Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Thaliparamba WS Section
Date: 28/09/2026

Work in progress | 97% Completed

PWD Road restoration works remaining. Compound wall work pending

Thaliparamba WS Section
Date: 02/07/2026

Work in progress | 96% Completed

Interconnection from 800mm to 150mm DI pipe is completed. Road restoration works remaining

Thaliparamba WS Section
Date: 25/06/2026

Work in progress | 96% Completed

Interconnection from 800mm to 150mm DI pipe is completed. Road restoration works remaining

Thaliparamba WS Section
Date: 09/06/2026

Work in progress | 96% Completed

Interconnection from 800mm to 150mm DI pipe is completed. Road restoration works remaining

Thaliparamba WS Section
Date: 12/05/2026

Work in progress | 92% Completed

Interconnection from 800mm to 150mm DI pipe is pending. Tank work painting and level gauge fixing pending.

Thaliparamba WS Section
Date: 24/04/2026

Work in progress | 92% Completed

Interconnection from 800mm to 150mm DI pipe is pending. Tank work painting and level gauge fixing pending.

Thaliparamba WS Section
Date: 07/04/2026

Work in progress | 92% Completed

Interconnection from 800mm to 150mm DI pipe is pending. Tank work painting and level gauge fixing pending.

Thaliparamba WS Section
Date: 27/03/2026

Work in progress | 92% Completed

Interconnection from 800mm to 150mm DI pipe is pending. Tank work painting and level gauge fixing pending.

Thaliparamba WS Section
Date: 13/03/2026

Work in progress | 92% Completed

Interconnection from 800mm to 150mm DI pipe is pending. Tank work painting and level gauge fixing pending.

Thaliparamba WS Section
Date: 04/03/2026

Work in progress | 92% Completed

Interconnection from 800mm to 150mm DI pipe is pending. Tank work painting and level gauge fixing pending.

Thaliparamba WS Section
Date: 21/02/2026

Work in progress | 92% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.

Thaliparamba WS Section
Date: 16/02/2026

Work in progress | 92% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.

Thaliparamba WS Section
Date: 06/02/2026

Work in progress | 92% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.

Thaliparamba WS Section
Date: 28/01/2026

Work in progress | 92% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.

Thaliparamba WS Section
Date: 23/01/2026

Work in progress | 92% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.

Thaliparamba WS Section
Date: 17/01/2026

Work in progress | 92% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.

Thaliparamba WS Section
Date: 13/01/2026

Work in progress | 92% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.

Thaliparamba WS Dn EE
Date: 09/01/2026

Work in progress | 92% Completed

92% Completed.

Thaliparamba WS Section
Date: 07/01/2026

Work in progress | 92% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.

Thaliparamba WS Section
Date: 31/12/2025

Work in progress | 92% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.

Thaliparamba WS Section
Date: 22/12/2025

Work in progress | 92% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.

Thaliparamba WS Section
Date: 15/12/2025

Work in progress | 92% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.

Thaliparamba WS Section
Date: 01/12/2025

Work in progress | 92% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.

Thaliparamba WS Section
Date: 22/11/2025

Work in progress | 92% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.

Thaliparamba WS Section
Date: 13/11/2025

Work in progress | 92% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.

Thaliparamba WS Section
Date: 04/11/2025

Work in progress | 92% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.

Thaliparamba WS Section
Date: 22/10/2025

Work in progress | 92% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.

Thaliparamba WS Section
Date: 15/10/2025

Work in progress | 92% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.

Thaliparamba WS Section
Date: 03/10/2025

Work in progress | 92% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work completed. Interconnection from 800mm to 150mm DI pipe is pending.

Thaliparamba WS Section
Date: 19/06/2025

Work in progress | 89% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work started

Thaliparamba WS Section
Date: 30/04/2025

Work in progress | 85% Completed

1 LL OHSR plastering work completed and painting work in progress . 996 FHTCs Completed. 10km pipes laid out of 12km. Pipe laying in PWD road completed. inter connection work from 800mm DI pipe not started. New NH crossing at Keezhatoor vayal not started.

Thaliparamba WS Section
Date: 01/02/2025

Work in progress | 66% Completed

1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km

Thaliparamba WS Section
Date: 27/11/2024

Work in progress | 65% Completed

1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km

Thaliparamba WS Section
Date: 11/11/2024

Work in progress | 65% Completed

1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km

Thaliparamba WS Section
Date: 05/11/2024

Work in progress | 65% Completed

1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km

Thaliparamba WS Section
Date: 30/10/2024

Work in progress | 65% Completed

1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km

Thaliparamba WS Section
Date: 23/10/2024

Work in progress | 65% Completed

1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km

Thaliparamba WS Section
Date: 09/10/2024

Work in progress | 65% Completed

1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km

Thaliparamba WS Section
Date: 07/10/2024

Work in progress | 64% Completed

1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km

Thaliparamba WS Section
Date: 01/10/2024

Work in progress | 64% Completed

1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km

Thaliparamba WS Section
Date: 24/09/2024

Work in progress | 64% Completed

1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km

Thaliparamba WS Section
Date: 18/09/2024

Work in progress | 64% Completed

1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km

Thaliparamba WS Section
Date: 02/09/2024

Work in progress | 64% Completed

1 LL OHSR plastering work completed and painting work in progress . 840 FHTC's given out of 996 FHTCs. 6 km pipes laid out of 12km

