Kollam Project Dn AE
Date: 26/06/2024

Work in progress | 25% Completed

Pipeline work -5500m completed

Kollam Project Dn AE
Date: 25/06/2024

Work in progress | 25% Completed

Pipeline laying work in progress.

Kollam Project Dn AE
Date: 22/06/2024

Work in progress | 25% Completed

Pipeline laying work in progress.

Kollam Project Dn AE
Date: 18/06/2024

Work in progress | 25% Completed

Pipeline laying work in progress.

Kollam Project Dn AE
Date: 13/06/2024

Work in progress | 24% Completed

Pipeline laying work in progress.

Kollam Project Dn AE
Date: 10/06/2024

Work in progress | 24% Completed

Pipeline laying work in progress.

Kollam Project Dn AE
Date: 06/06/2024

Work in progress | 24% Completed

Pipeline laying work in progress.

Kollam Project Dn AE
Date: 04/06/2024

Work in progress | 24% Completed

Pipeline laying work in progress.

Kollam Project Dn AE
Date: 01/06/2024

Work in progress | 22% Completed

Pipeline laying work in progress.

Kollam Project Dn AE
Date: 25/05/2024

Work in progress | 21% Completed

Pipeline laying work in progress.

Kollam Project Dn AE
Date: 21/05/2024

Work in progress | 20% Completed

Pipe line work - 4900 m completed.

Kollam Project Dn AE
Date: 24/04/2024

Work in progress | 10% Completed

PVC pipe supply completed