Nedumkandam Sn AE
Date: 21/01/2026

Work has been completed | 100% Completed

The pipeline laying work has been completed, and the house connection work for the water supply has also been completed.

Nedumkandam Sn AE
Date: 20/01/2026

Work in progress | 99% Completed

The pipeline laying work has been completed, and the house connection work for the water supply is in progress.

Nedumkandam Sn AE
Date: 17/01/2026

Work in progress | 99% Completed

The pipeline laying work has been completed, and the house connection work for the water supply is in progress.

Nedumkandam Sn AE
Date: 16/01/2026

Work in progress | 94% Completed

The pipeline laying work has been completed, and the house connection work for the water supply is in progress.

Nedumkandam Sn AE
Date: 12/01/2026

Work in progress | 86% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 09/01/2026

Work in progress | 86% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 06/01/2026

Work in progress | 86% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 03/01/2026

Work in progress | 86% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 30/12/2025

Work in progress | 85% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 29/12/2025

Work in progress | 85% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 27/12/2025

Work in progress | 85% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 24/12/2025

Work in progress | 85% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 20/12/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 15/12/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 08/12/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 04/12/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 01/12/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 25/11/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 22/11/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 17/11/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 11/11/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 06/11/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 03/11/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 30/10/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 27/10/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 13/10/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 09/10/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 06/10/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 25/09/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 19/09/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 15/09/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 11/09/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 08/09/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 30/08/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 27/08/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 23/08/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 20/08/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 29/07/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Painavu PH Sub Dn AEE
Date: 16/07/2025

Work in progress | 80% Completed

Pipes & specials are supplied, Laying works on-going

Nedumkandam Sn AE
Date: 21/06/2025

Work in progress | 30% Completed

Pipes & specials are supplied, Laying works on-going