Chittur Project Dn - AE 3
Date: 27/06/2024

Work in progress | 82% Completed

TOTAL-38.57 KM LAID /out of 47 km, 1).90mm pvc 6kg- 23715.3m, 2). 90MM 8 KG -8100M 3). 80mm GI- 4106.7 M, 4).110 mm pvc 6kg/cm2 -1938.00m 5).100 mm GI - 432M

Chittur Project Dn - AE 3
Date: 20/06/2024

Work in progress | 82% Completed

TOTAL-38.57 KM LAID /out of 47 km, 1).90mm pvc 6kg- 23715.3m, 2). 90MM 8 KG -8100M 3). 80mm GI- 4106.7 M, 4).110 mm pvc 6kg/cm2 -1938.00m 5).100 mm GI - 432M

Chittur Project Dn - AE 3
Date: 12/06/2024

Work in progress | 82% Completed

TOTAL-38.574KM LAID /out of 47 km , 1).90mm pvc 6kg- 23715.3m , 2) 90MM 8 KG -8100M 3). 80mm GI- 4094.7 M, 4).110 mm pvc6kg/cm2 -1938.00m 5) 100 mm GI - 312M FHTC 5975/out of 6480 NO

Chittur Project Dn - AE 3
Date: 06/06/2024

Work in progress | 82% Completed

TOTAL-38.574KM LAID /out of 47 km , 1).90mm pvc 6kg- 23715.3m , 2) 90MM 8 KG -8100M 3). 80mm GI- 4094.7 M, 4).110 mm pvc6kg/cm2 -1938.00m 5) 100 mm GI - 252M FHTC 5975/out of 6480 NO

Chittur Project Dn - AE 3
Date: 01/06/2024

Work in progress | 82% Completed

TOTAL-38.574KM LAID /out of 47 km , 1).90mm pvc 6kg- 23715.3m , 2) 90MM 8 KG -8100M 3). 80mm GI- 4094.7 M, 4).110 mm pvc6kg/cm2 -1938.00m 5) 100 mm GI - 252M FHTC 5975/out of 6480 NO

Chittur Project Dn - AE 3
Date: 23/05/2024

Work in progress | 82% Completed

TOTAL-38.574KM LAID /out of 47 km , 1).90mm pvc 6kg- 23715.3m , 2) 90MM 8 KG -8100M 3). 80mm GI- 4094.7 M, 4).110 mm pvc6kg/cm2 -1938.00m 5) 100 mm GI - 252M FHTC 5975/out of 6480 NO

Chittur Project Dn - AE 3
Date: 16/05/2024

Work in progress | 82% Completed

TOTAL-38.574KM LAID /out of 47 km , 1).90mm pvc 6kg- 23715.3m , 2) 90MM 8 KG -8100M 3). 80mm GI- 4094.7 M, 4).110 mm pvc6kg/cm2 -1938.00m 5) 100 mm GI - 252M FHTC 5975/out of 6480 NO

Chittur Project Dn - AE 3
Date: 09/05/2024

Work in progress | 82% Completed

TOTAL-38.574KM LAID /out of 47 km , 1).90mm pvc 6kg- 23715.3m , 2) 90MM 8 KG -8100M 3). 80mm GI- 4094.7 M, 4).110 mm pvc6kg/cm2 -1938.00m 5) 100 mm GI - 252M FHTC 5975/out of 6480 NO

Chittur Project Dn - AE 3
Date: 02/05/2024

Work in progress | 82% Completed

TOTAL-38.574KM LAID /out of 47 km , 1).90mm pvc 6kg- 23707.3m , 2) 90MM 8 KG -8100M 3). 80mm GI- 4094.7 M, 4).110 mm pvc6kg/cm2 -1938.00m 5) 100 mm GI - 252M FHTC 5975/out of 6480 NO

Chittur Project Dn - AE 3
Date: 25/04/2024

Work in progress | 82% Completed

TOTAL-38.46KM LAID /out of 47 km , 1).90mm pvc 6kg- 23617.30m , 2) 90MM 8 KG -8076M 3). 80mm GI- 4094.7 M, 4).110 mm pvc6kg/cm2 -1938.00m 5) 100 mm GI - 252M FHTC 5975/out of 6480 NO

Chittur Project Dn - AE 3
Date: 19/04/2024

Work in progress | 82% Completed

TOTAL-38.46KM LAID /out of 47 km , 1).90mm pvc 6kg- 23617.30m , 2) 90MM 8 KG -8076M 3). 80mm GI- 4094.7 M, 4).110 mm pvc6kg/cm2 -1938.00m 5) 100 mm GI - 252M FHTC 5975/out of 6480 NO

