Jal Jeevan Mission (JJM)-3rd SLSSC-Augmentaion of RWSS to Adichipuzha-Supplying & laying distribution lines with PVC,DI & GI pipes, Supplying and laying DI pumping main and gravity main and providing FHTCs at various wards in Vadasserikkara(500Nos), Pazhavangadi (330Nos), Naranammoozhy(1130Nos.), Perunadu(500Nos)panchayaths including road restoration charges. -Pipeline Work
Project |
Jal Jeevan Mission (JJM)-3rd SLSSC-Augmentaion of RWSS to Adichipuzha-Supplying & laying distribution lines with PVC,DI & GI pipes, Supplying and laying DI pumping main and gravity main and providing FHTCs at various wards in Vadasserikkara(500Nos), Pazhavangadi (330Nos), Naranammoozhy(1130Nos.), Perunadu(500Nos)panchayaths including road restoration charges. -Pipeline Work |
Project Code |
PTAJJM022215032 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission (JJM)-3rd SLSSC-Augmentaion of RWSS to Adichipuzha-Supplying & laying distribution lines with PVC,DI & GI pipes, Supplying and laying DI pumping main and gravity main and providing FHTCs at various wards in Vadasserikkara(500Nos), Pazhavangadi (330Nos), Naranammoozhy(1130Nos.), Perunadu(500Nos)panchayaths including road restoration charges. -Pipeline Work
|
Status |
On-going |
District |
Pathanamthitta |
Executing Office |
Pathanamthitta PH Dn |
AS Amount (Rs) |
343591000
|
AS Number |
G.O.(Rt) No.134/2022/WRD |
TS Amount (Rs) |
295500000 |
TS Number |
WRD/KWA-CE(SR)/EST_TS/10140/2022_26_1_1 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
8500 |
Capacity in MLD |
8.00 |
Actual Project Completion Date |
08 Aug 2024 |
Coverage |
Ranni Adichippuzh |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-3rd SLSSC-Augmentaion of RWSS to Adichipuzha-Supplying & laying distribution lines with PVC,DI & GI pipes, Supplying and laying DI pumping main and gravity main and providing FHTCs at various wards in Vadasserikkara(500Nos), Pazhavangadi (330Nos), Naranammoozhy(1130Nos.), Perunadu(500Nos)panchayaths including road restoration charges. -Pipeline Work |
Ranni Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 Feb 2024 |
Pipe supply order given. Pipe not received yet |
Ranni PH Sn - AE |
|
03 Jan 2024 |
Pipe supply order given. Pipe not received yet |
Ranni PH Sn - AE |
|
01 Jan 2024 |
Pipe supply order given. Pipe not received yet |
Ranni PH Sn - AE |
|
30 Dec 2023 |
Pipe supply order given. Pipe not received yet |
Ranni PH Sn - AE |
|
29 Dec 2023 |
Pipe supply order given. Pipe not received yet |
Ranni PH Sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
09/05/2023 |
Scheduled date of Completion of the Project |
08 Aug 2024 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
09 Feb 2023 |