JJM-2020-2021-WSS TO VADAKKENCHERY Panchayath-supplying,laying,testing,commissioning and maintanance of distribution systems with providing FHTCs (6480 Nos) including PWD and LSGD Road restoration work in palakkad District

Project JJM-2020-2021-WSS TO VADAKKENCHERY Panchayath-supplying,laying,testing,commissioning and maintanance of distribution systems with providing FHTCs (6480 Nos) including PWD and LSGD Road restoration work in palakkad District
Project Code PKDJJM022113924P1
Type Package
Main Project JJM-2020-2021-WSS TO VADAKKENCHERY Panchayath-supplying,laying,testing,commissioning and maintanance of distribution systems with providing FHTCs (6480 Nos) including PWD and LSGD Road restoration work in palakkad District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-2020-2021-WSS TO VADAKKENCHERY Panchayath-supplying,laying,testing,commissioning and maintanance of distribution systems with providing FHTCs (6480 Nos) including PWD and LSGD Road restoration work in palakkad District
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 156100000
TS Number TS/WRD/KWA/CE/(NR)/EST/497/2022 DTD 22.11.2022 FOR RS.1561.00 LAKHS
Technical specification supplying,laying,testing,commissioning and maintanance of distribution systems with providing FHTCs (6480 Nos) including PWD and LSGD Road restoration work in palakkad District
Contractor K R SURESH (Mob: 6282747455)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 07/02/2023
Scheduled date of Completion as per agreement 05 Sep 2023
Expected date of Completion 31/12/2024

Processing Dates

TS Date 22 Nov 2022
Estimate Approval 22 Nov 2022
NIT Approval 06 Mar 2023
Tender Closing 27 Dec 2022
Technichal Pre-Qualification 17 Dec 2022
Price bid opening 30 Dec 2022

Approval Dates

Workorder Date 07 Feb 2023
NA 06 Mar 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - AE 3
Date: 27/06/2024

Work in progress | 82% Completed

TOTAL-38.57 KM LAID /out of 47 km, 1).90mm pvc 6kg- 23715.3m, 2). 90MM 8 KG -8100M 3). 80mm GI- 4106.7 M, 4).110 mm pvc 6kg/cm2 -1938.00m 5).100 mm GI - 432M.

Chittur Project Dn - AE 3
Date: 20/06/2024

Work in progress | 82% Completed

TOTAL-38.57 KM LAID /out of 47 km, 1).90mm pvc 6kg- 23715.3m, 2). 90MM 8 KG -8100M 3). 80mm GI- 4106.7 M, 4).110 mm pvc 6kg/cm2 -1938.00m 5).100 mm GI - 432M .