| Thaliparamba WS Section |
| Date: 28/09/2026 |
Work in progress | 97% Completed
PWD Road restoration works remaining. Compound wall work pending
| Thaliparamba WS Section |
| Date: 02/07/2026 |
Work in progress | 96% Completed
Interconnection from 800mm to 150mm DI pipe is completed. Road restoration works remaining
| Thaliparamba WS Section |
| Date: 25/06/2026 |
Work in progress | 96% Completed
Interconnection from 800mm to 150mm DI pipe is completed. Road restoration works remaining
| Thaliparamba WS Section |
| Date: 09/06/2026 |
Work in progress | 96% Completed
Interconnection from 800mm to 150mm DI pipe is completed. Road restoration works remaining
| Thaliparamba WS Section |
| Date: 12/05/2026 |
Work in progress | 92% Completed
Interconnection from 800mm to 150mm DI pipe is pending. Tank work painting and level gauge fixing pending.
| Thaliparamba WS Section |
| Date: 24/04/2026 |
Work in progress | 92% Completed
Interconnection from 800mm to 150mm DI pipe is pending. Tank work painting and level gauge fixing pending.
| Thaliparamba WS Section |
| Date: 07/04/2026 |
Work in progress | 92% Completed
Interconnection from 800mm to 150mm DI pipe is pending. Tank work painting and level gauge fixing pending.
| Thaliparamba WS Section |
| Date: 27/03/2026 |
Work in progress | 92% Completed
Interconnection from 800mm to 150mm DI pipe is pending. Tank work painting and level gauge fixing pending.
| Thaliparamba WS Section |
| Date: 13/03/2026 |
Work in progress | 92% Completed
Interconnection from 800mm to 150mm DI pipe is pending. Tank work painting and level gauge fixing pending.
| Thaliparamba WS Section |
| Date: 04/03/2026 |
Work in progress | 92% Completed
Interconnection from 800mm to 150mm DI pipe is pending. Tank work painting and level gauge fixing pending.
| Thaliparamba WS Section |
| Date: 21/02/2026 |
Work in progress | 92% Completed
NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.
| Thaliparamba WS Section |
| Date: 16/02/2026 |
Work in progress | 92% Completed
NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.
| Thaliparamba WS Section |
| Date: 06/02/2026 |
Work in progress | 92% Completed
NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.
| Thaliparamba WS Section |
| Date: 28/01/2026 |
Work in progress | 92% Completed
NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.
| Thaliparamba WS Section |
| Date: 23/01/2026 |
Work in progress | 92% Completed
NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.
| Thaliparamba WS Section |
| Date: 17/01/2026 |
Work in progress | 92% Completed
NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.
| Thaliparamba WS Section |
| Date: 13/01/2026 |
Work in progress | 92% Completed
NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.
| Thaliparamba WS Dn EE |
| Date: 09/01/2026 |
Work in progress | 92% Completed
92% Completed.
| Thaliparamba WS Section |
| Date: 07/01/2026 |
Work in progress | 92% Completed
NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.
| Thaliparamba WS Section |
| Date: 31/12/2025 |
Work in progress | 92% Completed
NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.
| Thaliparamba WS Section |
| Date: 22/12/2025 |
Work in progress | 92% Completed
NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.
| Thaliparamba WS Section |
| Date: 15/12/2025 |
Work in progress | 92% Completed
NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.
| Thaliparamba WS Section |
| Date: 01/12/2025 |
Work in progress | 92% Completed
NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.
| Thaliparamba WS Section |
| Date: 22/11/2025 |
Work in progress | 92% Completed
NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.
| Thaliparamba WS Section |
| Date: 13/11/2025 |
Work in progress | 92% Completed
NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.
| Thaliparamba WS Section |
| Date: 04/11/2025 |
Work in progress | 92% Completed
NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.
| Thaliparamba WS Section |
| Date: 22/10/2025 |
Work in progress | 92% Completed
NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.
| Thaliparamba WS Section |
| Date: 15/10/2025 |
Work in progress | 92% Completed
NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.
| Thaliparamba WS Section |
| Date: 03/10/2025 |
Work in progress | 92% Completed
NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.
| Thaliparamba WS Section |
| Date: 19/06/2025 |
Work in progress | 89% Completed
NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work started
| Thaliparamba WS Section |
| Date: 30/04/2025 |
Work in progress | 85% Completed
1 LL OHSR plastering work completed and painting work in progress . 996 FHTCs Completed. 10km pipes laid out of 12km. Pipe laying in PWD road completed. inter connection work from 800mm DI pipe not started. New NH crossing at Keezhatoor vayal not started.