Thaliparamba WS Section
Date: 26/06/2024

Work in progress | 61% Completed

1 LL OHSR plastering work completed and painting work in progress . 680 FHTC's given out of 996 FHTCs.6 km pipes laid out of 12km

Thaliparamba WS Section
Date: 11/06/2024

Work in progress | 60% Completed

1 LL OHSR plastering work completed and painting work in progress . 670 FHTC's given out of 996 FHTCs.6 km pipes laid out of 12km

Thaliparamba WS Section
Date: 06/05/2024

Work in progress | 42% Completed

1 LL OHSR structure work completed, plastering progressing . Connection work in progress 630 FHTC given out of 996 FHTCs .3 km pipes laid out of 12km

Thaliparamba WS Section
Date: 24/04/2024

Work in progress | 42% Completed

1 LL OHSR structure work completed, plastering progressing . Connection work in progress 630 FHTC given out of 996 FHTCs .3 km pipes laid out of 12km

Thaliparamba WS Section
Date: 04/04/2024

Work in progress | 41% Completed

1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km

Thaliparamba WS Dn EE
Date: 19/03/2024

Work in progress | 40% Completed

1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km

Thaliparamba WS Dn EE
Date: 14/03/2024

Work in progress | 40% Completed

1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km

Thaliparamba WS Dn EE
Date: 13/03/2024

Work in progress | 40% Completed

1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km

Thaliparamba WS Section
Date: 01/03/2024

Work in progress | 40% Completed

OH tank structure work completed, 1000m pvc & 600m DI pipe laying work are completed , OH tank drainage work under progress.

Thaliparamba WS Section
Date: 13/02/2024

Work in progress | 40% Completed

OH tank structure work completed, 1000m pvc & 600m DI pipe laying work are completed , OH tank drainage work under progress.

Thaliparamba WS Section
Date: 11/02/2024

Work in progress | 40% Completed

1000m pvc & 600m DI pipe line are completed , plastering of OHSR and drainage work are under progress

Attached images

img img

Thaliparamba WS Section
Date: 09/02/2024

Work in progress | 40% Completed

Pipe laying , plastering of OHSR and drainage work are under progress

Attached images

img img

Thaliparamba WS Section
Date: 01/02/2024

Work in progress | 40% Completed

Pipe laying , plastering of OHSR and drainage work are under progress

Attached images

img img img

Thaliparamba WS Section
Date: 19/01/2024

Work in progress | 35% Completed

Tank covering slab concrete completed , connection work in progress 500 FHTC given

Thaliparamba WS Section
Date: 12/01/2024

Work in progress | 30% Completed

Tank covering slab concrete completed , connection work in progress 470 FHTC given

Attached images

img

Thaliparamba WS Section
Date: 08/01/2024

Work in progress | 30% Completed

Tank covering slab concrete completed , connection work in progress 450 FHTC given

Thaliparamba WS Section
Date: 05/01/2024

Work in progress | 30% Completed

Tank covering slab concrete completed , connection work in progress 420 FHTC given

Thaliparamba WS Section
Date: 28/12/2023

Work in progress | 25% Completed

Tank covering slab concrete completed , connection work in progress 350 FHTC given

Attached images

img img

Thaliparamba WS Section
Date: 22/12/2023

Work in progress | 20% Completed

vertical wall concrete completed, covering slab concrete work in progress, connection work in progress 250 FHTC given

Attached images

img

Thaliparamba WS Section
Date: 18/12/2023

Work in progress | 17% Completed

Tank work Deck slab and haunch concrete completed, vertical wall concrete under progress,connection work in progress 200 FHTC given

Attached images

img img

Thaliparamba WS Section
Date: 12/12/2023

Work in progress | 15% Completed

Tank work Deck slab and haunch concrete completed, vertical wall concrete under progress,connection work in progress 150 FHTC given

Attached images

img img img

Thaliparamba WS Section
Date: 10/12/2023

Work in progress | 15% Completed

Tank work Deck slab and haunch concrete completed, vertical wall concrete under progress,connection work in progress 150 FHTC given

Attached images

img img img

Thaliparamba WS Section
Date: 09/12/2023

Work in progress | 11% Completed

Tank work Deck slab and haunch concrete completed, vertical wall concrete under progress,connection work in progress 150 FHTC given

Attached images

img img img

Thaliparamba WS Section
Date: 04/12/2023

Work in progress | 11% Completed

Tank work Deck slab and haunch concrete completed, vertical wall concrete under progress,connection work in progress 100fhtc given

