| Nedumkandam Sn AE |
| Date: 21/01/2026 |
Work has been completed | 100% Completed
The pipeline laying work has been completed, and the house connection work for the water supply has also been completed.
| Nedumkandam Sn AE |
| Date: 20/01/2026 |
Work in progress | 99% Completed
The pipeline laying work has been completed, and the house connection work for the water supply is in progress.
| Nedumkandam Sn AE |
| Date: 17/01/2026 |
Work in progress | 99% Completed
The pipeline laying work has been completed, and the house connection work for the water supply is in progress.
| Nedumkandam Sn AE |
| Date: 16/01/2026 |
Work in progress | 94% Completed
The pipeline laying work has been completed, and the house connection work for the water supply is in progress.
| Nedumkandam Sn AE |
| Date: 12/01/2026 |
Work in progress | 86% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 09/01/2026 |
Work in progress | 86% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 06/01/2026 |
Work in progress | 86% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 03/01/2026 |
Work in progress | 86% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 30/12/2025 |
Work in progress | 85% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 29/12/2025 |
Work in progress | 85% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 27/12/2025 |
Work in progress | 85% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 24/12/2025 |
Work in progress | 85% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 20/12/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 15/12/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 08/12/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 04/12/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 01/12/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 25/11/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 22/11/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 17/11/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 11/11/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 06/11/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 03/11/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 30/10/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 27/10/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 13/10/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 09/10/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 06/10/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 25/09/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 19/09/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 15/09/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 11/09/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 08/09/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 30/08/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 27/08/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 23/08/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 20/08/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 29/07/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Painavu PH Sub Dn AEE |
| Date: 16/07/2025 |
Work in progress | 80% Completed
Pipes & specials are supplied, Laying works on-going
| Nedumkandam Sn AE |
| Date: 21/06/2025 |
Work in progress | 30% Completed
Pipes & specials are supplied, Laying works on-going