Jal Jeevan Mission (JJM)-3rd SLSSC-Augmentaion of RWSS to Adichipuzha-Supplying & laying distribution lines with PVC,DI & GI pipes, Supplying and laying DI pumping main and gravity main and providing FHTCs at various wards in Vadasserikkara(500Nos), Pazhavangadi (330Nos), Naranammoozhy(1130Nos.), Perunadu(500Nos)panchayaths including road restoration charges. -Pipeline Work
Project |
Jal Jeevan Mission (JJM)-3rd SLSSC-Augmentaion of RWSS to Adichipuzha-Supplying & laying distribution lines with PVC,DI & GI pipes, Supplying and laying DI pumping main and gravity main and providing FHTCs at various wards in Vadasserikkara(500Nos), Pazhavangadi (330Nos), Naranammoozhy(1130Nos.), Perunadu(500Nos)panchayaths including road restoration charges. -Pipeline Work |
Project Code |
PTAJJM022215032P1 |
Type |
Package |
Main Project |
Jal Jeevan Mission (JJM)-3rd SLSSC-Augmentaion of RWSS to Adichipuzha-Supplying & laying distribution lines with PVC,DI & GI pipes, Supplying and laying DI pumping main and gravity main and providing FHTCs at various wards in Vadasserikkara(500Nos), Pazhavangadi (330Nos), Naranammoozhy(1130Nos.), Perunadu(500Nos)panchayaths including road restoration charges. -Pipeline Work
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission (JJM)-3rd SLSSC-Augmentaion of RWSS to Adichipuzha-Supplying & laying distribution lines with PVC,DI & GI pipes, Supplying and laying DI pumping main and gravity main and providing FHTCs at various wards in Vadasserikkara (500Nos), Pazhavangadi (330Nos), Naranammoozhy(1130Nos.), Perunadu(500Nos)panchayaths including road restoration charges. -Pipeline Work |
Status |
On-going |
District |
Pathanamthitta |
Executing Office |
Ranni Sn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
295500000 |
TS Number |
WRD/KWA-CE(SR)/EST_TS/10140/2022_26_1_1 |
Technical specification |
Vadasserikkara (500Nos), Pazhavangadi (330Nos), Naranammoozhy(1130Nos.), Perunadu(500Nos)panchayaths including road restoration charges |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
01/06/2023 |
Scheduled date of Completion as per agreement |
01 Sep 2024 |
Expected date of Completion |
01/09/2024 |
Processing Dates
TS Date |
09 Feb 2023 |
Estimate Approval |
23 Feb 2022 |
NIT Approval |
23 Feb 2022 |
Tender Closing |
29 Mar 2023 |
Technichal Pre-Qualification |
29 Mar 2023 |
Price bid opening |
30 Mar 2023 |
Approval Dates
Workorder Date |
09 May 2023 |
NA |
01 Jun 2023 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Ranni PH Sn - AE |
Date: 15/06/2024 |
Work in progress | 2% Completed
Work in progress.
Ranni PH Sn - AE |
Date: 13/06/2024 |
Work in progress | 2% Completed
Work in progress.