Status Date Overall Project Status Project Officer Contact
13 Feb 2024 Pipe supply order given. Pipe not received yet Ranni PH Sn - AE
03 Jan 2024 Pipe supply order given. Pipe not received yet Ranni PH Sn - AE
01 Jan 2024 Pipe supply order given. Pipe not received yet Ranni PH Sn - AE
30 Dec 2023 Pipe supply order given. Pipe not received yet Ranni PH Sn - AE
29 Dec 2023 Pipe supply order given. Pipe not received yet Ranni PH Sn - AE
28 Dec 2023 Pipe supply order given. Pipe not received yet Ranni PH Sn - AE
26 Dec 2023 Pipe supply order given. Pipe not received yet Ranni PH Sn - AE
22 Dec 2023 Pipe supply order given. Pipe not received yet Ranni PH Sn - AE
01 Dec 2023 Pipe supply order given. Pipe not received yet Pathanamthitta PH Dn EE
01 Jun 2023 Agreement Executed on 01.06.2023 Pathanamthitta PH Dn EE