| Thaliparamba WS Section |
| Date: 01/02/2025 |
Work in progress | 66% Completed
1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km
| Thaliparamba WS Section |
| Date: 27/11/2024 |
Work in progress | 65% Completed
1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km
| Thaliparamba WS Section |
| Date: 11/11/2024 |
Work in progress | 65% Completed
1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km
| Thaliparamba WS Section |
| Date: 05/11/2024 |
Work in progress | 65% Completed
1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km
| Thaliparamba WS Section |
| Date: 30/10/2024 |
Work in progress | 65% Completed
1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km
| Thaliparamba WS Section |
| Date: 23/10/2024 |
Work in progress | 65% Completed
1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km
| Thaliparamba WS Section |
| Date: 09/10/2024 |
Work in progress | 65% Completed
1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km
| Thaliparamba WS Section |
| Date: 07/10/2024 |
Work in progress | 64% Completed
1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km
| Thaliparamba WS Section |
| Date: 01/10/2024 |
Work in progress | 64% Completed
1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km
| Thaliparamba WS Section |
| Date: 24/09/2024 |
Work in progress | 64% Completed
1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km
| Thaliparamba WS Section |
| Date: 18/09/2024 |
Work in progress | 64% Completed
1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km
| Thaliparamba WS Section |
| Date: 02/09/2024 |
Work in progress | 64% Completed
1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km
| Thaliparamba WS Section |
| Date: 26/06/2024 |
Work in progress | 61% Completed
1 LL OHSR plastering work completed and painting work in progress . 680 FHTC's given out of 996 FHTCs.6 km pipes laid out of 12km
| Thaliparamba WS Section |
| Date: 11/06/2024 |
Work in progress | 60% Completed
1 LL OHSR plastering work completed and painting work in progress . 670 FHTC's given out of 996 FHTCs.6 km pipes laid out of 12km
| Thaliparamba WS Section |
| Date: 06/05/2024 |
Work in progress | 42% Completed
1 LL OHSR structure work completed, plastering progressing . Connection work in progress 630 FHTC given out of 996 FHTCs .3 km pipes laid out of 12km
| Thaliparamba WS Section |
| Date: 24/04/2024 |
Work in progress | 42% Completed
1 LL OHSR structure work completed, plastering progressing . Connection work in progress 630 FHTC given out of 996 FHTCs .3 km pipes laid out of 12km
| Thaliparamba WS Section |
| Date: 04/04/2024 |
Work in progress | 41% Completed
1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km
| Thaliparamba WS Dn EE |
| Date: 19/03/2024 |
Work in progress | 40% Completed
1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km
| Thaliparamba WS Dn EE |
| Date: 14/03/2024 |
Work in progress | 40% Completed
1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km
| Thaliparamba WS Dn EE |
| Date: 13/03/2024 |
Work in progress | 40% Completed
1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km
| Thaliparamba WS Section |
| Date: 01/03/2024 |
Work in progress | 40% Completed
OH tank structure work completed, 1000m pvc & 600m DI pipe laying work are completed , OH tank drainage work under progress.
| Thaliparamba WS Section |
| Date: 13/02/2024 |
Work in progress | 40% Completed
OH tank structure work completed, 1000m pvc & 600m DI pipe laying work are completed , OH tank drainage work under progress.
