Kollam Project Dn AE |
Date: 26/06/2024 |
Work in progress | 25% Completed
Pipeline work -5500m completed
Kollam Project Dn AE |
Date: 25/06/2024 |
Work in progress | 25% Completed
Pipeline laying work in progress.
Kollam Project Dn AE |
Date: 22/06/2024 |
Work in progress | 25% Completed
Pipeline laying work in progress.
Kollam Project Dn AE |
Date: 18/06/2024 |
Work in progress | 25% Completed
Pipeline laying work in progress.
Kollam Project Dn AE |
Date: 13/06/2024 |
Work in progress | 24% Completed
Pipeline laying work in progress.
Kollam Project Dn AE |
Date: 10/06/2024 |
Work in progress | 24% Completed
Pipeline laying work in progress.
Kollam Project Dn AE |
Date: 06/06/2024 |
Work in progress | 24% Completed
Pipeline laying work in progress.
Kollam Project Dn AE |
Date: 04/06/2024 |
Work in progress | 24% Completed
Pipeline laying work in progress.
Kollam Project Dn AE |
Date: 01/06/2024 |
Work in progress | 22% Completed
Pipeline laying work in progress.
Kollam Project Dn AE |
Date: 25/05/2024 |
Work in progress | 21% Completed
Pipeline laying work in progress.
Kollam Project Dn AE |
Date: 21/05/2024 |
Work in progress | 20% Completed
Pipe line work - 4900 m completed.
Kollam Project Dn AE |
Date: 24/04/2024 |
Work in progress | 10% Completed
PVC pipe supply completed