Project | JJM-2020-2021-WSS TO VADAKKENCHERY Panchayath-supplying,laying,testing,commissioning and maintanance of distribution systems with providing FHTCs (6480 Nos) including PWD and LSGD Road restoration work in palakkad District |
---|---|
Project Code | PKDJJM022113924P1 |
Type | Package |
Main Project | JJM-2020-2021-WSS TO VADAKKENCHERY Panchayath-supplying,laying,testing,commissioning and maintanance of distribution systems with providing FHTCs (6480 Nos) including PWD and LSGD Road restoration work in palakkad District |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM-2020-2021-WSS TO VADAKKENCHERY Panchayath-supplying,laying,testing,commissioning and maintanance of distribution systems with providing FHTCs (6480 Nos) including PWD and LSGD Road restoration work in palakkad District |
Status | On-going |
District | Palakkad |
Executing Office | Chittur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 156100000 |
TS Number | TS/WRD/KWA/CE/(NR)/EST/497/2022 DTD 22.11.2022 FOR RS.1561.00 LAKHS |
Technical specification | supplying,laying,testing,commissioning and maintanance of distribution systems with providing FHTCs (6480 Nos) including PWD and LSGD Road restoration work in palakkad District |
Contractor | K R SURESH (Mob: 6282747455) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 07/02/2023 |
---|---|
Scheduled date of Completion as per agreement | 05 Sep 2023 |
Expected date of Completion | 31/12/2024 |
TS Date | 22 Nov 2022 |
---|---|
Estimate Approval | 22 Nov 2022 |
NIT Approval | 06 Mar 2023 |
Tender Closing | 27 Dec 2022 |
Technichal Pre-Qualification | 17 Dec 2022 |
Price bid opening | 30 Dec 2022 |
Workorder Date | 07 Feb 2023 |
---|---|
NA | 06 Mar 2023 |
Chittur Project Dn - AE 3 |
Date: 27/06/2024 |
Work in progress | 82% Completed
TOTAL-38.57 KM LAID /out of 47 km, 1).90mm pvc 6kg- 23715.3m, 2). 90MM 8 KG -8100M 3). 80mm GI- 4106.7 M, 4).110 mm pvc 6kg/cm2 -1938.00m 5).100 mm GI - 432M.
Chittur Project Dn - AE 3 |
Date: 20/06/2024 |
Work in progress | 82% Completed
TOTAL-38.57 KM LAID /out of 47 km, 1).90mm pvc 6kg- 23715.3m, 2). 90MM 8 KG -8100M 3). 80mm GI- 4106.7 M, 4).110 mm pvc 6kg/cm2 -1938.00m 5).100 mm GI - 432M .