Chittur Project Dn - AE 3
Date: 11/04/2024

Work in progress | 82% Completed

TOTAL-38.46KM LAID /out of 47 km , 1).90mm pvc 6kg- 23617.30m , 2) 90MM 8 KG -8076M 3). 80mm GI- 4094.7 M, 4).110 mm pvc6kg/cm2 -1938.00m 5) 100 mm GI - 252M FHTC 5975/out of 6480 NOS

Chittur Project Dn - AE 3
Date: 01/04/2024

Work in progress | 81% Completed

TOTAL-37.924 KM LAID /out of 47 km , 1).90mm pvc 6kg- 23617.30m , 2) 90MM 8 KG -8076M 3). 80mm GI- 4094.7 M, 4).110 mm pvc6kg/cm2 -1938.00m 5) 100 mm GI - 198M FHTC 5975/out of 6480 NOS

Chittur Project Dn - AE 3
Date: 30/03/2024

Work in progress | 81% Completed

TOTAL-37.87 KM LAID /out of 47 km , 1).90mm pvc 6kg- 23617.30m , 2) 90MM 8 KG -8076M 3). 80mm GI- 4094.7 M, 4).110 mm pvc6kg/cm2 -1938.00m 5) 100 mm GI - 144M FHTC 5975/out of 6480 NOS

Chittur Project Dn - AE 3
Date: 20/03/2024

Work in progress | 80% Completed

TOTAL-37.622 KM LAID /out of 47 km , 1).90mm pvc 6kg- 23581.30m , 2) 90MM 8 KG -8076M 3). 80mm GI- 4091.7 M, 4).110 mm pvc6kg/cm2 -1800.00m 5) 100 mm GI 72M FHTC 5975/out of 6480 NOS

Chittur Project Dn - AE 3
Date: 01/03/2024

Work in progress | 78% Completed

TOTAL-37.55 KM LAID /out of 47 km , 1).90mm pvc 6kg- 23581.30m , 2) 90MM 8 KG -8076M 3). 80mm GI- 4091.7 M, 4).110 mm pvc6kg/cm2 -1800.00m FHTC 5814/out of 6480 NOS

Chittur Project Dn - AE 3
Date: 22/02/2024

Work in progress | 78% Completed

TOTAL-37.55 KM LAID /out of 47 km , 1).90mm pvc 6kg- 23581.30m , 2) 90MM 8 KG -8076M 3). 80mm GI- 4091.7 M, 4).110 mm pvc6kg/cm2 -1800.00m FHTC 5814/out of 6480 NOS

Chittur Project Dn - AE 3
Date: 15/02/2024

Work in progress | 78% Completed

TOTAL-37.323 KM LAID /out of 47 km , 1).90mm pvc 6kg- 23581.30m , 2} 90MM 8 KG -7938.00M 3). 80mm GI- 4043.70 M, 4).110 mm pvc6kg/cm2 -1800.00m FHTC 5245/out of 6480 NOS

Chittur Project Dn - AE 3
Date: 24/01/2024

Work in progress | 77% Completed

TOTAL-36.298 KM LAID /out of 47 km , 1).90mm pvc 6kg- 23251.30m , 2}90MM 8 KG -7362.00M 3). 80mm GI- 3884.70M, 4).110 mm pvc6kg/cm2 -1800.00m FHTC 5245/out of 6480 NOS

Chittur Project Dn - AE 3
Date: 30/11/2023

Work in progress | 66% Completed

TOTAL-32.877 KM LAID /out of 47 km , 1).90mm pvc 6kg- 21144.30m , 2}90MM 8 KG -7158.00M 3). 80mm GI- 3452.70M, 4).110 mm pvc6kg/cm2 -1200.00m FHTC 5028/out of 6480 NOS

Chittur Project Dn - AE 3
Date: 09/11/2023

Work in progress | 64% Completed

TOTAL-32.2111 KM LAID /out of 47 km , 1).90mm pvc 6kg- 21002.80m , 2}90MM 8 KG -7086.00M 3). 80mm GI- 2999.70 M, 4).110 mm pvc6kg/cm2 -1200.00m FHTC 5028/out of 6480 NOS

Chittur Project Dn - AE 3
Date: 03/11/2023

Work in progress | 62% Completed

TOTAL-32.2025KM LAID /out of 47 km , 1).90mm pvc 6kg- 21002.80m , 2}90MM 8 KG -7000.00M 3). 80mm GI- 2999.70 M, 4).110 mm pvc6kg/cm2 -1200.00m FHTC 4747/out of 6480 NOS

