Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Edappal Sn AE
Date: 12/03/2025

Work in progress | 95% Completed

Chalissery - Valayamkulam road Partial Restoration Work (GSB and Wet Mix) completed, 500 mtr BM Work is pending. Othaloor - Pavittappuram road Completed. Bill under preparation.

Edappal PH Dn EE
Date: 01/03/2025

Work in progress | 51% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal PH Dn EE
Date: 21/02/2025

Work in progress | 51% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal PH Dn EE
Date: 12/02/2025

Work in progress | 51% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal PH Dn EE
Date: 07/02/2025

Work in progress | 51% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal PH Dn EE
Date: 28/01/2025

Work in progress | 51% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 24/01/2025

Work in progress | 51% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 20/01/2025

Work in progress | 51% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 14/01/2025

Work in progress | 51% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 06/01/2025

Work in progress | 51% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal PH Dn EE
Date: 01/01/2025

Work in progress | 51% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 26/12/2024

Work in progress | 51% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 21/12/2024

Work in progress | 51% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal PH Dn EE
Date: 19/12/2024

Work in progress | 51% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 12/12/2024

Work in progress | 51% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 09/12/2024

Work in progress | 50% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 05/12/2024

Work in progress | 50% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 02/12/2024

Work in progress | 50% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 29/11/2024

Work in progress | 50% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 25/11/2024

Work in progress | 50% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 21/11/2024

Work in progress | 50% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 18/11/2024

Work in progress | 50% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed.

Edappal Sn AE
Date: 11/11/2024

Work in progress | 50% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed.

Edappal PH Dn EE
Date: 08/11/2024

Work in progress | 50% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed.

Edappal Sn AE
Date: 04/11/2024

Work in progress | 50% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed.

Edappal Sn AE
Date: 30/10/2024

Work in progress | 50% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed.

Edappal Sn AE
Date: 23/10/2024

Work in progress | 50% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 09/10/2024

Work in progress | 50% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 01/10/2024

Work in progress | 50% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 25/09/2024

Work in progress | 50% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 09/09/2024

Work in progress | 50% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 03/09/2024

Work in progress | 45% Completed

Chalissery Valayamkulam road GSB and wet mix completed. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 27/08/2024

Work in progress | 45% Completed

Chalissery Valayamkulam road GSB and wet mix completed. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 19/08/2024

Work in progress | 45% Completed

Chalissery Valayamkulam road GSB and wet mix completed. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 13/08/2024

Work in progress | 45% Completed

Chalissery Valayamkulam road GSB and wet mix completed. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 06/08/2024

Work in progress | 45% Completed

Chalissery Valayamkulam road GSB and wet mix completed. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 02/08/2024

Work in progress | 45% Completed

Chalissery Valayamkulam road GSB and wet mix completed. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 27/07/2024

Work in progress | 45% Completed

Chalissery Valayamkulam road GSB and wet mix completed. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 15/07/2024

Work in progress | 45% Completed

Chalissery Valayamkulam road GSB and wet mix completed. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 28/06/2024

Work in progress | 44% Completed

Chalissery Valayamkulam road GSB and wet mix completed. Othaloor Pavittappuram road upto BM completed

Edappal Sn AE
Date: 26/06/2024

Work in progress | 44% Completed

Chalissery Valayamkulam road GSB and wet mix completed. Othaloor Pavittappuram road upto BM completed