad PH Dn EE
19 Apr 2022 10.79km completed. Balance 700 m to be completed after tree cutting (4 Nos) from PWD Roads Palakkad Chittur PH Sub Dn AEE
16 Mar 2022 Again the letter was given to PWD to grant permission for road cutting till 31/03/2022 on 15/03/22 Palakkad PH Dn EE
16 Mar 2022 Out of required laying length of 11.287km, 10.334km laid. PWD agreement period for road restoration expired on 28/02/2022, application for extension submitted. But permission not granted till date Nenmara Sn AE
16 Mar 2022 10.35km completed. Chittur PH Sub Dn AEE
02 Feb 2022 9.6km completed . Balance 1.2km will be completed within 31.3.2022 Palakkad PH Dn EE
12 Jan 2022 Balance work ongoing as the road cutting permission granted was not allowed to cut the road due to heavy rain and the permission was extended and the work is ongoing Palakkad PH Dn EE