Chittur Project Dn - AE 3
Date: 28/10/2023

Work in progress | 60% Completed

TOTAL-18.854KM LAID /out of 47 km , 1).90mm pvc 6kg- 20506.80m , 2}90MM 8 KG -6767.35M 3). 80mm GI- 1352.35 M, 4).110 mm pvc -140.30m FHTC 4747/out of 6480 NOS

Chittur Project Dn - AE 3
Date: 12/10/2023

Work in progress | 38% Completed

TOTAL-18.854KM LAID /out of 47 km , 1).90mm pvc 6kg- 18044.74m , 2}90MM 8 KG -156M 3). 80mm GI- 294 M, 4).110 mm pvc -360m FHTC 4200/out of 6480 NOS

Chittur Project Dn - AE 3
Date: 07/09/2023

Work in progress | 36% Completed

TOTAL-18.105KM LAID /out of 47 km , 1).90mm pvc 6kg- 17906.74m , 2). 80mm GI-198M, 3).110 mm pvc -360m FHTC 3399/out of 6480 NOS

Chittur Project Dn - AE 3
Date: 26/08/2023

Work in progress | 34% Completed

TOTAL-16.19074KM LAID /out of 47 km , 1).90mm pvc 6kg-15656.74m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 3008/out of 6480 NOS

Chittur Project Dn - AE 3
Date: 15/08/2023

Work in progress | 33% Completed

TOTAL-15.728KM LAID /out of 47 km , 1).90mm pvc 6kg-14122.74m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 2622

Chittur Project Dn - AE 3
Date: 04/08/2023

Work in progress | 28% Completed

TOTAL-15.654KM LAID /out of 47 km , 1).90mm pvc 6kg-14122.00m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 2622

Chittur Project Dn - AE 3
Date: 19/07/2023

Work in progress | 25% Completed

TOTAL-15.654KM LAID /out of 47 km , 1).90mm pvc 6kg-13402.00m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 2374

Chittur Project Dn - AE 3
Date: 13/07/2023

Work in progress | 25% Completed

TOTAL-15.552KM LAID /out of 47 km , 1).90mm pvc 6kg-13300.00m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 2374

Chittur Project Dn - AE 3
Date: 04/07/2023

Work in progress | 23% Completed

TOTAL-14.514KM LAID /out of 47 km , 1).90mm pvc 6kg-13300.00m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 2364

Chittur Project Dn - AE 3
Date: 23/06/2023

Work in progress | 23% Completed

TOTAL-12.095KM LAID /out of 47 km , 1).90mm pvc 6kg-10881m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 2364

Chittur Project Dn - AE 3
Date: 16/06/2023

Work in progress | 20% Completed

TOTAL-10.935KM LAID /out of 47 km , 1).90mm pvc 6kg-9721m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 2364

Chittur Project Dn - AE 3
Date: 09/06/2023

Work in progress | 17% Completed

TOTAL-9.972KM LAID /out of 47 km , 1).90mm pvc 6kg-9283m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 2244

Chittur Project Dn - AE 3
Date: 02/06/2023

Work in progress | 15% Completed

TOTAL-9.972KM LAID /out of 47 km , 1).90mm pvc 6kg-7967m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 2123

Chittur Project Dn - AE 3
Date: 25/05/2023

Work in progress | 10% Completed

TOTAL-8.245KM LAID /out of 47 km , 1).90mm pvc 6kg-6240m , 2). 80mm GI-174M, 3).110 mm pvc -360m

Chittur Project Dn - AE 3
Date: 19/05/2023

Work in progress | 10% Completed

TOTAL-7.291KM LAID /out of 47 km , 90mm pvc 6kg-5.658m , 80mm GI-162M

Chittur Project Dn - AE 3
Date: 11/05/2023

Work in progress | 2% Completed

TOTAL-5.820 KM LAID /out of 47 km , 90mm pvc 6kg-5.658m , 80mm GI-162M

Chittur Project Dn - AE 3
Date: 05/05/2023

Work in progress | 2% Completed

TOTAL-3.288 KM LAID /out of 47 km , 90mm pvc 6kg-3126m , 80mm GI-162M

Chittur Project Dn - AE 3
Date: 28/04/2023

Work in progress | 2% Completed

TOTAL-1692M LAID /out of 47 km , 90mm pvc 6kg-1530m , 80mm GI-162M

Chittur Project Dn - AE 3
Date: 24/04/2023

Work in progress | 1% Completed

TOTAL-570M LAID 90mm pvc 6kg-438m 80mm GI-132M