JJM-2020-2021-WSS TO VADAKKENCHERY Panchayath-supplying,laying,testing,commissioning and maintanance of distribution systems with providing FHTCs (6480 Nos) including PWD and LSGD Road restoration work in palakkad District
JJM-2020-2021-WSS TO VADAKKENCHERY Panchayath-supplying,laying,testing,commissioning and maintanance of distribution systems with providing FHTCs (6480 Nos) including PWD and LSGD Road restoration work in palakkad District
Project Code
PKDJJM022113924
Type
Main project
Funding Agency
JJM
Category
JJM
Type of scheme
Water Supply
Scheme
4215-01-102-92-02
Description
JJM-2020-2021-WSS TO VADAKKENCHERY Panchayath-supplying,laying,testing,commissioning and maintanance of distribution systems with providing FHTCs (6480 Nos) including PWD and LSGD Road restoration work in palakkad District
Status
On-going
District
Palakkad
Executing Office
Chittur Project Dn
AS Amount (Rs)
236780000
AS Number
GO (Rt No.134/2022/WRD dtd 23.02.2022
TS Amount (Rs)
156100000
TS Number
TS/497/2022/DTD22.11.2022 FOR RS.1561.00 LAKSH
Total Bill Submitted (Rs)
65518532
Total Bill Paid (Rs)
65518532
Population Benefitted
Capacity in MLD
Actual Project Completion Date
31 Dec 2024
Coverage
Vadakkenchery Gramapanchayath
Packages
No.
Project Name
Location
View
1
JJM-2020-2021-WSS TO VADAKKENCHERY Panchayath-supplying,laying,testing,commissioning and maintanance of distribution systems with providing FHTCs (6480 Nos) including PWD and LSGD Road restoration work in palakkad District
Project Division Chittur
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
20 Jun 2024
Work in progress | 82% Completed | 20/06/2024
TOTAL-38.57 KM LAID /out of 47 km, 1).90mm pvc 6kg- 23715.3m, 2). 90MM 8 KG -8100M 3). 80mm GI- 4106.7 M, 4).110 mm pvc 6kg/cm2 -1938.00m 5).100 mm GI - 432M
Chittur Project Dn - AE 3
12 Jun 2024
Work in progress | 82% Completed | 12/06/2024
TOTAL-38.574KM LAID /out of 47 km , 1).90mm pvc 6kg- 23715.3m , 2) 90MM 8 KG -8100M 3). 80mm GI- 4094.7 M, 4).110 mm pvc6kg/cm2 -1938.00m 5) 100 mm GI - 312M FHTC 5975/out of 6480 NO
Chittur Project Dn - AE 3
06 Jun 2024
Work in progress | 82% Completed | 06/06/2024
TOTAL-38.574KM LAID /out of 47 km , 1).90mm pvc 6kg- 23715.3m , 2) 90MM 8 KG -8100M 3). 80mm GI- 4094.7 M, 4).110 mm pvc6kg/cm2 -1938.00m 5) 100 mm GI - 252M FHTC 5975/out of 6480 NO
Chittur Project Dn - AE 3
01 Jun 2024
Work in progress | 82% Completed | 01/06/2024
TOTAL-38.574KM LAID /out of 47 km , 1).90mm pvc 6kg- 23715.3m , 2) 90MM 8 KG -8100M 3). 80mm GI- 4094.7 M, 4).110 mm pvc6kg/cm2 -1938.00m 5) 100 mm GI - 252M FHTC 5975/out of 6480 NO
Chittur Project Dn - AE 3
23 May 2024
Work in progress | 82% Completed | 23/05/2024
TOTAL-38.574KM LAID /out of 47 km , 1).90mm pvc 6kg- 23715.3m , 2) 90MM 8 KG -8100M 3). 80mm GI- 4094.7 M, 4).110 mm pvc6kg/cm2 -1938.00m 5) 100 mm GI - 252M FHTC 5975/out of 6480 NO