Attached images

img img img

Thaliparamba WS Section
Date: 30/11/2023

Work in progress | 10% Completed

Tank work Deck slab and haunch concrete completed, vertical wall concrete under progress,connection work in progress 100fhtc given

Thaliparamba WS Section
Date: 22/11/2023

Work in progress | 10% Completed

Deck slab and haunch concrete completed, vertical wall concrete under progress

Attached images

img img img

Thaliparamba WS Section
Date: 17/11/2023

Work in progress | 7% Completed

Work in progress

Attached images

img img img

Thaliparamba WS Section
Date: 12/11/2023

Work in progress | 7% Completed

Work in progress

Attached images

img img

Thaliparamba WS Section
Date: 07/11/2023

Work in progress | 6% Completed

work in progress

Thaliparamba WS Section
Date: 30/10/2023

Work in progress | 5% Completed

Work in progress

Thaliparamba WS Section
Date: 25/10/2023

Work in progress | 5% Completed

Work in progress

Thaliparamba WS Section
Date: 19/10/2023

Work in progress | 5% Completed

Work in progress

Thaliparamba WS Section
Date: 15/10/2023

Work in progress | 5% Completed

Work in progress

Thaliparamba WS Section
Date: 10/10/2023

Work in progress | 5% Completed

Work in progress

Attached images

img img img

Thaliparamba WS Section
Date: 03/10/2023

Work in progress | 5% Completed

Work in progress

Attached images

img img

Thaliparamba WS Section
Date: 29/09/2023

Work in progress | 5% Completed

Work in progress

Thaliparamba WS Section
Date: 23/09/2023

Work in progress | 5% Completed

5%completed

Attached images

img

Thaliparamba WS Section
Date: 15/09/2023

Work in progress | 5% Completed

Work in progress

Thaliparamba WS Section
Date: 11/09/2023

Work in progress | 5% Completed

Work in progress

Attached images

img

Thaliparamba WS Section
Date: 07/09/2023

Work in progress | 5% Completed

Work in progress

Attached images

img

Thaliparamba WS Section
Date: 06/09/2023

Work in progress | 5% Completed

work in progress

Thaliparamba WS Section
Date: 03/09/2023

Work in progress | 5% Completed

Work in progress

Attached images

img img

Thaliparamba WS Section
Date: 30/08/2023

Work in progress | 4% Completed

Work in progress

Attached images

img

Thaliparamba WS Section
Date: 22/08/2023

Work in progress | 4% Completed

Work in progress

Thaliparamba WS Section
Date: 20/08/2023

Work in progress | 4% Completed

Work in progress

Thaliparamba WS Section
Date: 16/08/2023

Work in progress | 4% Completed

Work in progress

Thaliparamba WS Section
Date: 11/08/2023

Work in progress | 4% Completed

Work in progress

Attached images

img

Thaliparamba WS Section
Date: 08/08/2023

Work in progress | 4% Completed

Work in progress

Attached images

img

Thaliparamba WS Section
Date: 05/08/2023

Work in progress | 4% Completed

Work in progress

Thaliparamba WS Section
Date: 03/08/2023

Work in progress | 4% Completed

Work in progress

Thaliparamba WS Dn EE
Date: 31/07/2023

Work in progress | 4% Completed

Work in progress

Thaliparamba WS Section
Date: 24/07/2023

Work in progress | 3% Completed

3% completed

Thaliparamba WS Section
Date: 19/07/2023

Work in progress | 3% Completed

3%completed

Thaliparamba WS Section
Date: 14/07/2023

Work in progress | 3% Completed

3%completed

Attached images

img img img

Thaliparamba WS Section
Date: 13/07/2023

Work in progress | 3% Completed

3%completed

Thaliparamba WS Section
Date: 10/07/2023

Work in progress | 2% Completed

Ongoing

Thaliparamba WS Section
Date: 05/07/2023

Work in progress | 2% Completed

Work started

Thaliparamba WS Section
Date: 27/06/2023

Work in progress | 1% Completed

For Package 1- Work order issued on 18.05.2023, Agreement executed For Package 2- request letter sent by District Collector to the Land Revenue Commissioner for providing land sanctioned under public use category on lease to Taliparamba Muncipality

Thaliparamba WS Section
Date: 19/06/2023

Work in progress | 1% Completed

For Package 1- Work order issued on 18.05.2023, Agreement executed For Package 2- request letter sent by District Collector to the Land Revenue Commissioner for providing land sanctioned under public use category on lease to Taliparamba Muncipality

Thaliparamba WS Dn EE
Date: 14/06/2023

Work in progress | 1% Completed

For Package 1- Work order issued on 18.05.2023, Agreement executed For Package 2- request letter sent by District Collector to the Land Revenue Commissioner for providing land sanctioned under public use category on lease to Taliparamba Muncipality

Thaliparamba WS Dn EE
Date: 08/06/2023

Work in progress | 1% Completed

For Package 1- work order issued on 18.05.2023, For Package 2- request letter sent by District Collect to the Land Revenue Commissioner for providing land sanctioned under public use category on lease to Taliparamba Muncipality