| Thaliparamba WS Section |
| Date: 11/02/2024 |
| Thaliparamba WS Section |
| Date: 09/02/2024 |
| Thaliparamba WS Section |
| Date: 01/02/2024 |
| Thaliparamba WS Section |
| Date: 19/01/2024 |
Work in progress | 35% Completed
Tank covering slab concrete completed , connection work in progress 500 FHTC given
| Thaliparamba WS Section |
| Date: 12/01/2024 |
| Thaliparamba WS Section |
| Date: 08/01/2024 |
Work in progress | 30% Completed
Tank covering slab concrete completed , connection work in progress 450 FHTC given
| Thaliparamba WS Section |
| Date: 05/01/2024 |
Work in progress | 30% Completed
Tank covering slab concrete completed , connection work in progress 420 FHTC given
| Thaliparamba WS Section |
| Date: 28/12/2023 |
| Thaliparamba WS Section |
| Date: 22/12/2023 |
| Thaliparamba WS Section |
| Date: 18/12/2023 |
| Thaliparamba WS Section |
| Date: 12/12/2023 |
| Thaliparamba WS Section |
| Date: 10/12/2023 |
| Thaliparamba WS Section |
| Date: 09/12/2023 |
| Thaliparamba WS Section |
| Date: 04/12/2023 |
| Thaliparamba WS Section |
| Date: 30/11/2023 |
Work in progress | 10% Completed
Tank work Deck slab and haunch concrete completed, vertical wall concrete under progress,connection work in progress 100fhtc given
| Thaliparamba WS Section |
| Date: 22/11/2023 |
| Thaliparamba WS Section |
| Date: 17/11/2023 |
| Thaliparamba WS Section |
| Date: 12/11/2023 |
| Thaliparamba WS Section |
| Date: 07/11/2023 |
Work in progress | 6% Completed
work in progress
| Thaliparamba WS Section |
| Date: 30/10/2023 |
Work in progress | 5% Completed
Work in progress
| Thaliparamba WS Section |
| Date: 25/10/2023 |
Work in progress | 5% Completed
Work in progress
| Thaliparamba WS Section |
| Date: 19/10/2023 |
Work in progress | 5% Completed
Work in progress
| Thaliparamba WS Section |
| Date: 15/10/2023 |
Work in progress | 5% Completed
Work in progress
| Thaliparamba WS Section |
| Date: 10/10/2023 |
| Thaliparamba WS Section |
| Date: 03/10/2023 |
| Thaliparamba WS Section |
| Date: 29/09/2023 |
Work in progress | 5% Completed
Work in progress
| Thaliparamba WS Section |
| Date: 23/09/2023 |
| Thaliparamba WS Section |
| Date: 15/09/2023 |
Work in progress | 5% Completed
Work in progress
| Thaliparamba WS Section |
| Date: 11/09/2023 |
| Thaliparamba WS Section |
| Date: 07/09/2023 |
| Thaliparamba WS Section |
| Date: 06/09/2023 |
Work in progress | 5% Completed
work in progress
| Thaliparamba WS Section |
| Date: 03/09/2023 |
| Thaliparamba WS Section |
| Date: 30/08/2023 |
| Thaliparamba WS Section |
| Date: 22/08/2023 |
Work in progress | 4% Completed
Work in progress
| Thaliparamba WS Section |
| Date: 20/08/2023 |
Work in progress | 4% Completed
Work in progress
| Thaliparamba WS Section |
| Date: 16/08/2023 |
Work in progress | 4% Completed
Work in progress
| Thaliparamba WS Section |
| Date: 11/08/2023 |
| Thaliparamba WS Section |
| Date: 08/08/2023 |
| Thaliparamba WS Section |
| Date: 05/08/2023 |
Work in progress | 4% Completed
Work in progress
| Thaliparamba WS Section |
| Date: 03/08/2023 |
Work in progress | 4% Completed
Work in progress
| Thaliparamba WS Dn EE |
| Date: 31/07/2023 |
Work in progress | 4% Completed
Work in progress
| Thaliparamba WS Section |
| Date: 24/07/2023 |
Work in progress | 3% Completed
3% completed
| Thaliparamba WS Section |
| Date: 19/07/2023 |
Work in progress | 3% Completed
3%completed
| Thaliparamba WS Section |
| Date: 14/07/2023 |
| Thaliparamba WS Section |
| Date: 13/07/2023 |
Work in progress | 3% Completed
3%completed
| Thaliparamba WS Section |
| Date: 10/07/2023 |
Work in progress | 2% Completed
Ongoing
| Thaliparamba WS Section |
| Date: 05/07/2023 |
Work in progress | 2% Completed
Work started
| Thaliparamba WS Section |
| Date: 27/06/2023 |
Work in progress | 1% Completed
For Package 1- Work order issued on 18.05.2023, Agreement executed For Package 2- request letter sent by District Collector to the Land Revenue Commissioner for providing land sanctioned under public use category on lease to Taliparamba Muncipality
| Thaliparamba WS Section |
| Date: 19/06/2023 |
Work in progress | 1% Completed
For Package 1- Work order issued on 18.05.2023, Agreement executed For Package 2- request letter sent by District Collector to the Land Revenue Commissioner for providing land sanctioned under public use category on lease to Taliparamba Muncipality
| Thaliparamba WS Dn EE |
| Date: 14/06/2023 |
Work in progress | 1% Completed
For Package 1- Work order issued on 18.05.2023, Agreement executed For Package 2- request letter sent by District Collector to the Land Revenue Commissioner for providing land sanctioned under public use category on lease to Taliparamba Muncipality
| Thaliparamba WS Dn EE |
| Date: 08/06/2023 |
Work in progress | 1% Completed
For Package 1- work order issued on 18.05.2023, For Package 2- request letter sent by District Collect to the Land Revenue Commissioner for providing land sanctioned under public use category on lease to Taliparamba Muncipality